Loading...
HomeMy WebLinkAboutCO 27 • i � Y ,..� Change Order #027 Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048) Contract Title: Rainier Ave S Improvements Change Order Number: 027 Prime Contractor: Johansen Excavating _X_ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications _ Change proposed by Contractor Endorsed by Surety Consent Contractor Attorney on Fact Date Bate Original Contract Amount: $16,032,772,44 Current Contract Amount: $16,811,088.51 Estimated Net Change This Order: $480.00 Estimated Contract Total After Change: $16,811,568.51 Approval Recommended ❑Approval Recommended esident Engineer Date Date A4Renon ecommended ?ity roved 2 City oroject Manager Nome] ento —Robert Ha 'son,RE at Z Transportation Systems Division Date e / Representing You are ordered to perform the following described work upon receipt of an approved copy of the change order: Page 1 of 2 I:Vtainier Ave File Structure\700 Construction Admin-Project ControN15 Change Orders\715.2 Individual Change Orders\715.2.027 CO 027 COR UPO Rate Increase\Change Order No 027 Cover-UPO Increase.docx n Change Order #027 fx Contract Number: CAG-11-192 Federal Aid#:STPUL-CM0167(048) Date:June 10, 2013 Page 2 of 2 THE CONTRACT IS MODIFIED AS FOLLOWS: WORK TO INCLUDE Background Since the time of bid, and execution of Change Order 21,.the City of Renton Police Officers Guild has increased the hourly rates for uniformed police officers per the Memorandum of Understanding between the City of Renton and the Renton Police Officers Guild dated 4/13/13. Therefore,the unit price for bid items A248 will be increase from$62.95 to$63.91. Description of Change Section 1-10.3(1)shall be revised to include the following hourly rate changes • The City.shall pay$63.91 per hour for actual time worked by City of Renton off-duty police officer.This revised rate shall take effect on May 16,2013. Material No new materials will be incorporated into the project via this Change. Specification Revised Section 1-10.3(1). Timeline A total of 0 additional working days will be included with this change order. Measurement&Payment Summary of Quantity Change and Added Bid Item: t a rev ou�x w 81 Mwwa§ � Amount . �.,�.�N .. . ,v A248 Uniformed Police Officer(City of HR 500 $62.95 $63.91 $0.96 $480.00 Renton)per Change Order 021 TOTAL Estimated Contract INCREASE: $480.00