HomeMy WebLinkAboutCO 22 J 1 Change Order # 022 Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048) Contract Title: Rainier Ave S(SR 167)—S Grady Way to S 2nd St Change Order Number: 022 Prime Contractor: Johansen Excavating,Inc. _X_ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications Change proposed by Contractor Endorsed by Surety Consent Contractor Attorney on Fact 2 - 2C,- 20 i3 Date Date Original Contract Amount: $16,032,772.44 Current Contract Amount: $16,881,239.43 Estimated Net Change This Order: $<96,936.12> Estimated Contract Total After Change: $16,784,303.31 <LApproval Recommended Approval Recommended esident Engineer Z/4f//3 Date T Date Approv commended ved .�.k 2 City of Renton— Derek Akesson,PE Aityofnton—Robert Hanson,�PE ae Transportation Systems Division Date Representing You are ordered to perform the following described work upon receipt of an approved copy of the change order: Page 1 of 3 \\10.21.6.1\data\RainierAve File Structure\700 Construction Admin-Project Control\715 Change Orders\7152 Individual Change Orders\7152.OXX CO West End Culvert\715.2-001 Change Order Cover.doc L Change Order #022 Contract Number: CAG-11-192 Federal Aid#:STPUL-CM0167(048) Date: February 25, 2013 Page 2 of 3 THE CONTRACT IS MODIFIED AS FOLLOWS: WORK TO EXCLUDE: Background The condition of the box culvert running beneath the intersection of Rainier Ave S and Sunset Way was not fully understood at the time of bid.Further investigation raised concerns with the Contactor and these concerns were acknowledged by the City of Renton regarding the potential structural and settlement impacts that could occur when performing the cleaning work as specified within the contract under Bid Item A94. After review,the City determined that the potential risks to achieve cleaning of the structure without structural impacts were outside the scope of the project. In addition,the decision was made that a full redesign to minimize the risk of such impacts would include critical path extensions and project delays,significantly increasing the timeline of the project,making this option impractical. The work associated with the cleaning of the 30"storm drain under Rainier Ave S.and S.Grady Way, per Bid Item A94, has also been removed from the Contract. Upon review of this scope of work,it was determined that the drain line is to be abandoned and filled per the Contract Documents.Therefore,cleaning the storm drain line at this section of the project is not necessary and once filled and abandoned per Bid Item A24,the City will still be provided the same end product upon completion. The revision of the Bid Item 94"Cleaning Existing Drainage Structure"eliminates the purpose for the west end box culvert modification(Bid Item 91),which was primarily designed to provide access to the culvert for cleaning. Therefore,this work was eliminated as well. Description of Change Delete the following the following scope of work: • Cleaning the 8-foot by 10-foot box culvert beneath Rainier Avenue S at Sunset Way(approximately 180 LF,Sediment 1-2'deep). • Box culvert modifications,west end,shall be as detailed on the Plans and in accordance with the requirements of Section 6-02 of the Standard Specifications and the Special Provisions. • Cleaning the 30-inch storm drain under Rainier Avenue at Grady Way(approximately 210 LF,Sediment 1-2'deep). Add the following scope of work: • Connect the storm lines from structures 140 and 95 to the existing structure of the box culvert at approximately STA 46+26, 129.63 LT,per Specification Section 7-05.3(3). Material No new material will be incorporated into the project as a result of this change order. Plans/Reference Rainier Avenue South(SR167), Plan Sheet 104,dated 10/3/2012,by KPG Rainier Avenue South(SR167), Plan Sheet 113,dated 10/3/2012, by KPG Specification Section 7-05 and 7-07. 0 Contract Number: CAG 11-192 STPUL-CM0167(048) 3 Timeline A total of_0_working days will be deleted by this Change Order.Adjustment to Contract duration will be per Serial Letter 012 (SL 012)and compensation for any additional days shall be via a forthcoming Change Order. Measurement&Payment Measurement and Payment shall be made by the following: WE fire hange Y �. Chan ang a Un�tPrace,� , Amount , A86 Connection to Existing Drainage Structure EA 11 13 2 $700.00 $1,400.00 A91 Box Culvert Modifications,West End LS 1 0 (1) $70,700.00 ($70,700.00) A94 Cleaning Existing Drainage Structure LS 1 .0303 0) $28,500.00 ($27,636.12) Tota redit To Contract: ($96,936.12) • CONSTRUCTION MANAGEMENT 2/22/13 Mike Dysert P.O. Box 674 Buckley,WA 98321 Project: Rainier Ave.S. (167) Improvement,S Grady Way to S 2"d St Subject: Time Impact Reconciliation PW#: CAG-11-192 Fed Aid#: STPUL-CM0167(048) Doc#: SL 012 Dear Mr. Dysert, The purpose of this letter is to summarize the time impact issues, correspondences, and meetings that have occurred throughout the life of the project. • Per SL006, an additional 3.5 days will be added to the contract due to unanticipated force account work. • Per SL006, an additional 2.5 days will be added to the contract due to work extension. • Per SL009, an additional 7.5 days will be added to the contract due to unanticipated force account work. • Per SL 011, an additional 6.5 days will be added to the contract due to work extension. • Per the 2/18/13 schedule analysis meeting, no work days will be deleted from the contract as part of the"west end culvert deletion" change order. • Per the 2/18/13 schedule analysis meeting, no time impacts will be requested or granted arising from unanticipated erosion control work performed to date. • Per the 2/22/13 schedule analysis meeting, six work days will be deleted from the contract as part of the"CTS roadway section" design change. • Per the 2/22/13 schedule analysis meeting, no alteration in contract days will be made in relation to the"concrete crosswalk deletion"change order. • Per negotiations that occurred.on 1/23/13, the compensation for an unanticipated force account work day will be at a rate of$603.41 per day and will contain all project costs associated with the extension of the project not covered by traditional force account markups. The compensation for a • 2/22/2013 work extension day will be at a rate of$2500.66 per day and will contain all costs associated with the extension of the project. Sincerely, Nathan Monroe,PE Resident Engineer cc: Bob Hanson,PE-Transportation Design Supervisor,City of Renton Derek Akesson, PE—Project Engineer,City of Renton File 2 IWY S C o � o gsx 55A F5 b � ssa � a m m N {w"• Pi °� < ^� R �m N�g8 V`1 Z — $ 33asg z h =1v A mg NN pig g- op NVA ' �a i sH ss 3o aea.t �� aaa9 m sam< N w a z soi��oo+zl vu rm wivn o z 9a z w € `a '. o c o CL Z Q , .. _ I ^ . W �\. I ♦ � �� _ rye LU O - .. --- ------ ----- LLI I _ w se Hirt wa a H -:- 3 w oZS Ix cc _ w _ m I W -- I: cc I � Q � �+ o g m co:s CIOU l/1 6.D'SNYIF,ontll_'M90\SDNVAVN\aa+O\nr saw axs ZI-u-s\-P--a-mo\says­j\s6r,-wO\wis30\"Y P�woa-ass90\r+oiwa�s���roaa\>, ff € y a m ' w LL gg �'= bbd ffi_g o d g w _ a� m <g N In t9 G O R 07 N W Ig�gS LAS-• � _x +1 ma zd� J W 2 �- O of 1 1 / .. Y F'• Z �. S .°}. - a Ila LU r / NOS I , 1 = -t •-�-- o �b $ v � i I Fo _-_ y C3 7g it Z g 9 a W Zll MHS OO+S►ViS W FMVM g OOO^OOOOO 6 Y"0:9 fIOVIL/I 6"75W-f-IDK 1575590\MNN1Ytl0\a&o\TN s331J akJ -,A0,q ,a\Nq,s3a\-w-m-j-Gm\NO1N3u\s1o3ro8d\:N