r Change Order #016
Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048)
Contract Title: Rainier Ave S Improvements
Change Order Number: 016
Prime Contractor: Johansen Excavating
_X_ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
_ Change proposed by Contractor
Endorsed by Surety Consent
Contractor Attorney on Fact
Date Date
Original Contract Amount: $16,032,772.44
Current Contract Amount: $16,908,331.68
Estimated Net Change This Order-CREDIT: $<10,597.88>
Estimated Contract Total After Change: $16,897,733.80
,Approval Recommended ❑Approval Recommended
resident EngineerT—
zAf/f3
Date Date
Afpprol)val Recommended 9ofRenton d
City of Renton–[Project Manager Name J ;ity – obert Ha so ,PE Date
-Z J 2/�3 Transportation Systems Division
Date
R+strrl±a-t�itii •
You are ordered to perjbbrm the following described Mork upon receipt q/an approved copy of the change order:
Page 1 of 2
W 0.21.6.11datalRainier Ave File structure1700 ConstrucUon Admin-Project Control1715 Change Orders1715,2 Individual Change Orders1715,2,0XX CO XX Apshalt Binder%Change
Order No 16 Cover.docx
' �- Change Order #016
Contract Number: CAG-11-192
Federal-Aid#:STPUL-CMO 7 .
Date:January 8.2012
Page 2 of 2
THE CONTRACT IS MODIFIED AS FOLLOWS:
Background
Per Special Provision 5-04.1,HMA Cl%",PG 70-22,shall be for all asphalt concrete roadway construction and reconstruction
per the Typical Roadway section details on the Plans.The Contractor requested a change to the HMA asphalt binder from PG
70-22 to PG 64-22,for all leveling lifts.After discussions with WSDOT and the City of Renton,it was determined that the use
of HMA CI'/:",PG 64-22 for leveling lifts would be appropriate to achieve maximum roadway performance and would assist
in constructability,as it is a more readily available binder.
Description of Change
Section 5-04.1.1 is revised to the following:
1. HMA Cl%", PG 70-22:For all asphalt overlay roadway construction and reconstruction per the Typical Roadway
section details on the Plans, Material Code#1.HMA CI'/:", PG 64-22:For all leveling lifts per the Typical Roadway
Section details on the Plans,Material Codes#2 and#5.
Description of Work
Contractor shall provide HMA Cl%", PG 64-22 for the 6.5"HMA base.-cnursp and the HMA prelevel,per the Typical Roadway
Section details on the Plans.
Material
Per the Contract Documents,approximately 10,000 Tons of HMA Class%", PG 64-22
Plans/Reference
Typical Sections,sheets 19 through 25,dated November 2011 and as revised,by KPG.
Timeline
A total of_0_additional working days will be included with this change order..
Measurement&Payment
Payment shall be made by the following:
PieYlous SNew tlptt �
rd item Descrl ton n an it'Pr
L
"'Unit tity n ice Price ' Ch n$ Amount
MA Class Y::"PG64-22 TN 8,240 $89.40 $88.34 $727,921.60
A45 HMA for Preleveling Class W PG64-22 T $80.30
A..........
$79.24 $139,303.92
Estimated Total Cost—Bid Items A44&A45: $867,225.52
a
Original Contract Total Cost—Bid Items A44&A45: $877,823.40
TOTAL CONTRACT CREDIT: $10,597.88
Johansen Excavating Lakeside Industries,INC,