Change Order #014
Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048)
Contract Title: Rainier Ave S Improvements
Change Order Number: 014
Prime Contractor: Johansen Excavating
_X_ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
Change proposed by Contractor
Endorsed by Surety Consent
Contractor Attorney on Fact
rZ - i/ - '201-2-
Date Date
Original Contract Amount: $ 16,032,772.44
Current Contract Amount: $16,345,871.79
Estimated Net Change This Order: $32,496.60
Estimated Contract Total After Change: $16,378,368.39
kJ AApproval Recommended 0 Approval Recommended
esident Engineer
t2/tt/1'4,
Date Date
Approv Recommended pr 4-Robert
t���2
�D e` -
City of Renton—[Project Manager Name] Jityof ReH nson,PE D e
121 3 z Transportation Systems Division
Date / Representing
You are ordered to perform the following described work upon receipt of an appnvved cupy of the change order.
Page 1 of 3
CADocuments and Settings\kfaasse\Local Settings\Temporary Internet Files\Content.Outlook\JBH19U3H\Change Order No 14 Cover.docx
Change Order #014
Contract Number: CAG-11-192
Federal Aid#:STPUL-CM0167(048)
Date: December 5, 2012
Page 2 of 3
THE CONTRACT IS MODIFIED AS FOLLOWS:
Background
Per the original plan design,the Joint Utility Trench (JUT)was to be installed under the BNSF Railroad trestle at depth of
approximately 4'to 6'.This section of JUT would also go through possible contaminated soils and beat a depth where
dewatering would be highly likely. To avoid these contaminated soils and other potential utility conflicts, it was decided by
the Utilities, City, and the Contractor,that the best alternative would be to shallow the JUT to a minimum depth 16".
So as to avoid delay through the design process and to be able to better handle potential conflicts in the field,it was decided
by all parties,that a design build approach tracked via Force Account was preferred.
Description of Change
Per Field Work Directive 006,the joint utility trench will be field fit from approximately 31+00 to 33+50.The installation of the
trench was per the requirements of Puget Sound Energy's"Trench Dimensions 6790.0130",page 3 and 4,dated 7/1/2011.
The installation of conduit and backfill for this section of trench was tracked via the applicable bid items and has been paid to
date.All extra work associated with this design built change was approved and tracked by the Construction Management field
staff according to WSDOT Standard Specification 1-09.6.All work, materials,and measurements were in accordance with the
provisions of the Contract for the type of construction involved, unless stated otherwise in this Change Order.
Description of Work
Field fit the installation of the joint utility trench to the west side of the existing sidewalk from approximately STA.31+00 to
approximately STA 33+50, as discussed during the 7/9/2012 weekly progress meeting.In areas where a minimum cover of
12-inches is installed, provide 3000 psi full strength concrete encasement.
The installation of the trench was per the requirements of Puget Sound Energy's"Trench Dimensions 6790.0130", page 3 and
4, dated 7/1/2011. Minimum separation in this area shall be 6-inches. Per the direction of the Resident Engineer,the
Contractor located and excavated an existing power vault before installation of this section of trench began.
In addition,a new 12"water main and storm drain had to be installed under the now shallow JUT,whereas the original design
was called for the water main and storm drain above this section of JUT.The additional time to go make this adjustment was
tracked via Force Account.
Material
32 cubic yards of 3000 psi Full Strength Concrete for encasement.
Plans/Reference
Puget Sound Energy's"Trench Dimensions 6790.0130",page 3 and 4,dated 7/1/2011.
Timeline
The original design per the Contract plan set was to install the joint utility trench at a depth of approximately 4'to 6'from STA
31+00 to 33+50.The time to construct this portion of the Joint Utility Trench was offset by eliminating the proposed deeper
trench section,eliminating off-haul of contaminated soils,and the elimination of dewatering activities. No time impacts were
realized for this scope of work.
A total of—0—additional working days will be included with this change order.
Contract Number: CAG 11-192 •
STPUL-CM0167(048) 3
Measurement& Payment
Payment shall be made by the following:
v < _ wlgSCri ion . "3 `, ?►fit t$ harg > ' gA. oiut
C42 FWD 006—Shallowing JUT LS 0 1 1 $29,677.26 $29,677.26
Total Cost: $29,677.26
WSST For Schedule'C': $2,819.34
TOTAL CONTRACT ADD: $32,496.60
Measurement for this scope of work was according to WSDOT Standard Specification 1-09.6;tracked and approved on the
attached Force Account Sheets.
Attached:
800.23(A) 7/19/2012 $2,081.10
800.23(6) 7/20/2012 $1,556.80
800.23(C) 8/02/2012 $3,896.21
800.23(D) 8/06/2012 $7,160.07
800.23(E) 8/09/2012 $3,887.57
800.49 8/20/2012 $4,492.45
800.71 10/10/2012 $3,229.07
800.53 11/15/2012 $3,373.99
TOTAL COST: $29,677.26