CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 10-040 STONEGATE LIFT STATION CONVEYANCE CIN OFREN�O6 # 3
IMPROVEMENTS JUN 29 2010
CONTRACTOR: SHORELINE CONSTRUCTION CO.
RECEIVED
SUMMARY OF PROPOSED CHANGE: CITY CLERK'S OFFICE
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price
048. NEW ITEM: 1-1/2"" Deep HMA Class%'Overlay. This item is for the SY 12,150.4 $8.00 $97,203.20
Modified Overlay Plan in the Stonegate Neighborhood.
049. NEW ITEM:Adjust Utility Covers in the Stonegate Neighborhood as a result LS 1 $44,850.00 $44,850.00
of the Modified Overlay Plan in the Stonegate Neighborhood.
Sub Total $142,053.20
Sales Tax (9.5%) $13,495.05
Total $155,548.25
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$875,888.86 $958,915.91 $155,548.25 $1,114,464.16