HomeMy WebLinkAboutCO 2 CITY OF RE'NTON Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 10-054, West Hill Reservoir Recoat and Upgrade 2010 C.O.# 2 (WTR 27-3488) CONTRACTOR: Coatings Unlimited, Inc. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment and materials, subcontracts,B&O Tax,bonding, and insurance for: Change Order No. 2 For the work identified in Coatings Unlimited Change Order Proposal#4 for the caulking of all interior roof plate lap joints and all interior roof beam/roof plate connections. i A total of 1 additional working day is granted by this change order, I Lump Sum Cost $3,284.40 Lump Sum Total $ 3,284.40 9.5% Sales Tax $ 312.02 Total CO#1 $ 3,596.42 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED CHANGE COMPLETION DATE AFTER COMPLETION DATE COMPLETION DATE CHANGE i January18,2011 February 8,2011 1 February 9,2011 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE $385,303.13 $399,511.55 $3,596.42 $403,107.97 SIGNATURES: Contractor: Date: ri Project Engineer: Date: -S LO t j Approved By: U�/ Q�t� Date: 31 20 tt " (Utility Systems Manager) RECEIVED FEB 0 ,gra t u," .,..t, ;nw ; "YSTEMC H:\File Sys\WTR-Drinking Water Utility\WTR-27-Water Project Files\WTR-27-3488 Recoat West Hill Reservoir2009\ContractoPayrnent\ChaugeOrderNo.2-OfficiahChangeOrder2.doc