HomeMy WebLinkAboutCO 4 *4%W CITY OF RENTON
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 10-087 STONEGATE LIFT STATION REPLACEMENT C.O.# 4
CONTRACTOR: SHORELINE CONSTRUCTION CO.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price
071. NEW ITEM:Additional Materials and Work by Advance Power, Inc(electrical LS 1 $3,841.15 $3,841.15
subcontractor)and Systems Interface to reprogram the Motor
Control Center and modify the City-supplied telemetry panel to work
with the new radio antenna.
(Shoreline Construction Co. Invoice dated 2/28/2012)
072, NEW ITEM:Additional Work and materials to upgrade the flexible coupling LS 1 $2,795.43 $2,795.43
adapters in the valve vault.
(Shoreline Construction Co. Invoice dated 3/5/2012)
Sub Total $6,636.58
Sales Tax (9.5%) $630.48
Total $7,267.06
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$1,213,270.95 $1,259,948.96 $7,267.06 $1,267,216.02
SIGNATURES:
Contractor: Date:
Project E (neer: Date: 3 Z-7
Approved By: Date:
(U ie stem rector)
H:FileSys\WWP-Wastewater\WWP-27-3473\CO-4-Stonegate Lift Station Replacement/JDH