CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 10-087 STONEGATE LIFT STATION REPLACEMENT C.O.# 2
CONTRACTOR: SHORELINE CONSTRUCTION CO.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price
059. NEW ITEM:Additional City of Renton Requested Landscaping and Irrigation LS 1 $5,843.85 $5,843.85
(Shoreline Construction Co. Invoice dated 11/03/2011)
Sub Total $5,843.85
Sales Tax (9.5%) $555.17
Total
$6,399.02
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$1,213,270.95 $1,223,127.92 $6,399.02 $1,229,526.94
SIGNATURES:
Contractor: Date:
Project E ineer: Date: /iIdlelli
Approved By: Date:
ysi t'bAiA rector)
H:FileSys\W W P-W astewater\W W P-27-3473\CO-2-Stonegate Lift Station Replacement/J DH