HomeMy WebLinkAboutCO 1 CITY OF RENTON 1*0e CAg-10-087, CO #1-11 Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 10-087 STONEGATE LIFT STATION REPLACEMENT C.O.# 1 CONTRACTOR: SHORELINE CONSTRUCTION CO. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price 058. NEW ITEM:Lake Washington Blvd N Emergency Sewer Repair LS 1 $9,001.78 $9,001.80 (Shoreline Construction Co. Invoice dated 5/24/2011) Sub Total $9,001.80 Sales Tax (9.5%) $855.17 Total $9,856.97 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $1,213,270.95 $1,213,270.95 $9,856.97 $1,223,127.92 SIGNATURES: Contractor: Date: $- Project Engineer: Date: Approved By: Z, ✓ Date: (Utilities System irector) H:FileSys\WWP-Wastewater\WWP-27-3473\CO-1-Stonegate Lift Station Replacement/JDH