HomeMy WebLinkAboutCO 3 0 CITY OF RENTON 0 CAG-10-142, CO #3-12
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 10-142 WESTVIEW LIFT STATION UPGRADES C.O.# 3
CONTRACTOR: FIRST NATIONAL INSURANCE COMPANY OF AMERICA
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price
007. NEW ITEM: Remove and Reset Valve Vault LS 1 $2,541.30 $2,541.30
(Omega Contractors, Inc. letter of Dec.22,2011)
008. NEW ITEM: Provide Additional Crushed Rock for Valve Vault LS 1 $872.41 $872.41
(Omega Contractors, Inc. letter of Dec.22,2011)
009. NEW ITEM:Grout voids around Valve Vault LS 1 $182.56 $182.56
(Omega Contractors, Inc. letter of Dec.22,2011)
010. NEW ITEM: Replace Upper Section of Wetwell LS 1 $1,139.04 $1,139.04
(Omega Contractors, Inc. letter of Dec.22,2011)
011. NEW ITEM: Remove Buried Concrete Mass LS 1 $1,659.76 $1,659.76
(Omega Contractors, Inc. letter of Dec.22,2011)
012. NEW ITEM: Change force main materials from PVC to DI LS 1 $1,426.03 $1,426.03
(Omega Contractors, Inc. letter of Dec.22,2011)
013. NEW ITEM:2-6"Conduits to replace"Fibercrete"Cable Trench LS 1 $661.87 $661.87
(Omega Contractors, Inc. letter of Dec.22,2011)
014. NEW ITEM: Provide two start capacitors to match new pumps LS 1 $191.58 $191.58
(Omega Contractors, Inc. letter.of Dec.22,2011)
015. NEW ITEM:Additional Pit Run LS 1 $1,875.50 $1,875.50
(Omega Contractors, Inc. letter of Dec.22,2011)
016. NEW ITEM: Saw Cut and Remove Additional Asphalt LS 1 $148.16 $148.16
(Omega Contractors, Inc. letter of Dec.22,2011)
017. NEW ITEM: Provide and Install Additional Intrinsically Safe Barrier LS 1 $1,162.47 $1,162.47
(Omega Contractors, Inc. letter of Jan.24,2012)
Sub Total $11,860.68
Sales Tax (9.5%) $1,126.76
Total $12,987.44
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$101,835.00 $122,300.06 $12,987.44 $135,287.50
SIGNATURES'
Contractor: Date: 03 Z8 f L
Project Engineer: Date: 29
Approved By: Date:
s S stem Director)
H:FileSys\W W P-W astewater\W W P-27-3536\CO-3-Westview Lift Station Upgrades/JDH