CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 09-157,2009 Pump Station Electrical Upgrades C.O.# 1
(WTR 27-3458)
CONTRACTOR: EC Company
SUMMARY OF PROPOSED CHANGE:
Provide all labor,equipment and materials, subcontracts,B&O Tax,bonding, and insurance for:
Change Order No. 1
Which includes the installation of a vacuum gauge on the new 750'KVA transformer to be installed at the
Mount Olivet Reservoir&Pump Station for the lump sum of$342.91;
No additional worldng days are granted by this change order.
Lump Sum Cost $342.91
' Lump Sum Total $342.91
9.5%Sales Tax $ 32.58
Total CO#1 $375.49
ORIGINAL CONTRACT CURRENT CONTRACT. ESTIMATED CHANGE COMPLETION DATE AFTER
COMPLETION DATE COMPLETION DATE CHANGE
June 21,2010 June 21,2010 0 June 21,2010
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$94,519.31 $94,519.31 $375.49 $94;894.80
SIGNATURES
Contractor ;' ., -; — Date:
Project Engineer:
Date: n S
�l ►4 Date:
�, 6 25 t7
Approved By: Gx C� tu.ility sy M-aser)
j
I
i
r,-:-va. 111—r W1tt%AWTR-27-Water Project Files\WTR-27-3458-ReplaceTransfomiers\COnstructionPeriod\ChangcOrderl-DOC