Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 09-171— 2009 Earlington Water and Sewer Improvements Project . C.O.# 5
CONTRACTOR: 'Laser Underground.and Earthworks, Inc.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
.ITEM Additinnal Quantities Under This Chanee Order Unit Quantity Unit Total Price
COS Additional work for Sewer Utility Change in site LS 1 $31,276.55 $31,276.55
conditions due to poor soils and excessive groundwater,
causing trench collapse.
Additional work for Water Utility: Installing 1" water LS 1 $4,692.00 $4,692.00
service at one address on SW 3rd Pi, and four addresses on
Earlington Ave. SW.
Additional costs due to delay of work from crossing LS 1 $19,077.02 $19,077.02
mislocated/missing utilities.
Subtotal
9.5% Sales Tax $5,229.33
Total $60,274.90
ORIGINAL CONTRACT
AMOUNT
CURRENT CONTRACT
AMOUNT
ESTIMATED NET
CHANGE THIS ORDER
ESTIMATED CONTRACT
TOTAL AFTER CHANGE
$2,162,511.12
$2,342,980.69
$60,274.90
$2,403,255.59
Cost Allocation
Water Utility
425.455170,018.595,34.63.000
$15,582.41
Sewer Utility
426.465405.018.595.35.63.000
$44,692.49
SIGNATURES:
Contractor:
Project Engineer:
-Approved By:
Date:
Date: /
bate: l�