HomeMy WebLinkAboutBurnett Project - Addendum No 22Burnett Avenues S Sidewalk & Utilities Replacement Project Addendum No. 2
Page 1 of 2
BURNETT AVENUE S SIDEWALK & UTILITIES REPLACEMENT PROJECT
CITY PROJECT NO. 4244
ADDENDUM NO. 2
DATE OF ADDENDUM ISSUE: September 25, 2023
BID DUE DATE: September 26, 2023
DATE OF BID OPENING: September 26, 2023
NOTE TO ALL PLANHOLDERS:
This Addendum No. 2, containing the following revisions, additions, deletions, and/or clarifications, is
hereby made a part of the Plans and Contract Provisions (Contract Documents) for the above-named
project. Bidders shall take this Addendum into consideration when preparing and submitting their bids.
Bidders shall acknowledge receipt and acceptance of this Addendum No. 2 in the space provided on the
Proposal Signature Page or by signing in the space provided below and submitting the signed addendum
with the bid package. Failure to provide this written acknowledge may result in disqualification of the Bidder’s
submittal.
SCHEDULE OF PRICES
· The attached form “Proposal for Incorporating Recycled Materials into the Project” included
with this Addendum no.2 must be completed and submitted as part of the bid.
ALL OTHER REQUIREMENTS OF THE CONTRACT DOCUMENTS REMAIN IN EFFECT.
Sincerely,
Abdoul Gafour
Water Utility Engineering Manager
City of Renton
Receipt acknowledged, and conditions agreed to this _____ day of ________, 2023
Bidder _______________________________
Signature
APWA-WA Division 1 Committee rev. 1/8/2016
Proposal for Incorporating Recycled Materials into the Project
In compliance with a new law that went into effect January 1, 2016 (SHB1695), the Bidder shall
propose below, the total percent of construction aggregate and concrete materials to be
incorporated into the Project that are recycled materials. Calculated percentages must be within
the amounts allowed in Section 9-03.21(1)E, Table on Maximum Allowable Percent (By Weight)
of Recycled Material, of the Standard Specifications.
Proposed total percentage: _____________________________ percent.
Note: Use of recycled materials is highly encouraged within the limits shown above, but does
not constitute a Bidder Preference, and will not affect the determination of award, unless two or
more lowest responsive Bid totals are exactly equal, in which case proposed recycling
percentages will be used as a tie-breaker, per the APWA GSP in Section 1-03.1 of the Special
Provisions. Regardless, the Bidder’s stated proposed percentages will become a goal the
Contractor should do its best to accomplish. Bidders will be required to report on recycled
materials actually incorporated into the Project, in accordance with the APWA GSP in Section
1-06.6 of the Special Provisions.
Bidder:
Signature of Authorized Official:
Date:
Addendum No. 2