Lesinski, David <david.lesinski@pse.com>Mon, Dec 5, 2022 at 2:38 PM
To: john@kplusarchitects.net
Hi, John. I can only provide and so can a project manager an estimate. Per my note below:
“The amount noted on this email is an estimated cost; however PSE’s Schedule 85 line extension tariff requires
customers to pay the actual cost of construction. PSE will determine the actual cost of the job once construction is
complete. If the actual cost of the job is more than 10% above or below the estimated cost, an additional billing or
refund will result to account for the difference. If the scope of work changes from “details known at this time,” this
estimate will become void until an updated estimate is obtained.”
This is our protocol.
Thanks.
Dave Lesinski
Senior Engineering Specialist
Customer & System Projects
PUGET SOUND ENERGY
253-395-6911 tel
253-905-4592 cell
david.lesinski@pse.com
www.pse.com
KJ7LVF
The amount noted on this email is an estimated cost; however PSE’s Schedule 85 line extension tariff requires
customers to pay the actual cost of construction. PSE will determine the actual cost of the job once construction is
complete. If the actual cost of the job is more than 10% above or below the estimated cost, an additional billing or
refund will result to account for the difference. If the scope of work changes from “details known at this time,” this
estimate will become void until an updated estimate is obtained.
5/24/23, 3:55 PM K+ Architects Mail - RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
https://mail.google.com/mail/u/0/?ik=c1066a72f8&view=pt&search=all&permthid=thread-f:1731305416749944642%7Cmsg-f:1751416797623566322&…2/6
From: john@kplusarchitects.net <john@kplusarchitects.net>
Sent: Monday, December 5, 2022 1:49 PM
To: Lesinski, David <david.lesinski@pse.com>
Cc: john@kplusarchitects.net
Subject: RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
CAUTION - EXTERNAL EMAIL
Phishing? Click the PhishAlarm "Report Phish" button.
Hello David
I heard back from the City and they want an itemized estimate. Are you able to put that together?
Thank you,
John Kay | Principal Architect
k+ Architects
10317 8th Ave NE
Seattle, WA 98125
C: (509) 336.9200
From: Lesinski, David <david.lesinski@pse.com>
Sent: Monday, November 21, 2022 9:09 AM
To: john@kplusarchitects.net
Subject: FW: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
Hi, John. Per our conversation I will be your contact for rough ballpark (feasibility) until you have a plan, then we will
work on the app and site plan and get you to a pm.
For now, for burying existing PSE overhead 3-phase feeder along SE Renton Maple Valley Rd will be around $350K to
$400K a foot plus customer will additionally pay for all excavation, trenching, backfill, restoration, permits and
easements.
5/24/23, 3:55 PM K+ Architects Mail - RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
https://mail.google.com/mail/u/0/?ik=c1066a72f8&view=pt&search=all&permthid=thread-f:1731305416749944642%7Cmsg-f:1751416797623566322&…3/6
If the city makes you underground the existing overhead single phase on the property (running north to south) the
rough ballpark estimate will be around $185 a foot plus customer will additionally pay for all excavation, trenching,
backfill, restoration, permits and easements.
Thanks much.
Dave Lesinski
Senior Engineering Specialist
Customer & System Projects
PUGET SOUND ENERGY
253-395-6911 tel
253-905-4592 cell
david.lesinski@pse.com
www.pse.com
KJ7LVF
The amount noted on this email is an estimated cost; however PSE’s Schedule 85 line extension tariff requires
customers to pay the actual cost of construction. PSE will determine the actual cost of the job once construction is
complete. If the actual cost of the job is more than 10% above or below the estimated cost, an additional billing or
refund will result to account for the difference. If the scope of work changes from “details known at this time,” this
estimate will become void until an updated estimate is obtained.
From: Construction - South King Electric -- mail -- <custconstelecsking@pse.com>
Sent: Monday, November 21, 2022 7:50 AM
To: Lesinski, David <david.lesinski@pse.com>
Subject: FW: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
Good Morning Dave,
Happy Monday, Are you able to help John with his questions? I had referred him to CCS but they don’t have that
information.
Thank you
5/24/23, 3:55 PM K+ Architects Mail - RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
https://mail.google.com/mail/u/0/?ik=c1066a72f8&view=pt&search=all&permthid=thread-f:1731305416749944642%7Cmsg-f:1751416797623566322&…4/6
Jerri L. Giemza She/Her
Administrative Specialist
PUGET SOUND ENERGY
C&SP South King Electric
253-234-6420 or 82-6420
Jerri.Giemza@pse.com
www.pse.com
From: john@kplusarchitects.net <john@kplusarchitects.net>
Sent: Thursday, November 17, 2022 1:44 PM
To: Construction - South King Electric -- mail -- <custconstelecsking@pse.com>
Cc: john@kplusarchitects.net
Subject: RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
CAUTION - EXTERNAL EMAIL
Phishing? Click the PhishAlarm "Report Phish" button.
Hello Jerri
Do you know how much PSE would charge for burying 5 power poles? I just need a Rough Order Magnitude. What is
the price PSE charges per linear foot?
Thank you!
John Kay | Principal Architect
5/24/23, 3:55 PM K+ Architects Mail - RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
https://mail.google.com/mail/u/0/?ik=c1066a72f8&view=pt&search=all&permthid=thread-f:1731305416749944642%7Cmsg-f:1751416797623566322&…5/6
k+ Architects
10317 8th Ave NE
Seattle, WA 98125
C: (509) 336.9200
From: Construction - South King Electric -- mail -- <custconstelecsking@pse.com>
Sent: Wednesday, April 27, 2022 3:52 PM
To: john@kplusarchitects.net
Subject: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
April 27, 2022
Dear John,
Thank you for contacting Puget Sound Energy. In order to start working and designing your project we need a couple
more pieces of project information from you.
The following information is required for design and permitting submissions:
• Application: Please complete attached application.
• Site plan: A CAD drawing will be required for your project (see below for requirements). This drawing may be the
Civil Drawings submitted for building permit.
The CAD drawings for your project should include the following information:
• Property Lines, Roads, Lots & Building footprints (include driveways if planned)
• Water Main (with stub locations )
• Storm Drainage
• Sewer Main & Profile
• Cross Section for Roads
• Surveyed location of any existing facilities (vaults, poles, homes, fences, construction)
5/24/23, 3:55 PM K+ Architects Mail - RE: PSE Request for Project Information- 15711 152ND AVE SE # MAIN RENTON
https://mail.google.com/mail/u/0/?ik=c1066a72f8&view=pt&search=all&permthid=thread-f:1731305416749944642%7Cmsg-f:1751416797623566322&…6/6
These documents can be returned to me electronically. If at any time you have questions about the application process,
my contact information is provided below.
In the event you are unsure of specific requirements complete as much as possible and a Project Manager will reach out
to you to obtain all information. Load information and a physical address assigned from the city and county will be
required before we are able to precede to the design process.
Project ID#: 512887597
Customer Construction Website
Thank You
Jerri L. Giemza She/Her
Administrative Specialist
PUGET SOUND ENERGY
C&SP South King Electric
www.pse.com