HomeMy WebLinkAboutM_Additional Scope Details_Sunset Undergrounding_231120_v1.pdfFrom: Chau, Jenny <Jenny.Chau@pse.com>
Sent: Thursday, November 2, 2023 9:30 AM
To: Rydberg, Corrie
Subject: FW: 101137749-SUNSET GARDEN SCH 73-EQUIPMENT AND OUTAGE TIME
LINE
Attachments: Approved 101137749-SUNSET GARDENS- SCH 73-FINAL.pdf
SEE BELOW:
From: Chau, Jenny
Sent: Tuesday, October 24, 2023 8:52 AM
To: Justin T. Johnson <JTJohnson@Rentonwa.gov>
Cc: Rydberg, Corrie <Corrie.Rydberg@pse.com>
Subject: 101137749-SUNSET GARDEN SCH 73-EQUIPMENT AND OUTAGE TIME LINE
Hello Justin,
Here is the list of equipment and a rough time line for the outage in about a week time period. Please
help me anyway you can with the night work noise variances that we requested! This job is for the
Renton housing authority and we want to help them move forward as much as we can.
At idle in DB at operating RPM in DB
Foreman truck 1ton 72 95
Line truck 91 95
Bucket truck 85 95
Vactor truck 90 98
Time line
3 days of prep 8hrs.+ day time work
1st night cut over at P04 ( grocery outlet ) & P05 ( 2806 NE 10 ST ) (6 hours)
2nd night cut over of old j-box to new J03 pull out and re-route pipes to J03 (8 hours)
Pull new cable jack in the box , Italian restaurant remove temp 3 ph xfmr
It would be nice to take the 1ph pri term cable ABH661 from pole 318548-166763
Reroute to J03 instead of P04
3rd night take outage on new 3 ph term at P01 outage to all customer south 2nd time & Safeway 1st &
only (8 hours)
time and reframe pole with tangent wing arm moved up, lateral 3ph arm lower feed south to Safeway &
3ph
term reframed and cut down all OH south to P04 & top poles.
Crew may need 1 half day to remove 3ph OH and top pole’s depending on time line for outage / work
hours
The night of 3rd night job.
If you have any questions, please let me know!
Thank you,
Jenny Chau
Project Coordinator – South King Electric
Customer & System Projects, NCC – PSE
Work: 253-208-9480
Desk: 253-234-6403
jenny.chau@pse.com