HomeMy WebLinkAboutChange Order - 1Change Order No. 1 Contract Title: Downtown Core Streetscape PH2 Williams Ave S Contract No. CAG-23-241 Page 1 of 3 Change Order No. 1 Contract Title:Downtown Core Streetscape Phase II Williams Ave S Contractor:Active Construction, Inc. Contract No. : CAG-23-241 Federal Aid No. : King County CDBG Project No.: C19352 Ordered by Engineer Force Account Proposed by the Contractor (VECP) Bid Item Unilateral Lump Sum Amount Working Days Original Contract: $1,109,109.00 40 Current Contract: $1,109,109.00 40 Estimated Net Change This Order: $76,000.00 0 New Contract: $1,185,109.00 40 Prepared By: Issued By: City of Renton Project Manager Date Director (City of Renton Development Engineering) Date Reviewed By: Consent By: Engineer of Record Date Surety (Greater than 25% cost and/or 20% time increase) Date Reviewed By: Endorsed By: Administrator (City of Renton Community & Economic Development) Date Contractor Date Reviewed By: Executed By: City Attorney Date City of Renton Mayor Date CAG-23-241, CO #1-23 12/7/2023Approved by Cheryl Beyer via email 11/15/2023 ___________________________________ Jason Seth, City Clerk Change Order No. 1 Contract Title: Downtown Core Streetscape PH2 Williams Ave S Contract No. CAG-23-241 Page 2 of 3 THE CONTRACT IS MODIFIED AS FOLLOWS: Description of Change: Street lighting cost adjustment to Bid Item #41 (Illumination System Along Williams Avenue, Complete) for using different manufacturer than was proposed in the original bid. Bid Item #41 to be increased from $311,000.00 to $387,000. Reason for Change: 1.Build America Buy America Act (BABAA) requirements per special provision 1-06 of the Contract Volume 1 requires that all steel and iron used in the project are produced in the United States and all construction materials are manufactured in the United States . During the procurement process of the street lights it was discovered that the original bid fixtures do not meet the BABAA requirements and the vendor did not have alternative. New manufacturer can meet the BABAA requirements. 2.The original street light manufacturer has a lead time of 35 weeks to deliver the street lights whereas the new manufacturer has a lead time of 15-20 weeks. The City s current CDBG grant contract #6242242 with King County terminates on April 30, 2024. Amending the street light lead time will provide delivery prior to the contract termination date. 3.Lead time reductions will result in less construction impacts to the downtown core and will reduce the time of having temporary lighting on the street. Affects DBE Work: Yes No Explain how this Change Order affects DBE work. Materials: No new or additional materials are proposed. Plans: N/A Equitable Adjustment: This Change Order does/does not include an equitable adjustment per Section 1-09.4 of the 2023 WSDOT/APWA Standard Specifications. There are no reductions in cost to the project. Change Order No. 1 Contract Title: Downtown Core Streetscape PH2 Williams Ave S Contract No. CAG-23-241 Page 3 of 3 Extension of Time: The Time for Completion is extended 0 Working Days. Sections 1-04.4 and 1-04.5 of the 2023 WSDOT/APWA Standard Specifications shall govern this Change Order. The Work of the referenced Contract is modified to include the changes detailed herein. The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change.