1. WASHINGTON STATE DEPARTMENT OF TRANSPORTATION UPDATE
a) Presentation
If you would like to attend this week's meeting remotely, you can do so by going to
https://us02web.zoom.us/j/86753290028?pwd=M2pOc09HWWNrY05uVnlIWnpGS1E4UT09
Zoom Meeting ID: 867 5329 0028, Passcode: 881839
You can call through Zoom at (253) 215-8782 and use the Meeting ID.
I-405, Renton to Bellevue
Widening and Express Toll
Lanes Project
Project Update
January 2024
AGENDA ITEM #1. a)
Agenda
2
•Project overview
•2023 progress overview
•2024 planned work
•Renton Ave. closure
•Construction details
•Intended detour routes
•Questions AGENDA ITEM #1. a)
Major multimodal project elements
•New capacity and interchange improvements
•Dual express toll lane system
•Direct access ramps
•Northeast 44th Street in Renton
•112th Avenue Southeast
•Main Street Bridge replacement
•Bus Rapid Transit infrastructure (with Sound Transit)
•Eastrail segments (with King County)
•Coordination with Mountains to Sound Greenway trail
Status:
•Construction work along the corridor on-going
3
Renton to Bellevue project overview
AGENDA ITEM #1. a)
Northeast 44th Street Interchange progress
Work has focused on the Northeast
44th Street interchange:
•New northbound on-ramp
•New northbound bridge and
alignment
•Regrading east side of NE 44th St.
•Culvert replacement
4AGENDA ITEM #1. a)
I-405 Culvert Replacement
AGENDA ITEM #1. a)
I-405 traffic shift, weekend of Sept. 9-10,
2023
6AGENDA ITEM #1. a)
I-405/112th Avenue SE/Lake WA Blvd. girder
setting
7AGENDA ITEM #1. a)
2024 Corridor Construction
8AGENDA ITEM #1. a)
2024 Renton to Bellevue construction
Upcoming work includes:
•Regrading the southbound Coal Creek
Parkway off-ramp
•Ongoing work at NE 44th Street including
potential roundabout construction
•Bridge widening at North Southport
•Bridge widening Sunset Boulevard in
Renton
•John’s Creek drainage at Houser Way
•Renton Avenue bridge extension
9AGENDA ITEM #1. a)
10
Work during this closure period will include:
•Installation of falsework to support the extension of the existing bridge
•Placement of forms, rebar, and concrete to extend the existing bridge
•Installation of new retaining walls
•Installation of new drainage, paving, and road striping
Extent:
Full closure of Renton Ave S from just west of S 3rd Street to just east of the Cedar River
Trail access road to start as soon as April 1, 2024.
300-day full closure of Renton Ave S bridge
Expected impacts:
•Most of the work throughout this closure will be at or below the typical noise of traffic from
the highway and scheduled mostly during the day
•Night work will include closing the freeway during the primary installation of falsework AGENDA ITEM #1. a)
Overview
•Preliminary work includes the securing of the abutment on the slope
•The bridge will be held up by temporary bracings under the Exit 4 sign
•Soil will need to be excavated before construction of a new western abutment
11
New bridge
span
Existing bridge
span
Area of
excavation
Renton Ave. NE
Southbound
I-405
Northbound
I-405 AGENDA ITEM #1. a)
Cross-section view
12
Partial demolition of
existing wall, and
excavation for
construction of new pier 1
New pier 1
Existing pier 1
Existing pier 2
Existing pier 3
Existing wall,
to remain
Temporary
concrete
barrier during
construction
Temporary vertical
support
Alternative
temporary support
AGENDA ITEM #1. a)
Detour route
12
Westbound Detour Route:
•Traffic headed eastbound on Renton Ave S
will be rerouted southward onto Cedar Ave
S, to then take a right onto Main Ave S.
Eastbound Detour Route:
•Traffic headed westbound on Renton Ave S
will be rerouted southward onto Main Ave S,
where they can then take a left onto Cedar
Ave S and use the road to cross over I-405.AGENDA ITEM #1. a)
Questions?