HomeMy WebLinkAboutR-410936CONSTRUCTION PROVISIONS: (REVISED 05/16/11)
4. CONNECTION TO EXISTING WATER SYSTEM
1. STANDARD SPECIFICATIONS:
ALL WORK, MATERIALS AND TESTING SHALL CONFORM TO THE STANDARDS OF SOOS CREEK WATER & SEWER DISTRICT AND THE "STANDARD
SPECIFICATIONS FOR ROAD, BRIDGE, AND MUNICIPAL CONSTRUCTION", CURRENT EDITION, AS PREPARED BY THE WASHINGTON STATE DEPARTMENT
OF TRANSPORTATION, AND HEREINAFTER REFERRED TO AS THE "STANDARD SPECIFICATIONS," EXCEPT AS HEREIN MODIFIED.
2. TRENCH EXCAVATION, BEDDING AND BACKFILL
ALL WORK WITHIN THE RIGHT-OF-WAY SHALL COMPLY WITH ALL PERTINENT PERMITS, THE GOVERNING AGENCY'S CURRENT ROAD STANDARDS, AND
THE STANDARD SPECIFICATIONS. ALL MATERIAL FROM CLEARING AND GRUBBING SHALL BE HAULED TO AN APPROVED WASTE DISPOSAL SITE
PROVIDED BY THE DEVELOPER/CONTRACTOR.
WHEN TRENCHING THROUGH EXISTING PAVEMENT, THE PAVEMENT SHALL BE CUT ON A NEAT -LINE BY SAW CUTTING. TRENCH SIDES SHALL BE KEPT AS
VERTICAL AS POSSIBLE GIVEN THE SOIL CONDITIONS. COMPACTION AND RESTORATION SHALL BE DONE AS DETAILED BELOW AND IMMEDIATELY AFTER
THE TRENCH BACKFILL IS PLACED SO AS TO CAUSE THE LEAST DISRUPTION TO TRAFFIC. ALL PAVEMENT SHALL BE CUT 1 FOOT OUTSIDE THE EDGE OF
THE TRENCH ON EACH SIDE.
ANY TRENCH EXCEEDING FOUR FEET IN DEPTH SHALL BE PROVIDED WITH ADEQUATE SAFETY SYSTEMS MEETING THE REQUIREMENTS OF THE
WASHINGTON STATE INDUSTRIAL SAFETY AND HEALTH ACT (WISHA), CHAPTER 49.17 RCW, AND ALL REGULATIONS ADOPTED PURSUANT THERETO. THE
wi DEVELOPER/CONTRACTOR SHALL HAVE A STRUCTURAL ENGINEER REVIEW AND STAMP ANY AND ALL SHORING PLANS AND CALCULATIONS. THE
DEVELOPER/CON1RACTOR SHALL BE RESPONSIBLE FOR WORKER SAFETY AND THE DISTRICT AND THE DISTRICT'S ENGINEER ASSUME NO
a
RESPONSIBILITY.
0
WHEN NATIVE MATERIAL AT THE TRENCH BOTTOM IS SUITABLE FOR PIPE BEDDING, THE BOTTOM SHALL BE HAND FINISHED TO GRADE SO THAT THE
co
0 PIPE WILL HAVE UNIFORM SUPPORT ALONG THE BARREL AND BELL. AFTER THE PIPE IS IN PLACE, ADDITIONAL HAND SELECTED NATIVE MATERIAL
cm
MEETING THE REQUIREMENTS FOR BEDDING MATERIAL SHALL BE PLACED AND TAMPED AROUND THE PIPE FOR A MINIMUM OF 4 INCHES ABOVE THE
o CROWN OF THE PIPE.
0
WHEN NATIVE MATERIAL AT THE TRENCH BOTTOM IS STONY OR OTHERWISE NON -UNIFORM, THE TRENCH SHALL BE OVER -EXCAVATED A MINIMUM OF 6
o INCHES BELOW THE SPECIFIED GRADE AND A LAYER OF PIPE BEDDING MATERIAL SHALL BE FURNISHED AND PLACED TO THE SPECIFIED GRADE. AFTER
w THE PIPE IS IN PLACE, ADDITIONAL HAND SELECTED NATIVE MATERIAL MEETING THE REQUIREMENTS FOR BEDDING MATERIAL SHALL BE PLACED AND
TAMPED AROUND THE PIPE FOR A MINIMUM OF 4 INCHES ABOVE THE CROWN OF THE PIPF
w
Li
IF THE NATIVE MATERIAL AT THE TRENCH BOTTOM IS UNSUITABLE FOR FOUNDATION PURPOSES OR WILL HAVE DIFFICULTY PROVIDING UNIFORM
G
BEARING FOR THE PIPE, SUCH MATERIAL SHALL BE REMOVED AND REPLACED WITH A MINIMUM OF 6 INCHES OF COMPACTED FOUNDATION MATERIAL.
c
Un
11
THE BEDDING MATERIAL SHALL BE CARRIED UP EVENLY ON BOTH SIDES OF THE PIPE SIMULTANEOUSLY IN APPROXIMATELY 6-INCH LAYERS
Li
AND EACH
LAYER THOROUGHLY COMPACTED WITH APPROPRIATE TOOLS IN SUCH MANNER AS TO AVOID INJURING OR DISTURBING THE COMPLETED PIPELINE.
w
ALL BEDDING AND NATIVE MATERIAL SHALL BE STORED AWAY FROM THE EDGES OF EXCAVATION AND OFF THE PAVED ROADWAY AND SHOULDER.
e
S
ALL TRENCH BACKFILL SHALL BE MECHANICALLY COMPACTED TO 95% OF THE MAXIMUM DENSITY WITHIN THE RIGHT-OF-WAY AND IN ALL AREAS
(PA\LED AND UNPAVED) WHERE STREETS, ROADWAY SHOULDERS, DRIVEWAYS, SIDEWALKS, OR PARKING LOTS WILL BE CONSTRUCTED OR
o
RECONSTRUCTED OVER THE TRENCH EXCEPT FOR TRENCHES OVER 8 FEET IN DEPTH. WHEN THE TRENCH DEPTH EXCEEDS 8 FEET, TRENCH BACKFILL
a�
UP TO 4 FEET FROM THE TOP OF THE TRENCH SHALL BE MECHANICALLY COMPACTED TO 90% OF THE MAXIMUM DENSITY. THE REMAINING TOP 4 FEET
�i
OF THE TRENCH SHALL THEN BE MECHANICALLY COMPACTED TO 95% OF THE MAXIMUM DENSITY. IN UNPAVED AREAS AND OTHER AREAS NOT SUBJECT
TO VEHICULAR TRAFFIC, TRENCH BACKFILL FROM THE PIPE TO WITHIN 3 FEET OF THE SURFACE SHALL BE COMPACTED TO 90% OF THE MAXIMUM
�
DENSITY. THE UPPER 3 FEET SHALL BE COMPACTED TO 95o/» OF THE MAXIMUM DENSITY.
U
i
o
ALL DENSITIES SHALL BE DETERMINED BY TESTING PER THE MODIFIED PROCTOR METHOD, ASTM D1557. THE DEVELOPER/CONTRACTOR SHALL BE
N
RESPONSIBLE FOR PROVIDING DENSITY TEST REPORTS CERTIFIED BY A PROFESSIONAL ENGINEER REGISTERED IN THE STATE OF WASHINGTON. A
Q;
MINIMUM OF ONE TEST SHALL BE TAKEN WITHIN EVERY 500 FEET OF TRENCH LENGTH AND AT DEPTHS UP TO 50% OF TRENCH DEPTH, OR AS DIRECTED
°
BY THE DISTRICT'S FIELD REPRESENTATIVE OR THE GOVERNING ROAD AGENCY. COMPACTION OF LATERALS OR SERVICE LINE TRENCHES SHALL ALSO
BE TESTED WHERE DIRECTED BY THE DISTRICT'S FIELD REPRESENTATIVE OR THE GOVERNING ROAD AGENCY. TESTING OF CDF, WHEN USED AS
REQUIRED BY THE GOVERNING ROAD AGENCY, SHALL BE IN ACCORDANCE WITH ASTM 04832.
U
n
TRENCH BACKFILL SHALL BE PLACED IN UNIFORM LOOSE LAYERS NO MORE THAN 12 INCHES THICK AND MECHANICALLY COMPACTED AS SPECIFIED. IN
g
ANY TRENCH WHERE THE SPECIFIED COMPACTION CANNOT BE ACHIEVED WITH NATIVE BACKFILL, THE TOP 4 FEET SHALL BE REPLACED AND
OF THE MAXIMUM DENSITY
COMPACTED TO 950/» WITH IMPORTED BANK RUN GRAVEL. THE DISTRICT'S FIELD REPRESENTATIVE RESERVES THE RIGHT
'
TO REQUEST A COMPACTION TEST AT ANY TIME ON THE BACKFILL MATERIAL.
0
cli
0
J
IN CUTS TRANSVERSE TO THE ROAD ALIGNMENT AND AT ALL UTILITY CROSSINGS, THE ENTIRE TRENCH SHALL BE BACKFILLED WITH CRUSHED
Q
SURFACING. BACKFILL SHALL BE PLACED AND MECHANICALLY COMPACTED IN 12-INCH MAXIMUM LIFTS.
s
AFTER BACKFILL AND COMPACTION, AN IMMEDIATE COLD MIX PATCH SHALL BE PLACED AND MAINTAINED IN A MANNER ACCEPTABLE TO THE
GOVERNING ROAD AGENCY UNTIL REPLACED WITH PERMANENT SURFACING.
a
ALL PIPE AND FITTINGS SHALL BE LAID "IN THE DRY" UNLESS OTHERWISE APPROVED BY THE DISTRICT. TRENCH EXCAVATIONS SHALL BE DEWATERED
BY USING WELL POINT SYSTEMS, SUMPS WITH PUMPS OR OTHER METHODS APPROVED BY THE DISTRICT. DEWATERING SYSTEMS SHALL BE USED IN
ACCORDANCE WITH GOOD STANDARD PRACTICE AND SHALL BE EFFICIENT ENOUGH TO LOWER THE WATER LEVEL IN ADVANCE OF THE EXCAVATION
AND MAINTAIN IT CONTINUOUSLY TO KEEP THE TRENCH BOTTOM AND SIDES FIRM AND DRY. DEVELOPER/CONTRACTOR SHALL SUBMIT THE
DEWATERING PLAN TO THE DISTRICT FOR REVIEW AT LEAST 10 DAYS PRIOR TO COMMENCING ANY DEWATERING WORK. ALL DEWATERING EFFLUENT
SHALL BE ROUTED THROUGH A DEWATERING POND PRIOR TO RELEASE,
GROUNDWATER SHALL BE CONTROLLED SUCH THAT SOFTENING OF THE BOTTOM OF EXCAVATIONS OR FORMATION OF "QUICK" CONDITIONS OR
"BOILS" DURING EXCAVATION SHALL BE PREVENTED AND NO SOIL SHALL BE ERODED INTO THE EXCAVATION FROM THE SIDES OF EXCAVATION.
DEWATERING SYSTEMS SHALL BE DESIGNED AND OPERATED SO AS TO PREVENT REMOVAL OF THE NATURAL SOILS. THE DEVELOPER/CONTRACTOR
SHALL AT ALL TIMES HAVE ON HAND SUFFICIENT PUMPING EQUIPMENT AND MACHINERY IN GOOD WORKING CONDITION FOR ALL ORDINARY
EMERGENCIES, INCLUDING POWER OUTAGES, AND SHALL HAVE AVAILABLE AT ALL TIMES COMPETENT WORKERS FOR THE OPERATION OF SAID
EQUIPMENT.
U
U
c DEVELOPER/CONTRACTOR SHALL CONTROL SURFACE RUNOFF SO AS TO PREVENT ENTRY OR COLLECTION OF WATER IN EXCAVATIONS AND SHALL
W MAINTAIN THE UNDISTURBED STATE OF THE FOUNDATION SOILS AND ALLOW THE PLACEMENT OF ANY BACKFILL TO THE REQUIRED DENSITY. THE
0 RELEASE OF GROUNDWATER TO ITS STATIC LEVEL SHALL BE PERFORMED IN SUCH A MANNER AS TO MAINTAIN THE UNDISTURBED STATE OF THE
NATURAL FOUNDATION SOILS, .PREVENT DISTURBANCE OF COMPACTED BACKFILL, AND PREVENT FLOTATION OR MOVEMENT OF STRUCTURES AND
PIPELINES.
Ln o DEVELOPER/CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLYING WITH ALL PERMIT REQUIREMENTS AND PROVISIONS FOR MONITORING AND
MANAGING WATER DISCHARGED FROM THE EXCAVATION.
0
w
3. COVER OVER PIPELINES
o THE DEPTH OF COVER FOR WATER MAINS SHALL BE 36-INCHES FOR 8-INCH DIAMETER AND SMALLER MAINS AND 48-INCHES FOR MAINS OVER 8-INCHES
IN DIAMETER. DEPTH OF COVER AT DITCH LINES SHALL MEET THE SAME REQUIREMENTS. EXCEPTIONS WILL BE ALLOWED ONLY WITH THE PRIOR
APPROVAL OF THE DISTRICT.
0
J
a-
THE DEVELOPER/CONTRACTOR SHAI I_ NOTIFY THE DISTRICT'S FIELD REPRESENTATIVE AND OTHER UTILITIES AT LEAST 48 HOURS IN ADVANCE OF ANY
CONSTRUCTION AND MAKE THE NECE:�SARY ARRANGEMENTS WITH THE DISTRICT'S FIELD REPRESENTATIVE FOR THE CONNECTION TO THE EXISTING WATER
MAIN. THE DEVELOPER/CONTRACTOR SHALL NOT OPERATE ANY GATE VALVE OF THE WATER SYSTEM BEFORE, DURING OR AFTER CONSTRUCTION WITHOUT
PRIOR APPROVAL OF THE DISTRICT. THE DEVELOPER/CONTRACTOR SHALL FURNISH ALL MATERIAL, EQUIPMENT AND LABOR NECESSARY FOR MAKING THE
CONNECTION UNDER THE SUPERVISION OF THE DISTRICT. THE 48 HOUR NOTICE REQUIREMENT SHALL NOT COUNT SATURDAYS, SUNDAYS, AND HOLIDAYS.
WORK SHALL NOT BE STARTED UNTIL ALL OF THE MATERIAL, EQUIPMENT AND LABOR NECESSARY TO PROPERLY COMPLETE WORK IS ASSEMBLED ON THE SITE.
ONCE WORK IS STARTED ON A CONNECTION, IT SHALL PROCEED CONTINUOUSLY WITHOUT INTERRUPTION AND AS RAPIDLY AS POSSIBLE UNTIL THE CONNECTION IS
COMPLETED. BEFORE ORDERING MATERIALS FOR ANY CONNECTION TO AN EXISTING WATER MAIN, DEVELOPER/CONTRACTOR SHALL EXCAVATE THE WATER MAIN
AND VERIFY OUTSIDE DIAMETER OF ALI PIPES FOR DETERMINATION OF TYPES OF FITTINGS TO BE USED. THE DEVELOPER/CONTRACTOR SHALL COORDINATE ALL
WORK WITH THE DISTRICT'S FIELD REPI�I=SENTATIVE
5. SEPARATION OF UTILITIES
MINIMUM SEPARATION BETWEEN WATFR AND SEWER MAINS SHALL CONFORM TO SECTION C1-9.1 OF THE "CRITERIA FOR SEWAGE WORKS DESIGN", CURRENT
EDITION, AS PUBLISHED BY THE DEPARTMENT OF ECOLOGY. MINIMUM SEPARATION BETWEEN OTHER UTILITIES SHALL BE 6 INCHES WITH A SAND
CUSHION.WATER MAINS SHALL PASS UNDER STORM SEWERS WHEN NECESSARY TO MAINTAIN THE MINIMUM COVER REQUIREMENTS FOR WATER MAINS.
THERE SHALL BE NOT LESS THAN A SIX-INCH CUSHION BETWEEN THE WATER MAINS AND THE STORM SEWERS.
PUGET SOUND ENERGY VAULTS, HAND HOLES AND LIGHT STANDARDS SHALL BE LOCATED NO CLOSER THAN 10 FEET FROM ANY WATER MAINS, FIRE
HYDRANTS, AND BLOW -OFF ASSEMBLIES AND NO CLOSER THAN 5 FEET FROM ANY WATER SERVICES. DEVELOPER SHALL BE RESPONSIBLE FOR
COORDINATION OF VAULTS, HAND HOLES, AND LIGHT STANDARDS WITH THE WATER MAINS, SERVICES, FIRE HYDRANTS, AND BLOW -OFF ASSEMBLIES. NO
CONSTRUCTION SHALL START UNTIL I -HE DEVELOPER HAS FURNISHED THE DISTRICT WITH A WORK SKETCH FROM PUGET SOUND ENERGY OR A SIGNED
HOLD HARMLESS AGREEMENT (FORM SUPPLIED BY THE DISTRICT) IS PROVIDED.
6. THRUST BLOCKING
ALL FITTINGS SHALL BE BLOCKED WI FH POURED CONCRETE AGAINST UNDISTURBED SOIL WITH SUFFICIENT CONCRETE AND 3/4-INCH ANCHOR RODS, IF
REQUIRED, TO RESIST THE RESULTAN f FORCES. BLOCKING SHALL PROVIDE FOR REMOVAL OF ANY CONNECTION TO THE FITTING WITHOUT DAMAGE TO THE
FITTING. WHERE UNFAVORABLE GROUND CONDITIONS ARE ENCOUNTERED, SPECIAL BLOCKING WILL BE REQUIRED AS DIRECTED BY THE DISTRICT IN THE
FIELD. WHEN DIGGING NEAR FITTING," ON EXISTING PIPELINES, TEMPORARY BLOCKING SHALL BE INSTALLED TO PREVENT BLOWOUTS. THRUST BLOCKING
SHALL CONFORM TO THE STANDARD DE -TAILS.
7. WATER WORKS TESTING
PRESSURE TESTING OF LINES SHALL 13E IN ACCORDANCE WITH SECTION 7-09.3(23) OF THE STANDARD SPECIFICATIONS. TEST PRESSURE SHALL BE THE
EXISTING SYSTEM LINE PRESSURE PLUS lS 150 PSI, BUT IN NO CASE SHALL THE TEST PRESSURE BE LESS THAN 250 PSI. MAINS SHALL BE DISINFECTED PER
SECTION 7-09.3(24) OF THE STANDARD SPECIFICATIONS.
THE DEVELOPER/CONTRACTOR SHALL_ CUBE AND FLUSH ALL NEW WATER MAINS WHILE BEING OBSERVED BY THE DISTRICT'S FIELD REPRESENTATIVE.
DISTRICT SHALL FURNISH THE CUBES FOR THE DEVELOPER/CONTRACTOR WHO SHALL THEN BE RESPONSIBLE FOR CUBING THE NEW WATER MAINS.
DEVELOPER/CONTRACTOR SHALL COORDINATE WITH DISTRICT'S FIELD REPRESENTATIVE FOR THE LOCATIONS TO BE CUBED. AFTER THE CUBES HAVE BEEN
FLUSHED FROM THE SYSTEM, THE RE,"T OF THE FLUSHING, CHLORINATING, PRESSURE AND PURITY TESTS SHALL BE COMPLETED. THE DISTRICT SHALL BE
RESPONSIBLE FOR COLLECTING THE SAMPLES AND OBTAINING THE BACTERIOLOGICAL TESTS.
8. REPAIR OF PIPELINE FAILURES
BROKEN OR OTHERWISE DEFECTIVE PIPE SHALL BE REMOVED AND REPLACED. REPAIR BANDS OR CLAMPS SHALL NOT BE USED TO REPAIR BROKEN PIPE.
9. JACKED CROSSING
AT LOCATIONS AS REQUIRED BY THE DISTRICT OR GOVERNING ROAD AGENCY, OR AS PROPOSED BY THE DEVELOPER, WATER MAIN CROSSINGS OF ARTERIAL
STREETS SHALL BE MADE BY JACKING, DRILLING, OR AUGURING A STEEL CASING PIPE BENEATH THE SURFACE. ALIGNMENT AND GRADE OF CASINGS FURNISHED
SHALL BE SUCH THAT NO ADDITIONAL FITTINGS ARE NECESSARY TO MAKE THE CONNECTION. IF THE CASING DOES NOT MEET THIS REQUIREMENT, IT SHALL BE
ABANDONED BY FILLING THE CASING WI fH MOIST SAND AND A NEW CASING INSTALLED TO MEET THE LINE AND GRADE REQUIREMENTS. NO OPEN EXCAVATION
SHALL BE MADE CLOSER THAN 6 FEET FI:OM THE EDGE OF PAVEMENT.
DIAMETER OF CASING PIPE SHALL BE :;UFFICIENT TO ALLOW INSTALLATION OF THE WATER PIPE. WALL THICKNESS SHALL BE SUFFICIENT TO WITHSTAND
INSTALLATION FORCE AND HIGHWAY LOADING WITH A MINIMUM THICKNESS OF /-INCH. AFTER THE WATER PIPE HAS BEEN ADJUSTED TO GRADE, MOIST SAND
SHALL BE TAMPED INTO THE CASING PIPE 30 THAT ALL VOIDS WILL BE FILLED. MANUFACTURED CASING SPACERS THAT PROHIBIT MOVEMENT OF THE PIPE IN
ANY DIRECTION WITHIN THE CASING MAY BE USED IN LIEU OF FILLING THE VOID BETWEEN THE WATER MAIN AND THE CASING WALL WITH SAND.
10. WATER SUPPLY
WATER SUPPLY FOR FILLING, TESTING AND FLUSHING OF THE NEW MAINS MAY BE AVAILABLE FROM THE EXISTING DISTRIBUTION SYSTEM; HOWEVER, THE
DEVELOPER/CONTRACTOR WILL BE BILLED BY THE DISTRICT FOR THE WATER USED AT THE CURRENT COMMERCIAL METER RATE. THE
DEVELOPER/CONTRACTOR MAY PROVIDE HIS OWN METERING FACILITIES TO THE SATISFACTION OF THE DISTRICT OR ACCEPT THE QUANTITIES ESTIMATED
BY THE DISTRICT.
11. EXISTING UTILITIES
EXISTING UTILITIES SHOWN ON ANY REFERENCE DRAWINGS PROVIDED BY THE DISTRICT HAVE BEEN PLOTTED FROM THE BEST INFORMATION AVAILABLE TO
THE DISTRICT. THE DEVELOPER/CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL EXISTING UTILITIES WELL ENOUGH IN AD\LANCE OF THE
EXCAVATION TO PREVENT DAMAGE DURING CONSTRUCTION. THE DEVELOPER/CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE RESULTING FROM
HIS OPERATIONS ON THE PROJECT.
THE DEVELOPER SHALL RELOCATE OR REPLACE ANY EXISTING FIRE HYDRANTS LOCATED WITHIN 50 FEET OF THE DEVELOPMENT TO MEET THE DISTRICT'S
REQUIREMENTS IF NEW CONSTRUCTION BY THE DEVELOPMENT CREATES A SAFETY HAZARD OR A NON -COMPLIANT CONDITION WITH DISTRICT STANDARD
SPECIFICATION REQUIREMENTS.
12. WARRANTY PERIOD
THE DEVELOPER MAKING THE APPLICA I ION FOR A LINE EXTENSION SHALL BE RESPONSIBLE FOR THE MATERIALS AND FOR SATISFACTORY OPERATION OF
THE FACILITY FOR A PERIOD OF ONE YEAR FROM THE DATE OF ACCEPTANCE OF THE COMPLETED PROJECT AND THE BILL OF SALE TO THE DISTRICT.
J
Q
LJ
U)
0
w
m
z
aul 41
51NGH
04 NYASj��,/gif/i. -
21
41773
701JfiL ��
r-- S E P 0 8
N
rn
Q W U
G
_j
L
Q d
as
u
o
z
iJ o_
c� rr
os
v
ti4
?n.
L
Q
Lj
m
Qa
11'2
Lij
Uy
z
C)
G Z
n_ '1
G
Ci
U
:2o
O
Z
F-
_
00
C)
O
Z
(
W
w 0
co
`�
o
>
X
C9
ZO
U
00
Z
Q
W
0 �
co U
(_0m
C
Q
coW
.J
Ij
o
-,
L
U
Q
=
%�
p
J
��
_
O
U
a
W
ft
r�
y
ro
0
0
i
T
z
0
z
cn
W
U
X
O
W
0
0,00'
z
W
�
�
w
Q
p
w>
U
O
�
OW
0
U
Q
asp A1, r- F_2
SHEET 2 )f- 5
DRAWING F2.011