HomeMy WebLinkAboutCO 3CITY OF RENTC CAC -02 -034 Adden #3 -02 FEB n 6 '2Q03 } CITY OF RENTON Public Works Department RECEIVED CONTRACT CHANGE ORDER AGREEMENT CITY CLERK'S OFFICE 0351 CONTRACT: CAG 02454. EAST KENNYDALE SANITARY SEWER INFILL & C.O.# 3 WATER MAIN REPLACMENT CONTRACTOR: FRANK COLUCCIO CONSTRUCTION CO. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: ITEM Additional Quantities Under This Change Order Unit Qnty Unit Price Total Price 041. NEW ITEM: Extra Work Items per Contractors Force Account Orders: LS S -1 #1 -Raise utility covers for overlay Monterey Ave NE, NE 16th St to NE 17" PI. ($633.10) S -4 #a'Wasser manhole coating on manholes with revised side 2 sewer corings, MH's 11, 12, 14, & 18 and additional MH at 1800 Blaine Ave NE. ($2,034.28) S -5 #1- Additional side sewer bends and labor to accommodate existing utility conflicts. ($22,558.72) S -5 #4- Additional sod replacement for revised sewer main located at NE 18th St. ($956.50) S -6 #1- Excavation and Backfilling of Trench for Sewer Main between MH 13 and MH 14 which couldn't be installed due to buried concrete duct bank. ($6,893.26) S -6 #3- Additional asphalt removal and grading for rebuilding NE 24th St. between Monterey and Aberdeen. ($4,937.44) S -6 #4 -Lost production on side sewer installation on Edmonds Ave NE at Sta. 3 +65, 6 +73 & 7 +19 due to 8" iron pipe not shown on plans. ($783.61) S -6 #7- Additional road base removal per City Inspector (Rea Hagan) Dayton Ave NE Sta 5 +40 to 6 +15. ($1,751.45) S -7 #1- Asphalt removal & regrade parking strips at 2416 & 2417 Dayton Ave NE per City Engineer. ($776.02) S -8 #4- Modify driveway at 2441 Monterey Ave NE to prevent autos from dragging at sidewalk transition. ($432.07) S -8 #5- Removal of temporary gang mail boxes for Dayton Ave NE & Monterey Ave NE. ($519.43) Sub Total Sales Tax (8.8 %) Total 1 $42,275.88 $42,275.88 ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE THIS ORDER ESTIMATED CONTRACT TOTAL AFTER CHANGE $1,030,126.02 $1,146,566.54 $45,996.16 $1,192,562.70 SIGNATURE Contractor: Project Engi Approved B i S: A k Date: z neer: Date: /! 02 By Date: (� '14JItilit4s Sy tem Director) H: Divisions \Utilties \Wastewtr\east kennydale infrill \C0- 2/JDH /tb I $42,275.88 $3,720.28 $45,996.16