CONTRACT CHANGE ORDER AGREEMENT
CITY OF Yl`=fV T ,tA
MAR 2 6 2003 C.O. #4
RECEIVED e 1 of 1
CITY CLERK'S OFFIGPI =fig
CONTRACT: SR -900 SUNSET /ANACORTES SIGNAL IMPROVEMENTS
CAG 02 -050
CONTRACTOR: Totem Electric of Tacoma, Inc.
SUMMARY OF PROPOSED CHANGE:
At the SW corner of Sunset Blvd and Anacortes Avenue NE, a wall was installed
due to the change in elevation from back of the new sidewalk and the McDonald parking lot
with a vertical drop off of 18" and 24 ". Because of the height difference it is in the best
interest of the City and the adjacent property owner to instail a 35 LF of Steel Hand Rail.
Standard Detail H024 and the attached drawing will be a part of this Change Order.
Add the following New Bid Items to the Contract:
Item
Approx.
Quantity
I Description
Unit Price
Amount
53
1 1
ISteel Pipe Handrail for Sidewalk
LS
1 $3,718.00
This item is to include any and all costs incurred for additional work approved
No additional payment will be made for this work
Dec I
Working Days:
7 additional working days are granted for this work.
All work, materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT
CURRENT CONTRACT
ESTIMATE NET CHANGE
ESTIMATED CONTRACT
AMOUNT
AMOUNT
THIS ORDER
TOTAL AFTER CHANGE
$248,097.28
$261,348.94
$3,718.00
$265,066.94
SIGNATURES:
Contractor:
Project Manager:
Approved By:
Approved By:
(Transporta6 ms Division Director)
Date:
Date: Z -Z -Q2
Date: /?,— Z,.dr -Q 1--**�
Date: 1 a2 —�