Loading...
HomeMy WebLinkAboutCO 17CHANGE ORDER owner COR Form Architect (This form is to be executed In triplicate and each party is to retain an original,) Contractor Project Name: RENTON SENIOR HOUSING Date: July 13, 1997 Project Address: 3151 NE 18th Street Change Order No.: Seventeen (17 ) Contractor Name: KIRTLEY-COLE ASSOCIATES ORB Project No.: 9007 d, Address 1002 -10th Street COR Project No,: CAG 095-91 Add ;l, 165.49 Snohomish, Washington 98290 Contract For General Construction 3) Per ORB Proposal Request No. 33, 6/2/92 and Kirtley-Cale Contract Date: October 31, 1991 The Contract is hereby amended as follows: O 1) Per ORB Proposal Request No. 27 (partial), 6/2/92 and Kirtley-Cole Modification Proposal No. 38R (attached): Add $2,330.99 ""Stick frame (2) dormers at 2 -hour area separation wall." 2) Per ORB Proposal Request No. 46, 6/25/92 and Kirtley-Cole Modification Proposal No. 56, 7/2/92 (attached): "Stick Add ;l, 165.49 frame (L) additional dormer at south end of east wing." 3) Per ORB Proposal Request No. 33, 6/2/92 and Kirtley-Cale Q Modification Proposal Vo. 51, 6/30/92 (attached): Provide . Add i309Q08 changes." plumbing and architectural, i 4) Per ORB Proposal Request No. 37, 6/2192 and Kirtley-Cole Modification Proposal No. 52, 6/30/92 (attached): Delete 155)."" Delete ( -L36.00) door louvres at Doors #162 b 465 (laundry room rh TOTAL CONSTRUCTION COST IMPACT OF THIS CHANGE ORDER: ...................................... Add $6,450.56 s labor, material, overhead, profit, and all direct The Change Order shall include all Contracton) and/or Indirect costs associated with the Change In Scope of Work. to This Change Order Is not valid unless signed by the Owner, Architect, and Contractor. $4,620.765.00 The Original Contract Sum was................................................................................................. 590,796,77 Net Change by previously authorized Change Order(s) was ......................................................... 5,211,561.78 The Contract Sum prior to this Change Order was 6.450.56 The Contract Sum wilt be revised by this Change Order in the amount of .................................... 012.34 5,2Lt3,4 The new Contract Sum Incorporating this Change Ordorwlll be + 4 days days TheContract Time will be changed by ..................................................................................... The Substantial Completion Date Including this Change Order Is ................................................"January 7, 1993 _ *See Change Odrer 112 for TBD items. NOTE: The above summary does not Include any changes in the Contract Sum or Contract Time whAh have been approved N by ORB Farm 301 - ConstrucUon Change Directive or Owners Field Directives. THE ORB ORGANIZATION, INC, 807 SW Grady Way, Suite 210 Renton, Washington 98055 t3oAar . Dev Date KIRTLEY-COLE ASSOCIATES 1002. 10th Street Snohomish, Washington 98290 7'\Pbrdon Cote / ai^j rf Date CITY OF RENTON. P ri R DEPT. 200 Mill Avenue South Renton, Washington 98055 1lincent Lea MODIYr'ICA IONx. -WPOSAL KM71.FsY Prn'w, RENI'ON SENIOR HOUSING - JOB 1315 COLE 0 ASSOCIATES, INC W1111111111111111 sonom Date: July 2, 1992 oorauwta P.O. �a �79 H1: To: TORB ORGANIZATION utobcmish wu6. 914.90 Initiated by: Archiltu (2061561.3115 ModIllt2tlon Propusal: Stick frame (2) dormers 10c3t0d at dormers at 2 -hour area separatlan walla: Murs Constructl0a NOTE: I,M11t)1iDIATE ApPRovAL IS NECESSARY TO AVOID DELAY IN SCHEDULE Subtotal • . Overhead & PrO It 0 15 % ... .. . Bonding ® 2% .. ... . . TOW . Rersnrt ror Moditleatlont as per PROPOSAL RUQUESi' #27 (PARTIAL ITEM #4 ONLY) Cost:Additional: 52,330,99 Credit,: 5-0- Net: Chance in Calendar Dabs: TWO (2) Iteeommendatlont Architect (General Contractor Owner Modincatiun Prnpoeal Inco puruted Into Chanttc Order Numbort 17 ,r Atuehmenv: Murs C=nntrwiun Coatpany ptvposrd dated 611702 No a stmt wrll bat trkcn regardlnj this item until we rjcaive wry Ruutoewlen d+rwint us M do "a - AO ooarnd wurlc will pr000ed on iu "O (whodulc PROPOSAL NO. _UlJBn41Si11 1.987.20 $1,987.20 $298.08 545.71 52.330.99 $2,330.99 «.. CITY OF RWON la 00g;peF; ILI t HIM$ C0143Z'RUCTIom COMPANY 06/13/92 4713 CLa1 WCft AV'R revised 06/17/!2 XV=W=, *&. 98303 =1 306-481-89$4 • lA7Cr206-621-0940 Q � � � � u ]FATLY -=LB 1002 10Th STREET JUN 7 S9gZ P.O. BOX 1179 BUDD i3A, WA. 982.90 M1206-568-317'3 !JORW•COLE AS$OCrIAT S PAX1206-568-79 .9 rat proposal 127 Regtiest Revised 6/17/92 GMNMJE is 1.Rslocate 2 -hour separation gall, 90 ainute double agrees. NOT WHIM OUR SCOPE OF / M/A. 2.INSTAM add. layer 6/8 qxb 1f/�► 3.Instsll 2- layars qwb N/A 4. Install 2 -hour separation galla through Dormers,add additions]. layer 3/8" 0W and delete strip vent at underside of soffit at 1 -hour wall locations. IS 3NEW Y 9=3X.3is-00� - $864.00 ' 129.60 $993.60 mi DOAIt PasT MxMG - 1 DORS 2 DORMERa X $993.61 TOTAL MU23T $ 1,967.20 8+001Mdary request not an this proposal request is for the reconstruction of and Dormer that xaorn as shad rmgt Ea + st wing .. Y y doz$ 993.60 Total request for both issues AUPACTF=Y KIRTLEY MODIFICATION . ROFOSAL, COLE • project: RENTON SENIOR HOUSING - JOB 0315 ASSOCIATES, INC �T Data: July 2, 1992 onntrAwn! P.O, bntt 1179 1041 • 10th To: THE ORB ORGANIZATION, INC. uwhmikh wqh. 9tt290 Initiated hy: Architect 1206) 563-3175 Modification Proposal: Stick frame (1) additional dormer located A 304 and of E. wing: Muts Construction Company NOTE: IMMEDIATE APPROVAL IS NECESSARY TO AVOID DELAY IN SCHEDULE Suluntal .. . , Overhead & Profit ® 13 %................. ............ Bonding 0 2% ... . Total .............. .. ... Ramon for Modification: tut per PROPOSAL, REQUEST' 046 Cal: Additiunal: $1,165.49 Credits: 5.0- Not: Change In Cakndar Dalm ONE (1) Recommendation: Architect Genoral Contractus Owner t Mudiflestion Pruponal Tncarpornted into CNqo Order Dumber: /7 , r�elyd (i✓ Y / Attat:ltments: Mure Conarmliun Company - proposal dxtud 6117/92 No action "I be seken ngardiva thi+ kan until we Twelve wrk tw mAlwnuttun dtreaing us to do to. All unrrreut work will PrOCOW On i1a narrnal tahodula. rltorosAt. NO, 993.60 $993.60 $149.04 $22.85 $1,165.49 $1,165.49 . 7� . CONSTRUCTION COMPA2tY 06/ls/9Z � 1 GLENWOOD AVE revised 06/17/92 ,KA. 98103 8206-481-3933 i2ti6-621-03Cs Q L� 1 10TH S7%ZXT JUN 17 1ca� WX 117'9 im'WA. 98290 KIR(.COLE ,ASSOCIATES 1106-348--3179 iZ04-968-7919 z O Proposal 127 2Aquast Revised 6/17/92 1.RelocAte 2 -hour separation wall, 9a minute double pig• HOT WX=X OUR SCOPE OP WORK/ X/A. Sin 2.VSTALL add. layer 5/8 gwb�4 N/A 0C 3.1notall 2-14y*" gwb R/aM 4.Inntall 1 -hour separation walls through Dormars,xdd additions:. Q layer s/a" Crib and delete strip vent at underside of soffit `_ r nt 3 -hour wall locations. Cn ADDITIONAL MAN HOURS PER DOREZR! � 3NEN X g S X $33.00/HR $464.00 i P60 ls% 1129.60 $993.60 PER DOW= �n EAST WING - 1 DORMERS Erin WEST WIXG - 1 DORS 2 �DORMEAS X $993.60 y* $ 1, 967.20 t;; To'iiLL RSCCJ T $ 1,987.20 zy request not on this proposal request is for the � ction of and Dormer that.was-shy as sh*d roofs �^ Lust wing 1 dox r # 993. 60 `1i } O n request for both issuets $ 2,980-80 in