HomeMy WebLinkAboutCO 32CHANGE ORDER Owner
Architect
CSR Form
("chis form is to be executed in triplicate and each party is to retain an origitlal.) Contractor
Project Name: RENTON SENIOR HOUSING Date, January 5, 1993
Change Order No.: Thirty-two (32)
Project Address: 3151 NE 161h Street
Contractor Name: KIRTLEY-COLE ASSOCIATES ORB Project No.: 9007
COR Project No.: CAG 095-91
& Address 1002 - 10th Street
Snohomish, Washington 98290 Contract For. General Construction
Contract Date: October 31, 1991
The Contrad is hereby amended as fri!ows:
1. Per Kirtley-Cale Modification Proposal #100, 912892 (copy attached):
Add $5,171'43
z
O
-1
'Add to prefinish millwark trim and jambs per RFI 0213.'
n
m
2. Per COR Proposal Request #61, 10121/92 and Kirtley-Cole Modification
Proposal #111R 112, 11/11/92 (cop!es attached): "Add new catch basin in gutter, east Add 1,864.90
zi m
of driveway at #3100 NE 16th.'
3. Per GOR Proposal Request 063, 10!26192 and Kirtley-Cote Modification
m 0
Proposal #111, 1114192 (copies attached). "Delete 4" high cr,lcrele pad atO
Subtract -0-
Q C
unit hot water tanks."
K
4. Per Kirtley-Cale Modification Proposal #119,12/22192 (copy attached):
Add 895.25
mm
rn M
"Provide wall cap at stairwells."
D Z
S
n
.......Add $7,932.07
CONSTRUCTION COST IMPACT OF THIS CRANGE ORDER: ............. ......... .... .
r�rn.
rt
TOTAL
The Change Order shall include all Contractor(s) labor, material, overhead, profit, and all direct and/or indirect costs associated
O Vi
Fn
with the Change in Scope of Work.
C EnEn
This Change Order is not valid unless signed by the Owner, Architect. and Contractor.
m�
..$4,620,765.00
The Original Contract Sum ..........................................................................
was
Net Chan y previously authorized Change Order(s) was ........................ .............................................:....667,122.24
Change b .......
5,287,887.24
The Contract Sum prior to this Change Order was ................. ..... .................,................................,.......
...... 7,932.07
Change Order 0 the amount of
The Contract Sum will be revised by this g
The new Contract Sum incorporating this Change Order will be ...... ..5,295,819.31
SEE ' BELOW.......................................... + 2 day
The Contract Time will be changed by ................................... ....
January 29. 1993
=
N
The Substantial Completion Date including this Change Order is................................................................
(See Change Orders 012. 18 3 19 for TBD items.)
z
does not include any changes in the Contract Sum or Contras Time which have been approved
NOTE: The at>ove summary
by ORB Form 301 - Construction Change Directive or Owner's Field Directives.
T
n
m
THE ORB ORGANIZATION. INC.
607 SVg Grady Way, Suite 210
RentfrrfiiWash ington 98055
AIA
Date
KIRTLEY-COLE ASSOCIATES
1002 - 10th Street
Snohomis , Washington 98290
tr 1�F
v Gordon Cole
Date
CITY OF RENTON, P & R DEP .
200 Mill Avenue South
Renton, Washington 98055
Vincent Lee
r 7 r,� _
D le
'Nt7TE: Acceptance of the additional days on this Change Order is conditional pending receipt of K.C.'s critical path method
schedule review.
MODIFICATION Pk . POSAL NO.100
KIRTLEY
COLE • Project: RENTON SENIOR HOUSING - JOB 1315
ASSOCIATES, INC
p"rat pate: September 28, 1992 J
contractors
p.o. box 1179
tom - 10th To: THE ORB ORGANIZATI,
snolxsmiah
wash. 9"- Initiated by: �
(:06) 568-3175
Modification Proposal: Add to prefinish millwork trim & jambs as per RFI1213.
Henry Bacon Building Materials
WSSTon materials (4.075 x 8.2 `S)
Subtotal
Overhead & Profit 0 15% .......... • •
Bonding (fV 2%
Total .. ............
Reason for Nfodirication: as per RFI 1213.
Cost: Additional: $5,171.93 Credits: S-0- Net:
Change in Calendar Days:
-7-
Approved Reject
$4,075.00
334.15
S4,409.15
$661.37
$101.4h
$5,171.93 I�
55,171.93
Recommendation: for C.O. i
I
Architect 15
General Contractor
Owner
hiodilication Proposal Incerporated Into Change order Number: 3�
h
Attachments: as per Henry Bacon proposal dated 9124192.
No action will be taken regarding this iter until we reLcivc wriiten autharization directing us lo do sa.
All contract work will proceed an its normal schedule, PROPOSAL N4. ONE-HONDRIDi-1-0o1-
I
z
0
5
rn
-i -n
V)
cm
my
OC
�C
to
04
Dz
r-1
cn
n
M rn
ON
C) Fn
K(n
rn n
to
z
O
t7
M
'MMCH 90 . PRCoucnc)N
P.O. Bait 7012
5210 East Lake SWMWiSh Pkwy S-F-
W"quah, WA 98027-7012
To*pto*: (206) 391-2075
Fax 1206) 391-2052
FAX INFORMATION SHEET
We Are Tmwr&kV ___L_ Psom WckaV TWs Cam Sh"L U you EVKW= Any
gft* Wh 7?js TnvmsdW-4.pbm Cal Us As Sow As PQ6sbW At P" 301-207"0'
Thm*YotL
r
CWT - RAY
GDRDY
ESTIMATOR
ARCH9ECT
SUpOKENDENT
AMNTING
DEBBIE
DIME IA WW ON 3n4WW Pm cm "I -MW
C FAX m
COMMENTS
0
IAV vu •C JG YI
LCA {7'[Lni ItiiJ{IrVK�M
4LL ciJC1`y91^17V♦
r. 1
��.MP.'Ii'loo.
4(
TODD ROBINSON PAINTING, INC.
Co,,M1RCWL CO � R1 WA MW
E00 SLEA A41 -1V 4 AX (M 1.1941
44e. i/t 1..5/1l �✓
A
/,,v 7 e,
5e
Cr ���5 � 5
rer
G � �If �
�r t car
-7- d'
/�pao� y'inN�•�•J
t