HomeMy WebLinkAboutCO 39 revisedCHANGE ORDER Owner Architect COR Farm (This form is to be executed in triplicate and each party is to retain an original.) Contractor Project Name: RENTON SENIOR HOUSING Date: Change Order Na.: March 19, 1993 Thirty-nine (39) Revised Project Address: 3151 NE 16th Street Contractor Name: KIRTLEY-COLE ASSOCIATES ORB Project. No.: COR Project Ido.: 9007 CAG 095-91 & Address 1002 - 1 Oth Street Snohomish, Washington 98294 Contract For. General Construction Contract Date: October 31, 1991 The Contract is hereby amended as follows: 1. Per COR Proposal Request #72, 2125193 and Kirtley-Cote Modification Proposal 0144, 312193 (copies attached): 'Credit for installation of (2) non-standard street Subtract (-$1,000.00) light poles ' 2. Per COR Field Directive #43, 2119193 and Kiriley-Cole Modification Proposal #146, 312193 (copies attached): 'Provide replacement sign at common area kitchen range.' Add 81.95 I TOTAL CONSTRUCTION COST IMPACT OF THIS CHANGE ORDER: I ..................................... Subtract $918.05 4 t The Change Order shall include all Contfactor(s) labor, material, overhead, profit, and all direct andlor indirect costs associated with the Change in Scope of Work. This Change Order is not valid unless signed by the Owner, Architect, and Contractor. $4,620,765.00 The Original Contract Sllm was.............................................................................................................................710.239.27 Net Change by previously authorized Change Order(s) was ......................................................... ..................5,331.004.27 The Contract Sum prior to this Change Order was........................................................................... ...........3 1, 08.05) The Contract Sum wil' by revised by this Change Order In lfha amount o1 ................................................ .$5.33-918. 22 The new Contract Sum incorporating this Change Order will be...................................................................... $5.3 .0 days The Contract Time will be changed by................................................................................. .................... ..............................................February 13, 199 The Substantial Completion Dale including this Change Order is ce Change Orders #12, 18, 19. 33, 34 8.36 for TBD items.) NOTE: The above summary does not include any changes in the Contract Sum or Contract Time which have been approved by ORB Form 301 - Construction Change Directive or OrNner"s Field Directives. R DEPT THE ORB ORGANIZATION, INC. 607 SW Grady Way, Suite 210 Renton, 7Washington 98055 �•F IC at William, AIA f Date KIRTLEY-COLE ASSOCIATES 1002 - 10th Street Snohomish, Washington 98290 rdon Cole =� ! CLZ Date CITY OF REN I UN, P rl 200 Md! Avenue South Renton, Washington 98055 Vincent Lee Z Q n m -=1 'Tr NM vm C M On c m mm �Z C O -n M ou' C o K COP {7 -1 Z O 0 m KIRTLEY f NIODIMATION PkiPOSAL NO. 144 COLE • Project: RENTON SENIOR HOUSING - JOB #315 ASSOCIATES, INC scr,cr,i Date: March 2, 1993 contractors p.o. box 1179 To: THE ORB ORGANIZATION. INC. 1002 - 10th snobomish wash. 9e"90 Initiated by: Owner (206) SW3175 Modification Proposal: Credit for installation of (2) incorrect non-standard street light poles as agreed by City of Ren.on Public Works: Rob's Electric, Inc. .1.'000.04 y Subtotal , . ........ .. , ... .. S-1,400.00 4S Total 54.000.00 Reason for blodifieation: as per PROPOSAL REQUEST 172 Cost: Additional: SO.00 Credits: 51,000.00 Net: 5400.00 Change In Calendar Days: -0- Approved Reject Recommendation: for C.O. Architect General Contractor Owner lilodincltlon Proposal Incorporated Into Change Order Number: 39 Attachments: Rob's Electric - proposal No action will be taken regarding this item until we r0ccive Written suthoriation directing us to do to. All contract work will pra:ced on its normal ALule. aP05ONE NUNDREI L KIRTLEY-COLE ASSOCIATES, INC. 1001. 101h Str##VP.O. fox 1179, Saabocnlrh, WA 99290 )'fine• (;G6) 561.3173/FAX (106) 5447919 Febru>iry 25, 1993 RIF -QUEST FOR 229 -P -0S A i._ RAY SUB/SUPPUER: R08'S ELECTRIC, INC. GORDY ESTIMATOR ARCHITECT ATTENTION: Rob SUPERINTENDENT ACCOUNTING PROJECT: RfiNTON SENIOR HOUSING DEBBIE 30B NUMBER: 315 DIANE DESCRIPTION OF FAX TO COMME`ITS WORK: 9)i per PROPOSAL REQUEST #72, attAched RESPOND BY: AS SOON AS POSSIBLE TOTAL AMOUNT (.it 10m.00 CONTRACT TliufE REQUEST DAY(S) MSR1lt1 MAX txrMvx /►lcf u rix! AYx ADtt� 0 IM �Oy*/AL XXYtXCTf ALL Or TIM M011 t�vllt.Vt:1t 11.0 VYIt1f1. ANY CAM nr 1,t 1�v1, 1, ►�R+ GCJi AMY lUp" ti*`F.CTt RSC turn MAW. AUTHORIZED SIGNATURE; DATE: SIGNEDI R