HomeMy WebLinkAboutChange Order - 7C.O.# 7 SUMMARY OF PROPOSED CHANGE: ITEM Unit Qty. Unit Price Total Price A70 LS 1.00 2,234.20 $2,234.20 APPROVAL SIGNATURES: Approved By: Date: Jesse Newman, Project Manager Approved By: Date: Will Dannenberg, Laser Underground and Earthworks, inc. Approved By: Date: Ronald Straka, Utility Systems Director Approved By: Date: Approved By: Date: Cheryl Beyer, Renton City Attorney Sub Total (Schedule A - Sewer) $2,155,179.40 CITY OF RENTON Additional Quantities Under This Change Order Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CONTRACTOR: Thunder Hills Sewer Interceptor Rehabilitation CAG-23-048 Laser Underground and Earthworks, inc. Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: ESTIMATED CONTRACT TOTAL AFTER CHANGE $2,234.20 $225.65 NEW ITEM: Re-core SSMH#3 to prevent removal of more trees. Re-core with saw and chip out channel to lower I/E in SSMH #3. $2,459.85Total (Schedule A - Sewer) ESTIMATED NET CHANGE THIS ORDER $2,459.85 ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT $2,152,719.55 $2,052,252.99 Sales Tax (10.1% for work performed before April 1, 2024) H:\File Sys\WWP - WasteWater\WWP-27-03921 Thunder Hills Sewer Interceptor Rehabilitation\110 - Construction\Change Orders\CO 7 Recore MH3\Backup\CAG-23-048_CO#7- THSIR 1 of 1 CAG-23-048, CO #7-24 Martin Pastucha, PW Administrator Approved by Cheryl Beyer via email l 3/15/2024