Loading...
HomeMy WebLinkAboutCM_Construction_Mitigation_180111_v1Preliminary Construction Mitigation Plan For Green’s Landing Proposed Construction Dates (begin and end dates): Based on this preliminary short plat application date, we anticipate construction permits for utilities and plat infrastructure (roads, sidewalks, etc.) to be finalized in the fourth quarter of 2018 with utility and plat infrastructure construction possibly beginning in late 2018 or early 2019. Home construction on the lots should begin during the summer of 2019 and run through at least the winter of 2019 and possibly longer, depending on lot sales. Hours and Days of Operation: Construction activities will be limited to the hours between 7:00am and 8:00pm, Monday through Friday and 9:00am and 8:00pm Saturday. In addition, haul hours are limited to the hours between 8:30am and 3:30pm on Saturdays, unless approved in writing in advance by the development services division. No work permitted on Sundays. Proposed Hauling/Transportation Routes: The site is most accessible from NE 4th Street to Duvall Avenue NE to NE 2nd Street. Duvall is accessible from two main directions - from the east via NE 4th Street / 156th Avenue SE / Maple Valley Highway / I-405 and from the west via NE 4th Street / I-405. Measures to be implemented to minimize dust, traffic and transportation impact, erosion, mud, noise and other noxious characteristics: Water Truck, Temporary Erosion Control Plan, BMPs, construction proposed during City of Renton permitted work hours. Any special hours proposed for construction or hauling (i.e. weekends, late nights): No special hours for construction or hauling are anticipated or proposed at this time. Preliminary Traffic Control Plan: Site is located along NE 2nd Street (classified residential access) at the intersection with Hoquiam Avenue NE (classified Minor Arterial). Anticipate “construction ahead” warning signs east / west of the project along NE 2nd Street, and north / south of the project along Hoquiam Avenue NE. Flaggers and additional signage will be provided when work is required in either right-of-way. Construction staging will be limited to on-site with parking on-site and along NE 2nd Street / Hoquiam Avenue NE only as permitted. Final Traffic Control Plan will be provided at the time of Engineering approval.