HomeMy WebLinkAboutChange Order - 5Docusign Envelope ID: 0320390A-5DDF-4DF3-85A5-CAF472ABB006 Contract Title: Change Order No. 5 Highlands to Landing Pedestrian Lighting Phase II Contractor: Colvico, Inc. Contract No. : CAG-21-004 Federal Aid No. : N/A 181 Ordered by Engineer D Proposed by the Contractor (VECP) D Unilateral Original Contract: Current Contract: Estimated Net Change This Order: New Contract: h/n/zoi'{ Date Reviewed By: Engineer of Record Date Reviewed By: &fflitef L� 7/17/24 City of Renton Project Manager Date Reviewed By: City Attorney Date 5 D LumpSum □Bid Item 181 Force Account Amount Working Days $330,490.83 60 $314,025.55 60 $21,414.00 0 $335,439.55 60 Design Manager) Consent By: Surety (Greater than 25% cost and/or 20% time increase) Endorsed By: y 1L Contractor Date 7/22/24 Date Executed By:�DocuSigned by: Martin Pastuch a3;7 ;2024 1 g: so AM PDT 8B8131FD988449D City of Renton Public Works Date Administrator/ Mayor Change Order No. Contract Title: Highlands to Landing Pedestrian Lighting Phase II Contract No. CAG-21-004 Page 1 of 4 CAG-21-004, CO #5-24 Approved by Cheryl Beyer via email 7/17/2024 Docusign Envelope ID: 0320390A-5DDF-4DF3-85A5-CAF472ABB006 Plans: None. Equitable Adjustment: This Change Order does include an equitable adjustment per Section 1-09.4 of the 2020 WSDOT/APWA Standard Specifications. See attached. Extension of Time: The Time for Completion is extended _O_ Working Days. Sections 1-04.4 and 1-04.5 of the 2020 WSDOT / APWA Standard Specifications shall govern this Change Order. The Work of the referenced Contract is modified to include the changes detailed herein. The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change. To be attached to Change Order: □Estimated Change Order Cost !xi Plans □Field Directive/Request for Information Response/Serial Letter □Change Order Quotation □Project Labor List □Force Account Equipment Rate Request (DOT Form 422-010 EF) □Overhead Adjustment Determination Change Order No. Contract Title: Contract No. 5 Highlands to Landing Pedestrian Lighting Phase II CAG-21-004 Page 3 of 4