Loading...
HomeMy WebLinkAboutPN_Project_Narrative_240904_v1Project Narrative: a. Project name size and location of site; Project name: Jin residence driveway replacement Project size: 750 square feet Location of site: 4304 SE 3rd Street, Renton WA 98059 Work summary: replacing an old double-car driveway, applying for a 16’ curb cutout, to make driveway access within the city right-of-way b. Zoning designation of the site and adjacent properties; R6 c. Current use of the site and any existing improvements; Single family home and city’s righ-of-way d. Special site features; N/A e. Statement addressing soil type and drainage conditions; Soil is predominantly gravel and sandy loam, driveway area slops southwest downwards to the NE 3rd street for drainage. f. Proposed use of the property and scope of the proposed development; Replacing a damaged double-car driveway with same size as previous; leaving a 24” wide pervious area from side property line to the new driveway; requesting a 16’ curb cutout within city’s right-of-way to accommodate an access to the new driveway. g. Proposed off-site improvements; N/A h. Total estimated construction cost and estimated fair market value of the proposed project; Estimated construction cost: $15000 i. Estimated quantities and type of materials involved if any fill or excavation is proposed; Approx. 9 yards of gravel and 9 yards of concrete. j. Number, type and size of trees to be removed; N/A k. Explanation of any land to be dedicated to the City; N/A l. For shoreline application only; N/A