Loading...
HomeMy WebLinkAboutCM_Construction Mitigation_240606_v1Poppy Court Short Plat 805 Hoquiam Ave NE, Renton 2-Lot Short Plat CONSTRUCTION MITIGATION Proposed Construction Dates (begin and end dates): Start of construction is proposed for the Spring of 2025 with installation of utilities including storm drainage facilities and frontage improvements. There is no on-site grading proposed for this project. Completion of construction improvements is proposed for Fall of 2025. Hours and days of operation: 8:00 am to 5:30 pm, Monday through Friday or as otherwise allowed by City of Renton. Proposed Hauling/ Transportation routes: Materials and labor to the site are proposed from NE 4th Street and Hoquiam Ave NE. Transportation access will be from Hoquiam Ave NE with on-site parking and material storage within the existing and proposed driveway and Lot 2 house footprint area. Measures to minimize construction activities: The minimal construction activity will be necessary to provide the required public and private improvements for this project. City required frontage improvements, will include matching the alignment of the existing frontage on the adjoining recent developments both north and south of the parcel. It is planned to minimize public disturbance and as much as is feasible, provide adequate pedestrian access during the new construction. Special hours: No special hours are necessary to complete construction. Weekend work may be necessary to complete the project on schedule; this will be determined by owner, contractor, and City of Renton. Preliminary Traffic Control Plan: Coordination with the City of Renton staff will be necessary to minimize disruption to vehicle and pedestrian traffic on Hoquiam Ave NE. Once a contractor is selected, a traffic control plan will be submitted and approved prior to the pre- construction meeting with the City of Renton. This plan will be implemented prior to any construction activities.