M E M O R A N D U M
DATE:September 14, 2017
TO:Jill Ding, Planner
FROM:Ann Fowler, Civil Plan Reviewer
SUBJECT:Utility and Transportation Comments for Moorman Short Plat
2004 Shattuck Avenue South
LUA 17-000546
I have reviewed the application for the Moorman Short Plat at 2004 Shattuck Avenue South (APN(‘s)
7222000382) and have the following comments:
EXISTING CONDITIONS
The site is approximately 0.52 acres in size and is triangular in shape. The site is currently developed with
a single family residence and associated detached accessory structures.
Water Water service is provided by City of Renton The site is in the Talbot Hill service area in the 300
hydraulic pressure zone. There is an existing 8-inch City water main located in Shattuck Avenue
South (see Water plan no. W-1132) that can deliver a maximum total flow capacity of
gallons per minute (gpm). The approximate static water pressure is 65 psi at the elevation of
150 feet. The site is located outside of an Aquifer Protection Area.
Sewer Wastewater service is provided by the City of Renton There is an existing 8-inch concrete
wastewater main located in Shattuck Avenue South (see City plan no. S-0022).
Storm There are stormwater mains located in Shattuck Avenue South. Runoff from the existing site
includes one single family residence where no stormwater infrastructure currently exists on-
site. Runoff from the site sheet flows east to west across the site and into a ditch and catch
basin at the northwest corner of the site.
Streets Shattuck Avenue South is a Residential Street with an existing right of way (ROW) width of 40-
feet as measured using the King County Assessor’s Map. No frontage improvements currently
existing along the property frontages.
CODE REQUIREMENTS
Moorman Short Plat – LUA17-000546
Page 2 of 5
WATER
1. Each lot shall have a separate meter. The project proposes one 1-inch water service line and meter
to each lot, for a total of two (2) new domestic water service lines and meters.
2. Minimum separation between water service lines and storm sewer stubs is 5-feet. Applicant will
be required to demonstrate compliance with the minimum pipe separations as outlined in
Appendix J of the 2012 Water System Plan Update as part of the Civil Construction Permit review.
3. Installation of fire hydrants within 300 feet of each lot is required by Renton Fire Authority. The
number and location of new hydrants will be dependent upon the finished square footage of the
homes.
4. The development is subject to applicable water system development charges and meter
installation fees based on the size of the water meters.
a. Water system development charges for each proposed 1-inch domestic water service is
$3,486.00 per meter or $6,972.00 for (2) 1-inch meters.
5. Water service installation charges for each proposed 1-inch water service is $2,850.00 per meter.
The total water service installation fee is $5,700.00 for (2) 1-inch meters. This is payable at
construction permit issuance.
6. Drop-in meter fee is $460.00 per meter. The total water drop-in meter fee is $920.00 for (2) 1-
inch meters. This is payable at issuance of the building permit.
7. Additional water system development charges and water meter charges will apply if a landscape
irrigation meter is required and is based on the size of the meter.
SEWER
1. All existing side sewers will be required to be cut and capped during demolition of the properties.
New side sewers shall be installed to serve each individual property.
a.Each lot shall be served by an individual side sewer, dual side sewers are not allowed.
b.The side sewers to benefit lots 2 and 3, which are shown to be along the south property
lines of lots 1 and 2, shall be in a dedicated 10-foot private sewer easement.
2. The development is subject to applicable wastewater system development charges based on the
size of the new domestic water to serve the project.
a. SDC fee for a 1-inch meter is $2,540.00 per meter. The total fee is $5,080.00 for ($2.00)
1-inch meters.
b. This is payable at construction permit issuance.
SURFACE WATER
1. A geotechnical report, dated May 23, 2017, completed by GEO Group Northwest, Inc., for the site
has been provided. The submitted report describes the site is a Low Erosion Hazard area. Erosion
control measures will need to be in place prior to starting grading activities on the site. The report
discusses the soil and groundwater characteristics of the site including infiltration potential and
provide recommendations for project design and construction. A Geotechnical Addendum
Report, dated August 8, 2017, completed by Geo Group Northwest, Inc., provided results of
infiltration testing on the site in order to evaluate the feasibility of utilizing On-Site Infiltration
BMPs. Based upon the results of the testing, the recommended design infiltration rate is 0.66
inches/hour, which exceeds the minimum recommended percolation rate for the use of Low
Impact Design (LID) On-Site BMPs such as Bioretention and Permeable Pavements. Geotechnical
recommendations presented need to be address within the project plans.
Moorman Short Plat – LUA17-000546
Page 3 of 5
2. A Preliminary Drainage Plan and Technical Information Report (TIR), dated July 19, 2017, was
submitted by CPH Consultants with the Land Use Application. Based on the City of Renton’s flow
control map, the site falls within the Flow Control Duration Standard area matching Forested Site
Conditions and is within the Black River Drainage Basin. The development is subject to Full
Drainage Review in accordance with the 2017 Renton Surface Water Design Manual (RSWDM).
All nine core requirements and the six special requirements have been discussed in the Technical
Information Report.
3. The development is required to provide On-Site Best Management Practices (BMPs) to help
mitigate the new runoff created by this development.
a. The soils classification presented in the geotechnical report classified the soils as silty
sandy loams and provided infiltration testing results indicating the soils have the
potential ability to infiltrate at a measured rate of up to 16 inches per hour. Applicant
shall explore the feasibility of limited infiltration, permeable pavements and
bioretention as potential On-Site BMPs for the proposed residences. The proposed On-
Site BMPs shall be designed and submitted with the Civil Construction Permit
Application and may be installed with the individual building permits for each proposed
parcel.
4. The development is required to provide flow control and basic water quality treatment prior to
discharge into the public conveyance system. The project proposes a detention vault beneath the
shared driveway tract and water quality treatment will consist of conveyance to a Stormfilter with
ZPG Media Filtration system prior to connection to the proposed detention vault.
a. The development is required to match 50% of the 2-year and up to the full 50-year
duration flows, as well as match the 2- and 10-year peak flows. The applicant will be
required to demonstrate compliance with Core Requirement #3 as part of the Civil
Construction Permit review.
b. Presettling shall be provided per Section 6.7.2.1 of the 2017 RSWDM.
c. The conveyance and water quality systems shall be designed in accordance with the
RSWDM that is current at the time of civil construction permit application.
d. For treatment upstream of detention, the water quality design rate is the peak 15-
minute flow rate. Applicant will be required to demonstrate compliance with Core
Requirement #8 as part of the Civil Construction Permit review.
5. There are no potential downstream flooding or erosion issues identified in the TIR.
a. The development shall not create protected slopes as defined by RMC 4-3-050.
b. Grading shall be in accordance with RMC 4-4-060.
6. Any proposed detention and/or water quality vault shall be designed in accordance with the
RSWDM that is current at the time of civil construction permit application. Separate structural
plans will be required to be submitted for review and approval under a separate building permit
for the detention and/or water quality vault. Special inspection from the building department is
required.
7. All work proposed outside of the applicant’s property will require a permanent drainage
easement to be provided to the City and a temporary construction easement prior to any permits
being issued.
8. A surface water development fee of $1,608.00 per new single family residence will apply. The
project proposes the addition of 2 new residences (3 new single family homes, 1 existing homes
to be removed). The estimated total fee is $3,216.00. This is subject to final design and payable
prior to issuance of the utility construction permit.
TRANSPORTATION
Moorman Short Plat – LUA17-000546
Page 4 of 5
1. The proposed development fronts Shattuck Avenue South along the west property lines. Shattuck
Avenue South is classified as a Residential Access Road. Existing right-of-way (ROW) width is
approximately 40 feet. To meet the City’s complete street standards for residential streets,
minimum right of way width is 53 feet. Dedication of 6.5 feet of right of way would be required.
Required half street frontage improvements shall include 26-feet of paved roadway width (13-
feet from centerline), installation of 0.5-foot curb and gutter, 8-foot planter strip and 5-foot
sidewalk.
2. Access to each of the lots may be granted via the proposed shared driveway provided the shared
driveway meets requirements for emergency services access and must provide a turnaround in
compliance with City code 4-6-060I.
a. Fire department apparatus access roadways are required to be a minimum of 20 feet wide
fully paved, with 25 feet inside and 45 feet outside turning radius. Fire access roadways
shall be constructed to support a 30 ton vehicle with 75 psi point loading. Access is
required within 150 feet of all points on the buildings.
3. Shared driveways are allowed for access to up to 4 lots provided at least one of the four (4) lots
abuts a public right-of-way with at least fifty (50) linear feet of frontage and the subject lots are
not created by a subdivision of ten (10) or more lots. Refer to the shared driveway requirements
as outlined in RMC 4-6-060J. The tract shall be the width of the paved surface (20-ft minimum if
fire access is required into the development) plus eight feet (8') for a landscape strip, when the
tract abuts properties that are not part of the subdivision.
4.Driveways shall be a minimum of 5-ft from the property line to the north, 8-ft if the landscape
strip is required. Refer City code 4-4-080 regarding driveway regulations.
a. Driveways shall be designed in accordance with City standard plans 104.1 and 104.2.
b. Maximum driveway slope is 15%. Driveways which exceed 8% shall provide slotted drains.
5. Paving and trench restoration shall comply with the City’s Trench Restoration and Overlay
Requirements.
6. Payment of the transportation impact fee is applicable on the construction of the development
at the time of application for the building permit. The current rate of transportation impact fee
is $5,430.85 per dwelling unit for single family homes. The project proposes the addition of 2 new
residences (3 new single family homes, 1 existing homes to be removed). The estimated total fee
is $10,861.70. Traffic impact fees will be owed at the time of building permit issuance. Fees are
subject to change. The transportation impact fee that is current at the time of building permit
application will be levied.
GENERAL COMMENTS
1. Adequate separation between utilities as well as other features shall be provided in accordance
with code requirements.
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other utilities is
required with the exception of water lines which require 10-ft horizontal and 1.5-ft
vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.
2. All construction utility permits for utility and street improvements will require separate plan
submittals. All utility plans shall confirm to the Renton Drafting Standards. A licensed Civil
Engineer shall prepare the civil plans.
Moorman Short Plat – LUA17-000546
Page 5 of 5
3. A landscaping plan shall be included with the civil plan submittal. Each plan shall be on separate
sheets.
4. All utility lines (i.e. electrical, phone, and cable services, etc.) serving the proposed development
must be underground. The construction of these franchise utilities must be inspected and
approved by a City of Renton inspector.
5. Fees quoted in this document reflect the fees applicable in the year 2017 only and will be assessed
based on the fee that is current at the time of the permit application or issuance, as applicable to
the permit type. Please visit www.rentonwa.gov for the current development fee schedule.