HomeMy WebLinkAboutRE BMC Secondary Review FindingsFrom: Jeff Gray <Jeff.Gray@otak.com>
Sent: Monday, October 23, 2017 1:22 PM
To: Jill Ding
Subject: RE: BMC Secondary Review Findings
Hi Jill,
Let me know if this suffices. My response is below:
Wetland A was rated as Category III and a habitat score of 4. We concur with the Category III wetland
rating and low habitat functions provided by Wetland A, and the buffer width determination of 75 feet
for any land use other than low impact. This revised buffer width recommendation is based on the
additional supporting documentation provided by the applicant’s consultant in the Technical
Memorandum dated October 4, 2017, the findings of which were reviewed in the field prior to the site
meeting on October 12, 2017.
Jeff
Jeff Gray | Otak, Inc.
c: 609.532.4620
jeff.gray@otak.com
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Monday, October 23, 2017 11:10 AM
To: Jeff Gray
Subject: RE: BMC Secondary Review Findings
Hi Jeff,
I just spoke with BMC and they were able to revise their site plan to include Drainage Z as a part of
Wetland A and are showing an enhanced 56.25’ reduced buffer from the wetland areas. Could you send
something to me clarifying that you now agree that the standard buffer from this wetland is 75 feet and
not 100 feet?
Thanks so much for your help!
Jill
From: Jeff Gray [mailto:Jeff.Gray@otak.com]
Sent: Friday, October 13, 2017 10:07 AM
To: Jill Ding <JDing@Rentonwa.gov>
Subject: RE: BMC Secondary Review Findings
Hi Jill,
I thought I’d follow up after our meeting yesterday. I stuck around another 5 minutes or so to help SVC
and the applicant understand what my concerns were, and that my opinion hasn’t changed about the
ditch being jurisdictional (and therefore has a buffer). It wasn’t clear to me what their next steps will be
(revise the site plan, dispute, etc). They wanted me to send you a scope of work but that’s not how the
process works since I’m working on behalf of the city, and its up to the city to tell me how I can help
them.
I saw a couple options moving forward for the city and the applicant, but I also know you’re trying to
avoid an endless cycle of dialogue. Give me a call Monday if you want to discuss and how I can help;
otherwise, I’ll wait to hear from you as needed. We are out of funds on our end at this point.
-Jeff
Jeff Gray | Otak, Inc.
c: 609.532.4620
jeff.gray@otak.com
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Monday, October 09, 2017 1:02 PM
To: Jeff Gray
Subject: RE: BMC Secondary Review Findings
Thanks, I’ll let the applicant know. If there’s a problem with the timing on their end I’ll let you know.
Jill
From: Jeff Gray [mailto:Jeff.Gray@otak.com]
Sent: Monday, October 09, 2017 12:54 PM
To: Jill Ding <JDing@Rentonwa.gov>
Subject: RE: BMC Secondary Review Findings
Yes. I’ll be there on the early side to check out the wetland breaks mentioned in the memo.
Jeff
Jeff Gray | Otak, Inc.
c: 609.532.4620
jeff.gray@otak.com
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Monday, October 09, 2017 12:50 PM
To: Jeff Gray
Subject: RE: BMC Secondary Review Findings
Jeff,
Do you have time available from 1-2 on Thursday for a meeting on-site with the applicant?
Thanks,
Jill
From: Jeff Gray [mailto:Jeff.Gray@otak.com]
Sent: Monday, October 09, 2017 8:27 AM
To: Jill Ding <JDing@Rentonwa.gov>
Subject: RE: BMC Secondary Review Findings
Hi Jill,
Yes, I’m in the office all today. Feel free to call any time. I was expecting a response from Soundview
based on the conversation I had with Jon Picket a couple weeks ago, but I didn’t have any preconceived
notions about what they’d find or respond with. He planned to do more aerial photo interpretation and
field work, and the findings are summarized in the newest memo. I’ll take a closer look at the memo this
morning. Want to talk around 9:30am?
Jeff
Jeff Gray | Otak, Inc.
c: 609.532.4620
jeff.gray@otak.com
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Monday, October 09, 2017 6:50 AM
To: Jeff Gray
Subject: FW: BMC Secondary Review Findings
Jeff,
Do you have time for a quick phone call with me today? I noticed that Soundview did not revise their
plans per the memo you sent and I wanted to know if the information they resubmitted was something
you were expecting.
Thanks,
Jill
From: Jon Pickett [mailto:jon@soundviewconsultants.com]
Sent: Friday, October 06, 2017 1:46 PM
To: Jill Ding <JDing@Rentonwa.gov>
Cc: Jeremy Downs <jeremy@soundviewconsultants.com>; Da Dalto, Michael
<Michael.DaDalto@BuildWithBMC.com>; Darrell Donovan <Darrell@dbros.com>; Todd Sawin
<TSawin@AHBL.com>; Chris Corr <ccorr@kiddermathews.com>; Cliff Long <CLong@Rentonwa.gov>
Subject: RE: BMC Secondary Review Findings
Jill,
Please find attached the response to the third-party review comments. Please let me know if you have
an questions prior to our call on Thursday. If possible, it may be helpful to have Otak review the findings
prior to the call to see if they have any questions which we can answer.
I will be available Monday if you have an questions.
Thanks,
Jon Pickett
Sr Environmental Planner
Soundview Consultants LLC
Environmental, Natural Resource, and Land Use Consulting
Office: 253.514.8952 x027
Fax: 253.514.8954
Email: Jon@SoundviewConsultants.com
Main Office and Mailing Address:
2907 Harborview Drive, Suite D
Gig Harbor, WA 98335
Satellite Office:
105 South Main Street, Suite 230
Seattle, WA 98104
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Tuesday, September 19, 2017 10:09 AM
To: Todd Sawin (TSawin@AHBL.com) <TSawin@AHBL.com>
Cc: Darrell Donovan <Darrell@dbros.com>
Subject: BMC Secondary Review Findings
Todd,
Please find attached a copy of the Secondary Review findings.
Thanks,
Jill