MITIGATION DOCUMENT
Quendall
Terminals
Renton, Washington
August 2015
prepared by
City of Renton
Department of Community and Economic Development
Quendall Terminals i
Mitigation Document
August 2015
SUMMARY OF MITIGATION MEASURES
Below is the final list of mitigation measures for the Quendall Terminals Redevelopment Project.
The mitigation measures list is also contained in the Quendall Terminals Final EIS (August
2015; a separate document). There is some duplication of mitigation measures under the
various elements of the environment discussed in this Mitigation Document and the Quendall
Terminals Final EIS. This is necessary in order to clearly indicate how specific impacts to each
element will be addressed by the project (e.g., the required stormwater control system will
address impacts on water resources as well as critical areas, and as such is included under
both elements).
It should be noted that this list of mitigation measures and the accompanying implementation
language later in this document do not exempt the applicant from complying with all portions of
vested Renton Municipal Code (RMC), and any conditions that may be applied through the
Master Site Plan and Site Plan Review processes. Furthermore, the site plan depicted as the
Preferred Alternative (see FEIS Figure 1-1, Preferred Alternative) has not been reviewed for
compliance with all segments of the RMC; this review will be conducted at a later date.
A. Earth
During Construction
A1. A temporary erosion and sedimentation control plan (TESCP), including Best
Management Practices (BMPs) for erosion and sedimentation control, shall be
implemented. This plan shall include, but not limited to, the following measures:
All temporary (and/or permanent) devices used to collect stormwater runoff shall
be directed into tightlined systems that shall discharge to an approved
stormwater facility.
Soils to be reused at the site during construction shall be stockpiled or stored in
such a manner to minimize erosion from the stock pile. Protective measures shall
include covering with plastic sheeting and the use of silt fences around pile
perimeters.
During construction, silt fences or other methods, such as straw bales, shall be
placed along surface water runoff collection areas in proximity to Lake
Washington and the adjacent wetlands to reduce the potential of sediment
discharge into these waters. In addition, rock check dams shall be established
along roadways during construction.
Temporary sedimentation traps or detention facilities shall be installed to provide
erosion and sediment transport control during construction.
The project construction shall adhere to the wet season construction
requirements between October 1st and April 30th.
A2. A geotechnical engineer that is a Certified Professional in Erosion and Sediment Control
or a Certified Erosion and Sediment Control Lead shall review the grading and TESCP
plans prior to final plan design to ensure that erosion and sediment transport hazards
are addressed during and following construction. As necessary, additional erosion
mitigation measures could be required in response to specific design plans.
Quendall Terminals ii
Mitigation Document
August 2015
A3. Site preparation for roadways, utilities, and structures, and the placement and
compaction of structural fill shall be based upon the recommendations of a geotechnical
engineer.
A4. Temporary excavation dewatering shall be conducted if groundwater is encountered
during excavation and construction activities. Such dewatering activities shall be
conducted in a manner that shall minimize potential impacts due to settlement.
A5. A geotechnical engineer shall determine whether structural fill shall be placed to control
the potential for settlement of adjacent areas; adjacent structures/areas shall be
monitored to verify that no significant settlement occurs.
A6. A geotechnical engineer shall determine whether deep foundation systems (such as
piles or aggregate piers) shall be installed and/or ground improvements made to
minimize potential damage from soil settlement, consolidation, spreading, and
liquefaction.
A7. If deep foundation systems (such as piles or aggregate piers) are used to support
structures, the following measures shall be implemented:
Measures shall be employed to ensure that the site cap (i.e., soils/impervious
surfaces, should they be installed) shall not be affected and that installation of
the piles/piers shall not mobilize contamination that shall be contained by the
cap. The U.S. Environmental Protection Agency (EPA) shall determine the
appropriate measures to be employed, which could include: installation of
surface casing through the contaminated zone; installation of piles composed of
impermeable materials (steel or cast-in-place concrete) using soil displacement
methods; the use of pointed-tip piles to prevent carry down of contamination;
and/or, the use of ground improvement technologies, such as in-place
densification or compaction grouting.
A pile vibration analysis and vibration monitoring shall be conducted during pile
installation in order to ensure that impacts due to vibration do not occur.
Suitable pile and pile hammer types shall be matched to the subsurface
conditions to achieve the required penetrations with minimal effort to reduce
potential vibration. Potential pile types could include driven open-end steel pipe
piles, driven closed-end steel pipe piles, or driven cast-in-place concrete piles.
Potential hammer types could include percussion hammers or vibratory
hammers.
Suitable hammer and pile cushion types shall be used for the specific conditions
to reduce potential noise. A typical hammer employs the use of a heavy impact
hammer that is controlled by a lead, which is in turn supported by a crane.
Pile installation shall occur during regulated construction hours.
A8. Fill soils shall be properly placed and cuts shall be used to reduce the potential for
landslide impacts during (and after) construction.
A9. The appropriate management of contaminated soils that could be disturbed and
groundwater that could be encountered during redevelopment of the site shall be
addressed through the cleanup/remediation process and by institutional control
requirements overseen by the EPA.
Quendall Terminals iii
Mitigation Document
August 2015
Following Construction
A10. A permanent stormwater control system shall be installed in accordance with the
applicable stormwater regulations.
A11. Offshore outfall locations for stormwater discharge from the permanent stormwater
control system shall be equipped with energy dissipation structures or other devices to
prevent erosion of the lake shoreline and bottom.
A12. All buildings shall be designed in accordance with the International Building Code to
address the potential for seismic impacts.
A13. The majority of the site will be covered with impervious surfaces following
redevelopment. Permanent landscaping shall also be provided to reduce the potential for
erosion and sedimentation with redevelopment.
A14. Flexible utility connections shall be employed to minimize the risk of damage to utility
lines due to differential settlement between structures and underground utilities, as
needed and as determined by the City’s responsible public official.
B. Critical Areas
During Construction
B1. A TESCP, including BMPs for erosion and sedimentation control, shall be implemented
during construction. Implementation of this plan shall prevent or limit impacts to the lake
and shoreline wetlands from erosion and sedimentation.
B2. If approved by EPA, trenching for utilities and stormwater outfalls shall be incorporated
into site grading associated with remediation efforts to limit or prevent later disturbance
of re-vegetated areas.
B3. Upland areas on the Main Property (i.e., areas landward of the minimum 100-foot
shoreline setback from Lake Washington’s ordinary high water mark (OHWM)) shall be
temporarily re-vegetated (e.g., with hydro-seed) following site remediation, if building
permits for the disturbed area have not been filed with the City of Renton.
Following Construction
B4. Proposed redevelopment shall avoid direct impacts to the on-site wetlands retained/re-
established and/or expanded as part of EPA’s Record of Decision (ROD) for the
remediation project or any Natural Resource Damages (NRD) settlement.
B5. Retained/re-established and/or expanded wetlands, associated buffers, and all other
habitat restoration areas required as part of EPA’s anticipated ROD for the remediation
project or any NRD settlement shall be retained within and be a function of the open
space tract(s).
B6. Proposed buildings shall be setback a minimum of 100 feet from the OHWM, consistent
with the City of Renton’s 2011 Shoreline Master Program.
Quendall Terminals iv
Mitigation Document
August 2015
B7. A permanent stormwater control system shall be installed consistent with the applicable
requirements. The system shall collect and convey stormwater runoff to Lake
Washington via a tight-lined system or another system approved by the City’s
responsible public official. Water quality treatment shall be provided for runoff from
pollution-generating surfaces to prevent water quality impacts to the lake and shoreline
wetlands.
B8. Native plant species shall be included within landscaping of the redeveloped upland area
on the Main Property to the extent feasible, and could provide some limited habitat
benefits to native wildlife species.
B9. Introduction of noxious weeds or invasive species shall be avoided to the extent
practicable in areas re-vegetated as part of the proposed redevelopment. Together with
the native species planted, this shall help limit the unnecessary spread of invasive
species that could adversely affect the suitability of open space habitats on site and in
the vicinity for wildlife.
B10. A publicly accessible, unpaved trail with interpretive viewpoints shall be provided through
the minimum 100-foot shoreline setback area unless the trail is prohibited by the EPA
ROD or any NRD settlement. If EPA’s ROD or any NRD settlement prohibit the trail, the
trail shall be relocated to the west side of the westernmost buildings onsite, and could be
combined with the fire access road.
B11. The proposed redevelopment shall include design elements to minimize the potential
adverse effects of artificial lighting on wetland, shoreline and riparian habitats, and
adjacent properties. These elements shall include directing lighting downward and away
from these habitats and adjacent properties, and shall also include shielding of lights,
use of low-pressure sodium lights, and/or minimizing the use of reflective glazing
materials in building design, as feasible.
C. Environmental Health
C1. Redevelopment of the site is being coordinated with the cleanup/remediation process,
and shall be conducted consistent with the requirements in the final cleanup remedy
selected and overseen by EPA, and with any associated institutional controls.
C2. The appropriate management of contaminated soils that could be disturbed and
groundwater that could be encountered during redevelopment of the site shall be
addressed through the cleanup/remediation process and by institutional control
requirements overseen by EPA. As necessary, lightweight fill materials, special capping
requirements, vapor barriers, and/or other measures shall be implemented to ensure
that unacceptable exposures to contaminated soils, groundwater, or vapors shall not
occur.
C3. Institutional controls shall be followed to prevent alteration of the site cap (should it be
installed) without EPA approval, and to prevent the use of on-site groundwater for any
purpose.
Quendall Terminals v
Mitigation Document
August 2015
C4. An Operations, Maintenance, and Monitoring Plan (OMMP) shall be implemented to
prevent the excavation of soils, installation of utilities, or other site disturbances without
prior EPA approval.
C5. As necessary, personal protection equipment for workers shall be used and special
handling and disposal measures followed during construction activities to prevent
contact with hazardous materials and substances.
C6. Institutional controls specified by EPA shall also be implemented to prevent exposure to
unacceptable vapors.
C7. If approved by EPA, utilities (including the main utility corridors) shall be installed as part
of the planned remedial action so that disturbance of the site cap (should it be installed)
and underlying contaminated soils/groundwater would not be necessary subsequent to
capping of the Main Property.
C8. Personal protection measures and special training costs shall be funded by the applicant
for City of Renton staff who provide inspection during construction and maintenance
following construction in areas where there is a potential to encounter contaminated soils
or groundwater.
C9. If approved by EPA, buried utilities, public roads, and infrastructure serving the site
development shall be placed in clean fill material (with the utilities in a trench with
sufficient width and depth of 3 to 4 feet below the invert of the utility), along with an
acceptable barrier to prevent recontamination of the clean fill material, in order to protect
the utility from contamination and to allow future maintenance of the road or utility lines.
If the above is not approved by EPA, no public utility lines shall be installed until the
applicant, EPA, and the City agree upon appropriate protection measures for future road
and utility maintenance.
C10. If EPA issues a ROD that is different than what is assumed in the Quendall Terminals
EIS, the City reviewing official shall determine whether the applicant shall be required to
prepare additional SEPA review, including a possible Supplement to the EIS or
Addendum to the EIS, to address any differences between the ROD and the
assumptions in the EIS.
D. Energy – Greenhouse Gas Emissions
D1. Development may incorporate low-impact/sustainable design features into the design of
proposed buildings on the site to reduce the demand for energy and reduce the amount
of greenhouse gas emissions. Such features could include architectural design features;
sustainable building materials; use of energy efficient products; natural drainage/green
roof features; use of native plants in landscaping; and/or other design features.
E. Land and Shoreline Use
E1. New driveways, landscaping, surface parking areas, and proposed building setback
areas shall be designed and constructed to provide a buffer between proposed buildings
and land uses on adjacent properties.
Quendall Terminals vi
Mitigation Document
August 2015
E2. Proposed landscaping, particularly along the north and south boundaries of the Main
Property, shall be designed and constructed to provide a partial visual screen between
proposed buildings and adjacent uses.
E3. Architectural features (i.e., roof slope, façade modulation, building materials, etc.) shall
be incorporated into the design of each building and are intended to enhance the
compatibility between the proposed development and surrounding land uses.
E4. As shown in the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), building heights shall be modulated to reduce potential
height/bulk/scale impacts on adjacent development (i.e., Barbee Mill); Building SW4
located adjacent to the southwest property line shall be 4 stories high; other buildings
shall be 5 to 6 stories high.
E5. A fire mitigation/impact fee shall be determined and paid for the proposed development
at the time of building permit issuance and as required by the Renton Municipal Code to
help offset the impacts of the project on the City’s fire emergency services.
F. Aesthetics/Views
F1. Building design shall include a variety of details and materials that are intended to create
a human scale and provide a visually interesting streetscape and façade, such as
horizontal plan modulation, projecting vertical elements, and alternating façade materials
and details.
F2. Street-level, under-building parking areas shall be screened from sidewalks and streets
by retail and commercial uses along certain façades. Where this parking extends to the
exterior of the building, elements, such as architectural façade components, trellises,
berms, and landscaping shall be used for screening.
F3. Public view corridors toward Lake Washington shall be provided along the main
east/west roadway onsite (Street “B”) and along the private driveways at the north and
south ends of the site. Public views of the lake shall also be provided from the publically
accessible trail in the minimum 100-foot shoreline setback area in the western portion of
the Main Property, if the trail is not prohibited by EPA or any NRD settlement. If EPA’s
ROD or any NRD settlement prohibit the trail, the trail shall be relocated to the west side
of the westernmost buildings onsite, and could be combined with the fire access road.
Additional views of the lake shall be provided for project residents from semi-private
landscaped courtyard areas between the new buildings onsite.
F4. New landscaping shall be provided in the upland area of the Main Property that is
intended to enhance the visual character of the site. Landscaping shall include new
trees, shrubs, and groundcovers of various sizes and species.
F5. Proposed landscaping along the north and south property lines shall be designed and
constructed to provide a partial visual screen between proposed buildings and adjacent
uses.
Quendall Terminals vii
Mitigation Document
August 2015
F6. The natural vegetation in the minimum 100-foot shoreline setback area and/or other site
areas established or protected by EPA’s ROD or any NRD settlement shall be retained
with proposed site development.
F7. Exterior building lighting, parking lot lighting, and pedestrian lighting shall be directed
downward and away from surrounding buildings, properties, and the shoreline of Lake
Washington to minimize the impacts to adjacent uses and fish.
F8. As indicated in the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), building setbacks shall be provided adjacent to Lake Washington
and along the south site boundaries, to enhance the aesthetic character of development
and retain views of Lake Washington.
F9. Building height modulation shall be provided across the site to enhance the aesthetic
character of development and retain some views of Lake Washington.
F10. No surface parking shall be located at the terminus of Street “B” in order to enhance the
aesthetic character of the development, particularly from the shoreline trail, if the trail is
located within the minimum 100-foot shoreline setback area and not prohibited by EPA’s
ROD or any NRD settlement. If EPA’s ROD or any NRD settlement prohibit the trail
within the minimum 100-foot shoreline setback area, the trail shall be relocated to the
west side of the westernmost buildings onsite, and could be combined with the fire
access road.
F11. During final building design, maximum building heights 100 feet from the Lake
Washington OHWM shall be reduced to one half of the maximum height allowed by the
COR zone (125 feet allowed height x ½ = 62.5 feet), consistent with the City of Renton’s
2011 Shoreline Master Program, which will help maintain views toward the lake.
F12. As determined by the City’s responsible public official, the amount of required parking
may be reduced, relocated, and/or redesigned (i.e., through implementation of
transportation demand management (TDM) measures or other means) so that additional
areas of the street-level, under-building parking can be setback from the exterior of the
building, particularly along Streets “A”, “C,” and the lake side of the development. This
will allow other uses, including retail, restaurant, commercial, and residential uses, and
plaza areas to occupy these areas and enhance the aesthetic character at the ground
level.
F13. Reflectivity of glazing materials, as well as the use of shading devices, shall be
considered as part of the façade design in order to minimize the potential glare impacts
to surrounding uses.
F14. Design features such as: public art, special landscape treatment, additional open
space/plazas, landmark building form, special paving/pedestrian scale lighting, and/or
prominent architectural features shall be provided as part of development to further
enhance the gateway/landmark features on the site.
F15. Vertical and/or horizontal modulation shall be provided along the west or lake side of the
buildings to provide a human scale and break up the larger structures which will be
adjacent to the shoreline area and pedestrian environment.
Quendall Terminals viii
Mitigation Document
August 2015
G. Parks and Recreation
Measures to Improve Public Open Space and Related Areas/Fees1
G1. A parks mitigation/impact fee shall be determined and paid for each multifamily unit in
the proposed development at the time of building permit issuance and in accordance
with the City of Renton Municipal Code.
G2. As shown on the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), approximately 10.6 acres of “Natural Public Open Space Areas”
and “Other Related Areas” shall be provided on the site. The “Natural Public Open
Space Areas” shall include the approximately 0.5-acre trail within the minimum 100-foot
shoreline setback area, and approximately 3.2 acres of natural area along the trail. If
EPA’s ROD or any NRD settlement prohibits the trail, the trail shall be relocated to the
west side of the westernmost buildings onsite, and could be combined with the fire
access road. It is the City’s intent that the natural area along the trail be used for
retained/re-established and/or expanded wetlands, associated buffers, and all other
habitat restoration areas required as part of EPA’s ROD for the remediation project or
any NRD settlement. The “Other Related Areas” onsite shall include street-level
landscaping, landscaped courtyards, sidewalks, paved plazas, and the Isolated
Property. These areas may or may not meet the City’s standards, regulations, and
procedures for public open space. If EPA’s ROD or any NRD settlement result in
alterations to the plans for the Preferred Alternative, including the “Natural Public Open
Space Areas” or “Other Related Areas,” the City could re-evaluate the plans.
G3. Frontage improvements, including sidewalks, shall be provided along the west side of
Lake Washington Boulevard and Ripley Lane N along the site. These sidewalks shall
connect to sidewalks to the north and south, which connect to other pedestrian facilities
in the area.
G4. If the trail through the minimum 100-foot shoreline setback area is not prohibited by
EPA’s ROD or any NRD settlement, public parking shall be provided in the same general
area as the retail/restaurant parking; the applicant shall specifically identify this parking
prior to site plan approval. If EPA’s ROD or any NRD settlement prohibit the trail, the trail
shall be relocated to the west side of the westernmost buildings onsite, and could be
combined with the fire access road; public parking shall be provided for the relocated
trail as described above. Public parking spaces shall be provided as required by the
Renton Municipal Code and the Shoreline Master Program and shall be identified as
public by signage or other means approved by the City.
G5. Signage, detours, and safety measures shall be put in place to detour bicyclists from
using the Lake Washington Loop trail at the time of construction.
G6. If the trail through the minimum 100-foot shoreline setback area is not prohibited by EPA
or any NRD settlement, the connection between the trail and Lake Washington
Boulevard shall be enhanced by providing wider sidewalks (i.e., 15-foot wide) that are
part of public rights-of-way along the Street “B” corridor. If EPA’s ROD or any NRD
1 Hours of public access shall meet park standards of sunrise to sunset to count toward public recreation.
Quendall Terminals ix
Mitigation Document
August 2015
settlement prohibits the trail, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road. The
connection of the relocated trail to Lake Washington Boulevard shall also be enhanced
by providing wider sidewalks (i.e., 15-foot wide), as described above.
G7. If the trail through the minimum 100-foot shoreline setback area is not prohibited by EPA
or any NRD settlement, the hours of public use (i.e., not the residents’ use) of the trail
shall be determined by the City’s Community Services Administrator. If EPA’s ROD or
any NRD settlement prohibit the trail, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road; the
hours of public use (i.e., not the residents’ use) of the trail shall be determined by the
City’s Community Services Administrator.
G8. Approximately 1.8 acres of indoor and/or outdoor area shall be provided onsite for active
recreation (e.g., Frisbee, swimming pools, tot lots, bocce ball courts, exercise rooms,
active recreation in courtyards, etc.), as approved by the City’s responsible public
official.
G9. A crosswalk including pedestrian crossing warning signs at and in advance of the
crosswalk shall be provided across Lake Washington Boulevard in order to connect the
proposed development to the May Creek Trail on the east side of the Boulevard. The
crosswalk shall be controlled by Rectangular Rapid Flashing Beacons, if the City
determines that such lighting is warranted.
G10. If the trail through the minimum 100-foot shoreline setback area is not prohibited by EPA
or any NRD settlement, the trail and other recreation areas shall be enhanced with site
amenities, such as tables, litter receptacles, benches, interpretive signage, etc., and
approved by the City’s Community Services Administrator. If EPA’s ROD or any NRD
settlement prohibit the trail, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road; the trail
and other recreation areas shall be enhanced with site amenities, such as tables, litter
receptacles, benches, interpretive signage, etc. and approved by the City’s Community
Services Administrator.
G11. The trail shall connect to the Barbee Mill residential development to the south. If EPA’s
ROD or any NRD settlement prohibits the trail, the trail shall be relocated to the west
side of the westernmost buildings onsite, and it could be combined with the fire access
road; the trail shall connect to the Barbee Mill residential development to the south.
Measures to Improve Semi-Private Recreation Access for Residents
G12. As part of the total open space, semi-private landscaped courtyards on top of the
parking garages shall be provided as shared open space for residents of the site. These
areas shall help to meet the demand for recreation facilities from project residents.
G13. Street level landscaping, plazas, and sidewalks shall be provided. These areas will help
meet the project’s demand for passive recreation facilities.
Quendall Terminals x
Mitigation Document
August 2015
H. Transportation
With or Without Planned I-405 Improvements
H1. A traffic mitigation/impact fee shall be determined and paid for the proposed
development at the time of building permit issuance and in accordance with the City of
Renton Municipal Code to help offset the impacts of the project on the City’s roadways.
H2. TDM measures shall be implemented to reduce the number of vehicle trips and thus
provide some benefit to improving LOS and queuing impacts at study intersections.
H3. Infrastructure improvements within the site shall include full curbs, gutters, sidewalks,
and landscape strips (where applicable) as well as frontage improvements (curb, gutter,
sidewalk, landscape strips, bike lanes, pavement width, and utilities) along the west side
of Lake Washington Boulevard and Ripley Lane N in front of the project site. Provisions
for safe pedestrian circulation shall encourage future transit usage to and from the site
when planned public transit becomes available.
H4. If approved by EPA and any NRD settlement, a pedestrian trail shall be provided onsite
through the minimum 100-foot shoreline setback area that shall be accessible to the
public and shall connect to Lake Washington Boulevard through the internal site
sidewalk system. If EPA’s ROD or any NRD settlement prohibits the trail, the trail shall
be relocated to the west side of the westernmost buildings onsite, and could be
combined with the fire access road; this trail shall connect to Lake Washington
Boulevard through the internal site sidewalk system.
H5. To mitigate traffic impacts to the Lake Washington Boulevard corridor south of the
development, the applicant shall install traffic calming treatments on Lake Washington
Boulevard south of N 41st Street to encourage primary trips generated by the project to
utilize the I-405 corridor. Although the City of Renton has no adopted residential traffic
management program, arterial calming measures could include treatments that create
either horizontal or vertical deflection for drivers. Such treatments could include, but not
limited to chicanes, serpentine raised curb sections, raised median treatments, speed
tables, and/or speed humps. Final design of traffic calming elements shall be approved
by the City.
H6. The parking supply under the Preferred Alternative shall meet the minimum off-street
parking requirements of the City of Renton.
H7. Shared parking agreements between on-site uses and implementation of TDM
measures for proposed residential uses shall be implemented to reduce parking demand
during peak periods, thereby reducing the necessary parking supply.
H8. A fire access road shall be provided to the west of the westernmost buildings onsite. The
road shall be a minimum of 20 feet wide, and shall be constructed with crushed rock or
grass-crete to support the weight of fire apparatus, and shall be available for emergency
vehicle access. If located in the minimum 100-foot shoreline setback area, and approved
by the EPA ROD and any NRD settlement, the road shall also serve as a pedestrian
trail. If EPA’s ROD or any NRD settlement prohibit the fire access road within the
Quendall Terminals xi
Mitigation Document
August 2015
minimum 100-foot shoreline setback area, the road shall be relocated to the west side of
the westernmost buildings onsite, and could be combined with the trail.
H9. In order to promote a multimodal transportation network, redevelopment on the Quendall
Terminals site shall include site amenities (i.e., planting strips, street lighting, etc.) and
access to future transit zones on Lake Washington Boulevard and at the I-405/NE 44th
Street interchange to encourage and accommodate public transportation access in the
future (future potential public transportation in the vicinity could include Bus Rapid
Transit on I-405 planned by Sound Transit and Washington State Department of
Transportation (WSDOT) with a flyer stop at the I-405/NE 44th Street interchange).
H10. A paved bicycle lane shall be provided along the east and west sides of Ripley
Lane/Lake Washington Boulevard from the end of the current bike trail along Ripley
Lane to the intersection of Ripley Lane/Lake Washington Boulevard or a multi-use path
could be developed on one side or separated from Ripley Lane/Lake Washington
Boulevard to mitigate potential conflicts between bicycles and the Quendall Terminals
site access point on Ripley Lane.
With Planned I-405 Improvements
H11. Lake Washington Boulevard between Barbee Mill Access (N 43rd Street) and Ripley
Lane N. The eastbound and westbound through lanes planned by WSDOT shall be
extended beyond and through the Barbee Mill access intersection. This shall result in
two through lanes in each direction on Lake Washington Boulevard from the I-405
interchange past the Barbee Mill access (N 43rd Street). Ultimately, the City of Renton
shall determine the best configuration for the improvements, given ongoing coordination
with WSDOT on the adjacent interchange design, King County (owner of the vicinity rail
right-of-way), and adjacent private development.
H12. Barbee Mill Access (N 43rd Street)/Lake Washington Boulevard. A traffic signal shall
be installed at this intersection. At the Barbee Mill Access (N 43rd Street)/Lake
Washington Boulevard intersection the eastbound approach shall be widened to include
a separate left-turn only lane and the northbound approach shall be widened to include a
separate left-turn only lane. Ultimately, the City of Renton shall determine the best
configuration for the improvements, given ongoing coordination with WSDOT on the
adjacent interchange design, King County (owner of the vicinity rail right-of-way), and
adjacent private development. If the traffic signal and eastbound left turn lane at N 43rd
Street have not been constructed prior to the WSDOT improvements at the NE 44th
Street/I-405 interchange, the City will consider changing the location of this signal to the
intersection at Ripley Lane/Lake Washington Boulevard. Relocating the traffic signal to
Ripley Lane/Lake Washington Boulevard. could reduce/eliminate potential impacts of
traffic queues on N 43rd Street between Lake Washington Boulevard and Road A, and
with the existing rail crossing (should it be re-activated for rail service or converted to a
trail corridor). An engineering study will be completed at that time to support the
determination of the location for the installation of the traffic signal at either N 43rd Street
or Ripley Lane.
Quendall Terminals xii
Mitigation Document
August 2015
Without Planned I-405 Improvements
H13. Traffic Signals. Traffic signals shall be installed at the intersections of the I-405
northbound and southbound ramp intersections, as well as at the intersection of Barbee
Mill Access (N 43rd Street)/Lake Washington Boulevard. The City will consider moving
the location of this signal to the intersection at Ripley Lane/Lake Washington Boulevard
as part of a future WSDOT improvement project to the NE 44th Street interchange.
Relocating the traffic signal to Ripley Lane/Lake Washington Boulevard could
reduce/eliminate potential longer-range impacts of traffic queues on N 43rd Street
between Lake Washington Boulevard and Road A, and with the existing rail crossing
(should it be re-activated for rail service or converted to a trail corridor). An engineering
study will be completed at that time to support the determination of the location for the
installation of the traffic signal at either N 43rd Street or Ripley Lane.
H14. Intersection #1 - I-405 Northbound Ramps/NE 44th Street. The southbound and
northbound approaches shall be widened so that a separate left turn lane and shared
thru-right turn lane is provided on both legs of the intersection. The final configuration of
the intersection with the additional widening improvements shall be coordinated with
WSDOT.
H15. Lake Washington Boulevard between Barbee Mill Access (N 43rd Street) and I-405
Southbound Ramps. Additional channelization improvements between the Barbee Mill
access and the I-405 southbound ramps shall be constructed. Additional eastbound and
westbound lanes shall be constructed to provide additional queue storage created by the
traffic signals required at the southbound ramp and Barbee Mill Access (N 43rd Street)
along Lake Washington Boulevard. At the Barbee Mill Access (N 43rd Street)/Lake
Washington Boulevard intersection the westbound approach on the Barbee Mill Access
shall be widened to include a separate left-turn only lane and the northbound approach
on Lake Washington Boulevard shall be widened to include a separate left-turn only
lane. Ultimately, the City of Renton shall determine the best configuration for the
improvements, given ongoing coordination with WSDOT on the adjacent interchange
design, King County (owner of the vicinity rail right-of-way), and adjacent private
development.
I. Cultural Resources
I1. Limited and focused cultural resource monitoring shall be conducted during construction
activities on the site (clearing and grading of the upland portion, construction of deep
building foundations, and excavation of utilities). During construction, a monitoring plan
and inadvertent discovery plan shall be developed as part of the project (see Appendix F
to the Quendall Terminals EIS Addendum for a copy of the proposed monitoring plan
and inadvertent discovery plan).
I2. In the unlikely event that ground-disturbing or other activities result in the inadvertent
discovery of archaeological deposits, construction activities shall be halted in the
immediate area and the Washington State Department of Archaeology and Historic
Preservation (DAHP) shall be contacted. Work shall be halted until such time as further
investigation and appropriate consultation is concluded.
Quendall Terminals xiii
Mitigation Document
August 2015
I3. In the unlikely event of the inadvertent discovery of human remains, construction shall
be halted in the area, the discovery shall be covered and secured against further
disturbance, and contact shall be made with law enforcement personnel, DAHP, and
authorized representatives of the concerned Indian tribes.
J. Construction Impacts
Air Quality
J1. Site development and construction activities shall comply with applicable Puget Sound
Clean Air Agency (PSCAA) regulations regarding demolition activities and fugitive dust
emissions. If approved by the EPA, wetting of exposed soils, covering or wetting
transported earth materials, washing of truck tires and undercarriages prior to travel on
public streets, and prompt cleanup of any materials tracked or spilled onto public streets
shall be provided.
J2. The EPA cleanup/remediation process for the site and associated institutional control
requirements shall ensure that unacceptable exposures to contaminated soils/dust and
vapors shall not occur during or following construction. An OMMP shall be implemented
to prevent the excavation of soils, installation of utilities, and other site disturbances
without prior EPA approval.
Noise
J3. Per the City of Renton’s construction standards related to permitted hours of work (RMC
4-4-030C), commercial and multifamily construction activities within 300 feet of
residential areas shall be restricted to the hours of 7:00 AM to 8:00 PM, Monday through
Friday. Work on Saturdays shall be restricted to the hours of 9:00 AM to 8:00 PM and no
work shall be permitted on Sundays. The City of Renton Development Services Director
shall be required to approve any work outside of these construction hours via a variance.
J4. Noise from construction shall be governed by the timing restrictions and the noise limits
included in the King County noise code requirements (KCC Section 12.88.040). This rule
defines maximum permissible sound levels based on the zoning of the source and
receiving properties and sets maximum levels and durations of allowable daytime
construction noise.
Quendall Terminals 1
Mitigation Document
August 2015
QUENDALL TERMINALS PROJECT
MITIGATION DOCUMENT
INTRODUCTION AND PURPOSE
The applicant submitted Applications for the Quendall Terminals project in 2009; the City of
Renton determined that the Applications were complete on February 5, 2010. In order to meet
SEPA requirements, the Environmental Review Committee for the City of Renton issued the
Quendall Terminals Draft Environmental Impact Statement (DEIS) on December 10, 2010, the
Quendall Terminals EIS Addendum on October 19, 2012, and the Quendall Terminals Final
Environmental Impact Statement (FEIS) on August 31, 2015. The purpose of this Mitigation
Document is to establish specific mitigation measures and discuss these measures, based upon
significant impacts that were identified in the DEIS, EIS Addendum, and FEIS.
USE OF TERMS
The subject site may be referenced as the “Quendall Terminals site” or “site” in this Mitigation
Document.
EIS preparation was triggered by applications submitted for Master Site Plan Approval, Binding
Site Plan Approval, and Shoreline Substantial Development Permit, collectively, the
“Applications”.
The “Proposal” covered by the EIS and addressed in this Mitigation Document includes the
construction and operation of the Quendall Terminals Redevelopment Project substantially as
proposed in the foregoing Applications, as revised on June 25, 2012.
In the Quendall Terminals DEIS (2010) and the Quendall Terminals EIS Addendum (2012), the
phrase “Shoreline Restoration Area” is used to indicate the building setback area from the Lake
Washington ordinary high water mark (OHWM) in which a number of shoreline-related site
cleanup and remediation activities would occur under the oversight of the U.S. Environmental
Protection Agency (EPA), and in which a number of restoration activities could potentially occur
if a settlement is reached with the Natural Resource Trustees. In the list of mitigation measures
in this Mitigation Document and in the Quendall Terminals FEIS (2015), the phrase “Shoreline
Restoration Area” has been replaced with the phrase “minimum 100-foot shoreline setback
area.” This change was made in order to clarify that this area was set aside for activities that
include retention/re-establishment and/or expansion of wetlands, and provision of associated
buffers, as anticipated to be required by EPA in the Record of Decision (ROD) for the
remediation project and any Natural Resource Damage (NRD) settlement.
SEPA REQUIREMENTS
State regulations (WAC 197-11) and local regulations (RMC Title 4, Chapter 9) govern the
development of mitigation measures to address identified environmental impacts. The primary
regulatory chapters are cited below.
WAC 197-11-060, titled Content of Environmental Review, states in part that agencies shall
“carefully consider the range of probable impacts, including short-term and long-term effects”
Quendall Terminals 2
Mitigation Document
August 2015
including “those that are likely to arise or exist over the lifetime of a proposal” or in some cases,
continues beyond the life of the proposal.
WAC 197-11-330, titled Threshold Determination Process, requires in part that the responsible
official take into account the direct, indirect, and cumulative effects of a proposal when
determining whether a proposal has significant adverse impacts. In reaching a decision, SEPA
states that the responsible official shall not balance whether the beneficial aspects of a proposal
outweigh the adverse impacts, but rather shall consider whether a proposal has any probable
significant adverse environmental impacts.
WAC 197-11-768 titled Mitigation, defines mitigation as the following:
1. Avoiding the impacts altogether by not taking a certain action or parts of an action;
2. Minimizing the impacts by limiting the degree or magnitude of the action and its
implementation, by using appropriate technology, or by taking affirmative steps to
avoid or reduce impacts;
3. Rectifying the impact by repairing, rehabilitating, or restoring the affected
environment;
4. Reducing or eliminating the impact over time by preservation and maintenance
operations during the life of the action;
5. Compensating for the impact by replacing, enhancing, or providing substitute
resources or environments; and/or,
6. Monitoring the impact and taking appropriate corrective measures.
WAC 197-11-660(1) titled Substantive Authority and Mitigation, states that decision-makers may
impose mitigation measures designed to mitigate the environmental impacts, subject to the
following limitations:
A. Mitigation measures or denials shall be based on policies, plans, rules, or regulations
formally designated by the agency;
B. Mitigation measures shall be related to specific, adverse environmental impacts
clearly identified in an environmental document on the proposal and shall be stated
in writing by the decision-maker;
C. Mitigation measures shall be reasonable and capable of being accomplished;
D. Responsibility for implementing mitigations measures may be imposed upon an
applicant only to the extent attributable to the identified adverse impacts of its
proposal. Voluntary additional mitigation may occur;
E. Before requiring mitigation measures, agencies shall consider whether local, state, or
federal requirements and enforcement would mitigate an identified significant impact;
and,
Quendall Terminals 3
Mitigation Document
August 2015
F. If, during project review, a jurisdiction’s development regulations or comprehensive
plan adopted under Chapter 36.70A RCW, or in other applicable local, state, or
federal laws or rules, provided adequate analysis of and mitigation for the specific
adverse environmental impacts of the project action under RCW 43.21C.240, the
jurisdiction shall not impose additional mitigation under this chapter.
MITIGATION DOCUMENT
This Mitigation Document identifies the mitigation measures established under the SEPA rules
to address specific impacts identified in the Quendall Terminals DEIS, Quendall Terminals EIS
Addendum, and Quendall Terminals FEIS. Numerous state and local regulations will serve to
govern development of the Quendall Terminals site, and application of those regulations will
also serve to mitigate certain significant adverse environmental impacts. Additional consistency
review will be conducted by the City of Renton under the Master Site Plan, Binding Site Plan,
Site Plan, and Shoreline Substantial Development Permit; reviews for permits by other agencies
will also be conducted.
Provided below for each element of the environment analyzed in the DEIS, EIS Addendum, and
FEIS are: 1) References to text for Affected Environment and Impacts sections within the DEIS,
EIS Addendum, and/or FEIS; 2) Mitigation measures; 3) Discussion of the mitigation measures;
and, 4) Policy nexus.
A. Earth
Refer to DEIS Section 3.1 and EIS Addendum Section 4.1 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on geotechnical conditions. The
mitigation measures below address the identified earth-related impacts of the project.
Mitigation Measures and Discussion
During Construction
A1. A temporary erosion and sedimentation control plan (TESCP), including Best
Management Practices (BMPs) for erosion and sedimentation control, shall be
implemented. This plan shall include, but not limited, to the following measures:
All temporary (and/or permanent) devices used to collect stormwater runoff shall
be directed into tightlined systems that shall discharge to an approved
stormwater facility.
Soils to be reused at the site during construction shall be stockpiled or stored in
such a manner to minimize erosion from the stock pile. Protective measures shall
include covering with plastic sheeting and the use of silt fences around pile
perimeters.
During construction, silt fences or other methods, such as straw bales, shall be
placed along surface water runoff collection areas in proximity to Lake
Washington and the adjacent wetlands to reduce the potential of sediment
discharge into these waters. In addition, rock check dams shall be established
along roadways during construction.
Temporary sedimentation traps or detention facilities shall be installed to provide
erosion and sediment transport control during construction.
Quendall Terminals 4
Mitigation Document
August 2015
The project construction shall adhere to the wet season construction
requirements between October 1st and April 30th.
A2. A geotechnical engineer that is a Certified Professional in Erosion and Sediment Control
or a Certified Erosion and Sediment Control Lead shall review the grading and TESCP
plans prior to final plan design to ensure that erosion and sediment transport hazards
are addressed during and following construction. As necessary, additional erosion
mitigation measures could be required in response to specific design plans.
Discussion:
As listed above, a variety of BMPS shall be included as part of the TESCP for the project to limit
erosion and sedimentation during construction. Site work shall be phased to minimize the
amount of soil exposed during construction. The TESCP shall be available at the site and the
BMPs shall be in place prior to the start of construction. By effectively using construction BMPs,
erosion, sediment-laden water, and dust will be controlled and adverse impacts to water
resources will be reduced. Also see the discussion under mitigation measure B1 below of the
Stormwater Pollution Prevention Plan (SWPPP) that will be required for the National Pollution
Discharge Elimination System (NPDES) Construction Stormwater General Permit for the
project.
A3. Site preparation for roadways, utilities, and structures, and the placement and
compaction of structural fill shall be based upon the recommendations of a geotechnical
engineer.
A4. Temporary excavation dewatering shall be conducted if groundwater is encountered
during excavation and construction activities. Such dewatering activities shall be
conducted in a manner that shall minimize potential impacts due to settlement.
A5. A geotechnical engineer shall determine whether structural fill shall be placed to control
the potential for settlement of adjacent areas; adjacent structures/areas shall be
monitored to verify that no significant settlement occurs.
A6. A geotechnical engineer shall determine whether deep foundation systems (such as
piles or aggregate piers) shall be installed and/or ground improvements made to
minimize potential damage from soil settlement, consolidation, spreading, and
liquefaction.
A7. If deep foundation systems (such as piles or aggregate piers) are used to support
structures, the following measures shall be implemented:
Measures shall be employed to ensure that the site cap (i.e., soils/impervious
surfaces, should they be installed) shall not be affected and that installation of
the piles/piers shall not mobilize contamination that shall be contained by the
cap. The U.S. Environmental Protection Agency (EPA) shall determine the
appropriate measures to be employed, which could include: installation of
surface casing through the contaminated zone; installation of piles composed of
impermeable materials (steel or cast-in-place concrete) using soil displacement
methods; the use of pointed-tip piles to prevent carry down of contamination;
and/or, the use of ground improvement technologies, such as in-place
densification or compaction grouting.
Quendall Terminals 5
Mitigation Document
August 2015
A pile vibration analysis and vibration monitoring shall be conducted during pile
installation in order to ensure that impacts due to vibration do not occur.
Suitable pile and pile hammer types shall be matched to the subsurface
conditions to achieve the required penetrations with minimal effort to reduce
potential vibration. Potential pile types could include driven open-end steel pipe
piles, driven closed-end steel pipe piles, or driven cast-in-place concrete piles.
Potential hammer types could include percussion hammers or vibratory
hammers.
Suitable hammer and pile cushion types shall be used for the specific conditions
to reduce potential noise. A typical hammer employs the use of a heavy impact
hammer that is controlled by a lead, which is in turn supported by a crane.
Pile installation shall occur during regulated construction hours.
A8. Fill soils shall be properly placed and cuts shall be used to reduce the potential for
landslide impacts during (and after) construction.
A9. The appropriate management of contaminated soils that could be disturbed and
groundwater that could be encountered during redevelopment of the site shall be
addressed through the cleanup/remediation process and by institutional control
requirements overseen by the EPA.
Following Construction
A10. A permanent stormwater control system shall be installed in accordance with applicable
stormwater regulations.
A11. Offshore outfall locations for stormwater discharge from the permanent stormwater
control system shall be equipped with energy dissipation structures or other devices to
prevent erosion of the lake shoreline and bottom.
A12. All buildings shall be designed in accordance with the International Building Code to
address the potential for seismic impacts.
A13. The majority of the site will be covered with impervious surfaces following
redevelopment. Permanent landscaping shall also be provided to reduce the potential for
erosion and sedimentation with redevelopment.
A14. Flexible utility connections shall be employed to minimize the risk of damage to utility
lines due to differential settlement between structures and underground utilities, as
needed and as determined by the City’s responsible public official.
Discussion:
Prior to submittal of building permit application(s), the applicant shall provide geotechnical
analyses prepared by a geotechnical engineer to the City that address the appropriateness of
the above construction-related measures. The analyses of the potential need to place fill to
control settlement and the need for deep foundation systems (measures A5 and A6) shall be
prepared by a geotechnical engineer in conjunction with the project architect and structural
engineer.
Quendall Terminals 6
Mitigation Document
August 2015
Regarding measure A9, see the discussion following measures C1 through C10 for discussion
of appropriate management of contaminated soils that could be disturbed and groundwater that
could be encountered during site redevelopment.
Due to the nature of the soils that underlie the site (unconsolidated granular and soft fine
grained sediments) and the regional tectonic setting (high seismic risk), several geotechnical
issues related to project design and construction are identified in the Quendall Terminals DEIS.
These issues include: 1) the presence of soft and loose soils to depths of approximately 40 feet
below planned site grades; 2) the presence of potentially liquefiable, saturated granular soils to
depths of approximately 80 feet below planned site grades; and, 3) the potential lateral
movement of soil above liquefiable zones. These issues and potential impacts related to
settlement of the site and proposed structures and utilities shall be mitigated by the measures
listed above, appropriate project design, and proper implementation of the design during
construction.
Policy Nexus:
City of Renton Environmental Review Procedures (RMC 4-9-070); City of Renton Building
Standards (RMC 4-5); City of Renton Grading, Excavation and Mining Regulations (RMC 4-4-
60); City of Renton Drainage (Surface Water) Standards (RMC 4-6-030); and, City of Renton
Utility Lines – Underground Installation Standards (RMC 4-6-090).
B. Critical Areas
Refer to DEIS Section 3.2 and EIS Addendum Section 4.2 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on critical areas (e.g., Lake
Washington and the shoreline wetlands). The mitigation measures below address the identified
critical areas-related impacts of the project.
Mitigation Measures and Discussion
During Construction
B1. A TESCP, including BMPs for erosion and sedimentation control, shall be implemented
during construction. Implementation of this plan shall prevent or limit impacts to the lake
and shoreline wetlands from erosion and sedimentation.
Discussion:
A National Pollution Discharge Elimination System (NPDES) Construction Stormwater General
Permit will be required for the project and calls for preparation and implementation of a
Stormwater Pollution Prevention Plan (SWPPP). The SWPPP shall include temporary erosion
and sedimentation control requirements and BMPs for construction activities in order to prevent
stormwater from washing soil, nutrients, chemicals, and other harmful pollutants into the critical
areas on and adjacent to the site (e.g., shoreline wetlands and Lake Washington). The SWPPP
shall include the following measures:
Mark Clearing Limits: Prior to clearing or disturbing, the limits shall be marked. This
element is part of most typical construction plans as one of the first steps.
Quendall Terminals 7
Mitigation Document
August 2015
Establish Construction Access: All erosion control plans shall install a stabilized
construction entrance (or other method of preventing sediment transport onto the
roads). If a standard gravel construction entrance is proposed, geo-textile fabric shall
be used under the rock.
Detain Flows: Based on a downstream analysis, runoff from the site under
construction shall be provided, as necessary. A detention or temporary sediment
pond shall be used to control flows during construction, as necessary.
Install Sediment Controls: If there is runoff from the construction site, sediment shall
be removed from the water. Water quality standards shall be met prior to discharge
to Lake Washington.
Stabilize Soils: All exposed and non-worked soil shall be stabilized by use of BMPs.
Seasonal requirements limiting time periods of allowed exposure shall be followed.
Both temporary and permanent groundcover shall be part of the construction plans.
Protect Slopes: Cut and fill slopes shall be protected from erosive flows and
concentrated flows until permanent cover and drainage conveyance systems are in
place.
Protect Drain Inlets: All storm drain inlets shall be protected from sediment and silt
laden water.
Stabilize Channels and Outlets: Temporary and permanent conveyance systems
shall be stabilized to prevent erosion during and after construction. Culvert outlets
shall be protected.
Control Pollutants: The SWPPP shall indicate how all pollutants, including waste
materials and demolition debris, shall be handled. This shall include maintenance of
construction equipment, fertilizers, application of chemicals, and water treatment
systems.
Control De-Watering: The water from de-watering systems for trenches, vaults, and
foundations shall be discharged into a controlled system.
Maintain BMPs: The SWPPP shall provide for inspection and maintenance of the
planned and installed construction BMPs as well as their removal at the end of the
project.
Manage the Project: The SWPPP shall outline how the site shall be managed for
erosion control. The plan shall cover phasing, training, coordination, monitoring and
reporting.
Specific BMPs for the project shall include the following:
Land disturbing or grading activities shall be limited between October 1 and April 30.
Quendall Terminals 8
Mitigation Document
August 2015
In-water work for the installation of the stormwater treatment pond outfalls shall be
conducted during Washington State Department of Fish and Wildlife’s (WDFW)-
prescribed in-water work period for Lake Washington.
Stormwater during construction shall be routed to a holding pond for sediment
control. The majority of construction stormwater runoff from the site shall be
temporarily routed to this pond via interceptor trenches and berms. Later, stormwater
shall be routed via permanent drainage pipes.
The area designated for the permanent stormwater facility shall remain in an
undisturbed condition until the site has been completely stabilized.
Stormwater released from the on-site TESC pond during construction shall be
controlled and monitored to ensure compliance with established water quality
discharge requirements.
Soils shall be stabilized at the end of each day based on the weather forecast.
Applicable stabilization practices shall include, but are not limited to, temporary and
permanent seeding, sodding, mulching, plastic covering, erosion control fabrics and
matting, the early application of a gravel base on areas to be paved, and dust
control.
Matting, plastic sheeting, or other approved slope stabilization measures shall be
installed on all slopes greater than or equal to 3:1. Plans shall make provisions to
prevent concentrated flows from being routed over slopes.
Water quality shall be monitored throughout the construction period. A monitoring
plan shall be part of the quality assurance plan for compliance. The construction
SWPPP shall contain a plan for stormwater sampling locations, background
measurements and a periodic reporting schedule. The sampling points shall be
marked on a map and on the ground.
B2. If approved by EPA, trenching for utilities and stormwater outfalls shall be incorporated
into site grading associated with remediation efforts to limit or prevent later disturbance
of re-vegetated areas.
B3. Upland areas on the Main Property (i.e., areas landward of the minimum 100-foot
shoreline setback from Lake Washington’s ordinary high water mark (OHWM)) shall be
temporarily re-vegetated (e.g., with hydro-seed) following site remediation, if building
permits for the disturbed area have not been filed with the City of Renton.
Discussion:
Geologic hazards (other than seismic) identified at the site are primarily related to erosion
hazards. These erosion hazards, and their potential to impact the lake and adjacent wetlands,
shall be addressed through the development and implementation of a TESCP and use of BMPs
during construction, including potentially managing the timing of trenching for utilities/stormwater
outfalls, as well as planting temporary vegetation in the upland areas on the Main Property to
protect site soils from erosion until permanent impervious surfaces and landscaping are
installed.
Quendall Terminals 9
Mitigation Document
August 2015
Temporary re-vegetation (via seeding or by other means) shall avoid use of plant species that
can invade lakeshore riparian and wetland restoration areas and impair growth and
development of native plantings. These include, but are not limited to species on the current
King County list of noxious weeds or other weeds of concern. Plantings or seed mixes could
consist of sterile annuals designed to provide cover and soil stabilization for a short period of
time, as appropriate.
Following Construction
B4. Proposed redevelopment shall avoid direct impacts to on-site wetlands retained/re-
established and/or expanded as part of EPA’s Record of Decision (ROD) for the
remediation project or any Natural Resource Damages (NRD) settlement.
Discussion:
The outer boundaries of the riparian and wetland areas along the lake retained/re-established
and/or expanded as part of EPA’s ROD for the remediation project or any NRD settlement shall
be marked with permanent fencing and signage to clearly indicate the limits of the native growth
tract where it meets the ornamental landscaping of the developed area. Fencing could be
designed in a manner consistent with the landscape aesthetic, while providing a physical divide.
Signage could consist of standard critical areas signs or include interpretive elements, or a
combination of the two.
B5. Retained/re-established and/or expanded wetlands, associated buffers, and all other
habitat restoration areas required as part of EPA’s anticipated ROD for the remediation
project or any NRD settlement shall be retained within and be a function of the open
space tract(s).
Discussion:
The open space tract(s) on the Quendall Terminals Main Property (adjacent to the lake) and on
the Isolated Property (to the northeast of the Main Property, across Ripley Lane N) shall be
placed in common ownership or management, through a homeowners association or other
similar entity.
Following Construction
B6. Proposed buildings shall be setback a minimum of 100 feet from the OHWM, consistent
with the City of Renton’s 2011 Shoreline Master Program.
B7. A permanent stormwater control system shall be installed consistent with applicable
requirements. The system shall collect and convey stormwater runoff to Lake
Washington via a tight-lined system or another system approved by the City’s
responsible public official. Water quality treatment shall be provided for runoff from
pollution-generating surfaces to prevent water quality impacts to the lake and shoreline
wetlands.
Discussion:
The baseline assumptions used in the Quendall Terminals DEIS were consistent with the
Renton Shoreline Management Plan (1983) in place at the time complete Applications for the
Quendall Terminals 10
Mitigation Document
August 2015
Quendall Terminals Project were submitted to the City, and other relevant information described
in Appendix E to the DEIS. The Project is vested to the development standards of the City’s
Shoreline Management Plan in place at the time of complete Applications (February 5, 2010) for
purposes of local permits and approvals. In 2011, the City’s Shoreline Management Program
(SMP) was updated, and more stringent shoreline setbacks and wetland buffers established.
EPA indicated in their comment letter on the DEIS that their final mitigation/restoration
requirements will be based on the shoreline regulations in place at the time EPA issues their
Record of Decision (ROD) which will constitute the final cleanup and mitigation plan for the site
for remediation purposes.
According to current City of Renton regulations and standards, the wetland and shoreline
restoration areas to be established as part of the anticipated ROD and any NRD settlement
would be larger than those assumed in the DEIS. The City of Renton’s 2011 SMP requires a
100-foot minimum setback from the OHWM of Lake Washington. In part, this setback will help
protect critical areas, such as the lake and adjacent wetlands. The Quendall Terminals Site Plan
for the Preferred Alternative incorporates this 100-foot minimum setback to provide for
mitigation and restoration as part of the anticipated ROD and any NRD settlement.
The operation and maintenance of the permanent stormwater control system shall conform to
applicable requirements. The plans for this system shall be reviewed and approved by the City
at the time of building permit application(s) and associated utility construction permit
application(s). If this system is properly implemented, significant adverse water quality impacts
on the lake and adjacent wetlands are not expected.
B8. Native plant species shall be included within landscaping of the redeveloped upland area
on the Main Property to the extent feasible, and could provide some limited habitat
benefits to native wildlife species.
B9. Introduction of noxious weeds or invasive species shall be avoided to the extent
practicable in areas re-vegetated as part of the proposed redevelopment. Together with
the native species planted, this shall help limit the unnecessary spread of invasive
species that could adversely affect the suitability of open space habitats on site and in
the vicinity for wildlife.
Discussion:
A variety of native species appropriate for the developed site conditions shall be incorporated
within the landscaped areas to minimize the need for fertilizers, pesticides, herbicides, and
excessive watering, and reduce adverse effects on terrestrial wildlife, native vegetation, and
aquatic organisms in Lake Washington.
In addition, high quality soil materials with ample organic material should be used in ornamental
landscape areas to ensure adequate soil health and decrease the need for chemical
supplements or controls in landscape maintenance.
The landscape plantings shall avoid use of plant species on the current King County list of
noxious weeds or other weeds of concern, including those sometimes used in ornamental
plantings (e.g., English ivy, holly, or laurel; European mountain ash; and, others). The final
landscape requirements for the project shall be determined by the City through Site Plan review.
Quendall Terminals 11
Mitigation Document
August 2015
B10. A publicly accessible, unpaved trail with interpretive viewpoints shall be provided
through the minimum 100-foot shoreline setback area unless the trail is prohibited by the
EPA ROD or any NRD settlement. If EPA’s ROD or any NRD settlement prohibit the
trail, the trail shall be relocated to the west side of the westernmost buildings onsite, and
could be combined with the fire access road.
Discussion:
If the trail is constructed in the minimum 100-foot shoreline setback area, it could be routed
through the outer portions of the wetland buffers, to the extent feasible, to allow greater
screening and cover between wetland areas and human activity.
The trail shall be designed to discourage users from straying off the trail into the restoration
areas, to the extent feasible. Design features could include, but would not be limited to, elevated
boardwalk sections, overlooks with railings, and low railings or fencing along the edges.
Plantings along the trail shall be designed to form dense cover to discourage off-trail access.
B11. The proposed redevelopment shall include design elements to minimize the potential
adverse effects of artificial lighting on wetland, shoreline, and riparian habitats, and
adjacent properties. These elements shall include directing lighting downward and away
from these habitats and adjacent properties, and shall also include shielding of lights,
use of low-pressure sodium lights, and/or minimizing the use of reflective glazing
materials in building design, as feasible.
Discussion:
The architectural design of the proposed buildings shall limit the use of highly reflective
materials (e.g., expanses of metal siding and glass windows) and incorporate low reflectivity
materials (e.g., could include, but would not be limited to, brick, stucco, and wood) on building
facades to the greatest extent possible.
Policy Nexus:
City of Renton Environmental Review Procedures (RMC 4-9-070); City of Renton Critical Areas
Regulations (RMC 4-3-050); City of Renton Shoreline Master Program Regulations (RMC 4-3-
090); City of Renton Drainage (Surface Water) Standards (RMC 4-6-030); and, City of Renton
Exterior On-site Lighting Standards (RMC 4-4-075).
C. Environmental Health
Refer to DEIS Section 3.3 and EIS Addendum Section 4.3 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on environmental health; also
refer to FEIS Section 2-2 for a summary of the environmental health analysis. The mitigation
measures below address the identified environmental health-related impacts of the project.
Mitigation Measures and Discussion
C1. Redevelopment of the site is being coordinated with the cleanup/remediation process,
and shall be conducted consistent with the requirements in the final cleanup remedy
selected and overseen by EPA, and with any associated institutional controls.
Quendall Terminals 12
Mitigation Document
August 2015
C2. The appropriate management of contaminated soils that could be disturbed and
groundwater that could be encountered during redevelopment of the site shall be
addressed through the cleanup/remediation process and by institutional control
requirements overseen by EPA. As necessary, lightweight fill materials, special capping
requirements, vapor barriers, and/or other measures shall be implemented to ensure
that unacceptable exposures to contaminated soils, groundwater, or vapors shall not
occur.
C3. Institutional controls shall be followed to prevent alteration of the site cap (should it be
installed) without EPA approval, and to prevent the use of on-site groundwater for any
purpose.
C4. An Operations, Maintenance, and Monitoring Plan (OMMP) shall be implemented to
prevent the excavation of soils, installation of utilities, or other site disturbances without
prior EPA approval.
C5. As necessary, personal protection equipment for workers shall be used and special
handling and disposal measures followed during construction activities to prevent
contact with hazardous materials and substances.
C6. Institutional controls specified by EPA shall also be implemented to prevent exposure to
unacceptable vapors.
C7. If approved by EPA, utilities (including the main utility corridors) shall be installed as part
of the planned remedial action so that disturbance of the site cap (should it be installed)
and underlying contaminated soils/groundwater would not be necessary subsequent to
capping of the Main Property.
C8. Personal protection measures and special training costs shall be funded by the applicant
for City of Renton staff who provide inspection during construction and maintenance
following construction in areas where there is a potential to encounter contaminated soils
or groundwater.
C9. If approved by EPA, buried utilities, public roads and infrastructure serving the site
development shall be placed in clean fill material (with the utilities in a trench with
sufficient width and depth of 3 to 4 feet below the invert of the utility), along with an
acceptable barrier to prevent recontamination of the clean fill material, in order to protect
the utility from contamination and to allow future maintenance of the road or utility lines.
If the above is not approved by EPA, no public utility lines shall be installed until the
applicant, EPA, and the City agree upon appropriate protection measures for future road
and utility maintenance.
C10. If EPA issues a ROD that is different than what is assumed in the Quendall Terminals
EIS, the City reviewing official shall determine whether the applicant shall be required to
prepare additional SEPA review, including a possible Supplement to the EIS or
Addendum to the EIS, to address any differences between the ROD and the
assumptions in the EIS.
Quendall Terminals 13
Mitigation Document
August 2015
Discussion:
Construction bid specifications for future infrastructure and building development shall address
protecting the established EPA-approved components of the remedial action and the potential
for encountering contaminated soil and groundwater. A contamination response plan and
hazardous materials contingency plan shall be developed that includes: specific worker, City of
Renton personnel, and public health safety precautions; protocols for handling materials
suspected and confirmed to be contaminated; and, treatment and disposal options for these
materials.
Policy Nexus:
City of Renton Environmental Review Procedures (RMC 4-9-070); United States
Comprehensive Environmental Response, Compensation and Liability Act (CERCLA); United
States Superfund Amendments and De-authorization Act; and, City of Renton Utility Lines –
Underground Installation Standards (RMC 4-6-090).
D. Energy – Greenhouse Gas Emissions
Refer to DEIS Section 3.4 and EIS Addendum Section 4.4 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on energy-greenhouse gas
(GHG) emissions. The mitigation measure below addresses the identified energy–GHG
emission-related impacts from the project.
Mitigation Measures and Discussion
D1. Development may incorporate low-impact/sustainable design features into the design of
proposed buildings on the site to reduce the demand for energy and reduce the amount
of greenhouse gas emissions. Such features could include architectural design features;
sustainable building materials; use of energy efficient products; natural drainage/green
roof features; use of native plants in landscaping; and/or other design features.
Discussion:
Building design at Quendall Terminals could include a wide variety of green building features to
reduce the demand for energy and the amount of GHG emissions. Green building encompasses
energy and water conservation, waste reduction, and good indoor environmental quality. Tools
and standards that are used to measure green building performance could be used at Quendall
Terminals. Some options could include: Built Green, Leadership in Energy & Environmental
Design (LEED), and the Evergreen Sustainable Development Criteria. Some of the specific
building design strategies that could be considered include: energy star-rated appliances; water
conserving fixtures beyond code; low toxicity materials, finishes, and flooring; high efficiency
fixtures, such as dual flush toilets; and, irrigation supplied by recaptured rainwater.
Landscaping with native plants shall be incorporated into the Quendall Terminals Project, to the
extent feasible, to reduce water demand and integrate with the local ecosystem. Native plants
are plants that are adapted to the local climate and do not depend upon irrigation after plant
establishment for ultimate survival. The final landscape requirements for the project shall be
determined by the City through Site Plan review.
Quendall Terminals 14
Mitigation Document
August 2015
Policy Nexus
City of Renton Environmental Review Procedures (RMC 4.9-070); and, Washington State GHG
Emission Reduction Requirements (RCW 70.235.020).
E. Land and Shoreline Use
Refer to DEIS Section 3.5 and EIS Addendum Section 4.5 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on land and shoreline use; also
refer to FEIS Section 2-3 for a summary of the land use analysis. The mitigation measures
below address the identified land use-related impacts of the project.
Mitigation Measures and Discussion
E1. New driveways, landscaping, surface parking areas, and proposed building setback
areas shall be designed and constructed to provide a buffer between proposed buildings
and land uses on adjacent properties.
E2. Proposed landscaping, particularly along the north and south boundaries of the Main
Property, shall be designed and constructed to provide a partial visual screen between
proposed buildings and adjacent uses.
Discussion:
As shown in the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred Alternative
Site Plan), a minimum building setback of 40 feet shall be maintained from the site’s south
boundary (adjacent to Barbee Mill); a minimum building setback of 38 feet shall be maintained
from the site’s north boundary (adjacent to the Seattle Seahawk’s Training Facility); and, a
minimum building setback of 100 feet shall be maintained from the Lake Washington OHWM.
Landscaping for the Quendall Terminals Project shall meet or exceed the City of Renton’s
landscaping regulations in place at the time of complete Applications (February 2010). While not
required by the 2010 landscape regulations, landscaping shall be provided along the site’s
south boundary that shall be a minimum ten-foot (10’) wide, partially sight-obscuring visual
barrier for the length of the boundary, except the area along the minimum 100-foot shoreline
setback area. A minimum five-foot (5’) wide, partially sight-obscuring landscaped visual barrier
shall be provided along the site’s north boundary for the length of the boundary, except the area
along the minimum 100-foot shoreline setback (see FEIS Figure 1-1, Preferred Alternative Site
Plan). The final landscape requirements for the project shall be determined by the City through
Site Plan review.
E3. Architectural features (i.e., roof slope, façade modulation, building materials, etc.) shall
be incorporated into the design of each building and are intended to enhance the
compatibility between the proposed development and surrounding land uses.
E4. As shown in the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), building heights shall be modulated to reduce potential
height/bulk/scale impacts on adjacent development (i.e., Barbee Mill); Building SW4
located adjacent to the southwest property line shall be 4 stories high; other buildings
shall be 5 to 6 stories high.
Quendall Terminals 15
Mitigation Document
August 2015
E5. A fire mitigation/impact fee shall be determined and paid for the proposed development
at the time of building permit issuance and as required by the Renton Municipal Code to
help offset the impacts of the project on the City’s fire emergency services.
Discussion:
The City will review the Master Plan, Binding Site Plan, and Shoreline Substantial Development
Permit Applications for the Quendall Terminals project determined to be complete (February
2010); information and analysis provided in the Quendall Terminals Draft EIS (2010), Quendall
Terminals EIS Addendum (2012), and Quendall Terminals Final EIS (2013), and additional
information that the City may request to ensure that the potential land use impacts of the project
(i.e., height/bulk/scale impacts) are adequately mitigated.
The Master Plan review process provides the opportunity for the City to analyze the
overall Quendall Terminals Project concept and phasing, as well as review how the
major project elements work together to implement the City goals and policies.
The Binding Site Plan process creates or alters existing lot lines on the Quendall
Terminals site, subject to the development standards of the underlying zoning district
(the COR zone in this case).
The Shoreline Substantial Development Permit requirements ensure that proposed
development is appropriate for the shoreline location. This permit includes provisions
for allowed uses in the shoreline jurisdiction, as well as shoreline bulk standards that
establish the minimum dimensional requirements for development including all
structures and substantial alteration of natural topography.
The Quendall Terminals site is located in the City of Renton’s Urban Design District C, and the
proposed mixed-use development will be subject to the urban design regulations for this District
in place on February 5, 2010. These design regulations are applied through the governing land
uses process (i.e., the Master Plan and Site Plan review processes), at the appropriate level of
review for the particular approvals.
The Site Plan review process will be required at a later date, prior to building and
construction permit issuance. Site Plan review will provide the opportunity for
detailed analysis of the arrangement of project elements to mitigate negative impacts
where necessary to ensure project compatibility with the physical characteristics of
the immediate site and surrounding area. Through Site Plan review, the City will
analyze elements including: site layout, building orientation and design, pedestrian
and vehicular environment, landscaping, natural features of the site, screening and
buffering, parking and loading facilities, and illumination to ensure compatibility with
potential future development. The Site Plan review is intended to build upon and be
consistent with the Master Plan review.
Compliance with Master Plan, Binding Site Plan, and Site Plan Approvals is also reviewed and
enforced through the building and construction review process.
As shown on the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred Alternative
Site Plan, and EIS Addendum Figures 2-5 through 2-9), and as required by the Urban Design
regulations for Urban Design District C in which the site is located (RMC 4-3-100 I.1.c):
Quendall Terminals 16
Mitigation Document
August 2015
All buildings shall include measures to reduce the apparent scale of the buildings
and add visual interest.
All buildings shall be articulated with one or more of the following:
- Defined entry features;
- Window treatment;
- Bay windows and/or balconies;
- Roofline features; or
- Other features approved by the Administrator of the Department of Community
and Economic Development.
Single-purpose residential buildings (i.e., proposed buildings SE 1, SE 2, SW 2, SW
3, SW 4, NE 2, and NW 2) shall feature building modulation.
Quendall Terminals building SW 4 shall be no more than 4 stories high; buildings SE 2, SW 3,
NE 2, and NW 2 shall be no more than 5 stories high; and, buildings NE 1, SE 1, NW 1, SW 1,
and SW 2 shall be no more than 6 stories high (see FEIS Figure 1-1, Preferred Alternative Site
Plan).
As shown on EIS Addendum Figures 2-5, 2-6, 2-8, and 2-9, Quendall Terminals exterior
building materials could include, but would not be limited to, brick, stucco, masonry, and precast
concrete, to the greatest extent possible. Metal siding shall be minimized.
Policy Nexus
City of Renton Environmental Review Procedures (RMC 4-9-070); City of Renton Master Plan
and Site Plan Review (RMC 4-9-200); City of Renton Zoning Districts – Uses and Standards
(RMC 4-2); City of Renton Urban Design Regulations (RMC 4-3-100); City of Renton
Landscaping Standards (RMC 4-4-070); City of Renton Parking, Loading, and Driveway
Regulations (RMC 4-4-080); City of Renton Ordinance #5670 – Fire Protection Impacts Fee;
City of Renton Binding Site Plan (RMC 4-7-230); and, City of Renton Shoreline Permits (RMC 4-
9-190).
F. Aesthetics/Views
Refer to DEIS Section 3.7 and EIS Addendum Section 4.6 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on aesthetics/views; also refer
to FEIS Section 2-4 for a summary of the aesthetics/view analysis. The mitigation measures
below address the identified aesthetics and view-related impacts of the project.
Mitigation Measures and Discussion
F1. Building design shall include a variety of details and materials that are intended to create
a human scale and provide a visually interesting streetscape and façade, such as
horizontal plan modulation, projecting vertical elements, and alternating façade materials
and details.
F2. Street-level, under-building parking areas shall be screened from sidewalks and streets
by retail and commercial uses along certain façades. Where this parking extends to the
Quendall Terminals 17
Mitigation Document
August 2015
exterior of the building, elements, such as architectural façade components, trellises,
berms, and landscaping shall be used for screening.
Discussion:
See the discussion following mitigation measures E3 through E5 above regarding building
design. The Quendall Terminals mixed-use development shall be subject to the urban design
regulations for Urban Design District C. These regulations include specific provisions related to
the pedestrian environment (per RMC 4-3-100 E.2.b), including:
Buildings on designated pedestrian-oriented streets shall contain pedestrian-oriented
uses, feature “pedestrian-oriented facades,” and have clear connections to the
sidewalk. Such buildings shall be located adjacent to the sidewalk, except where
pedestrian-oriented space is located between the building and the sidewalk. Parking
between the building and pedestrian-oriented streets is prohibited.
Buildings fronting on pedestrian-oriented streets shall contain pedestrian-oriented
uses.
Nonresidential buildings may be located directly abutting any street as long as they
feature a pedestrian-oriented façade.
Buildings containing street-level residential uses and single-purpose residential
buildings shall be set back from the sidewalk a minimum of ten feet (10’) and feature
substantial landscaping between the sidewalk and the building.
If buildings do not feature pedestrian-oriented facades, they shall have substantial
landscaping between the sidewalk and building. Such landscaping shall be at least
ten feet (10’) in width as measured from the sidewalk.
Proposed buildings NE 1, SE 1, NW 1, and SW 1 shall contain retail and restaurant uses which
shall screen street-level, underbuilding parking from the sidewalk and street (Street “B”). The
street-level, underbuilding parking shall be screened by landscaping where this parking extends
to the exterior of the building. An example of how this requirement could be met is shown in a
detail of the Preferred Alternative (see EIS Addendum Figure 2-10, “Green Wall” Façade
Section – Preferred Alternative) where the bases of the parking structure have grids to support
vines to create “green walls”. Pursuant to RMC 4-3-100E.2, this landscape area could be
increased to 10 feet if the building does not feature a pedestrian-oriented façade. Landscaped
berms shall also be provided (e.g., along the westernmost buildings to screen views of the
underbuilding parking from Lake Washington and Mercer Island). The design details of the
subject project will be reviewed for consistency with the Urban Design Regulations in place on
February 5, 2010, at the time of specific Site Plan review for each phase of the proposed
development. At this time, the proposed Preferred Alternative does not provide enough detail to
verify compliance with all design standards.
F3. Public view corridors toward Lake Washington shall be provided along the main
east/west roadway onsite (Street “B”) and along the private driveways at the north and
south ends of the site. Public views of the lake shall also be provided from the publically
accessible trail in the minimum 100-foot shoreline setback area in the western portion of
the Main Property, if the trail is not prohibited by EPA or any NRD settlement. If EPA’s
Quendall Terminals 18
Mitigation Document
August 2015
ROD or any NRD settlement prohibit the trail, the trail shall be relocated to the west side
of the westernmost buildings onsite, and could be combined with the fire access road.
Additional views of the lake shall be provided for project residents from semi-private
landscaped courtyard areas between the new buildings onsite.
Discussion
As shown on the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred Alternative
Site Plan), the following public view corridors shall be provided along proposed on-site
roadways:
Street “B”: minimum 74-feet-wide
Private Drive “D”: minimum 40-feet-wide
Private Drive “E”: minimum 38-feet-wide
F4. New landscaping shall be provided in the upland area of the Main Property that is
intended to enhance the visual character of the site. Landscaping shall include new
trees, shrubs, and groundcovers of various sizes and species.
F5. Proposed landscaping along the north and south property lines shall be designed and
constructed to provide a partial visual screen between proposed buildings and adjacent
uses.
Discussion:
Landscaping for the Quendall Terminals Project shall meet or exceed the City of Renton
landscaping regulations in place at the time Applications were determined to be complete
(February 2010). Landscaping under the Preferred Alternative is intended to improve the
aesthetic quality of the built environment; improve and soften the appearance of parking areas;
increase privacy and protection from visual or physical intrusion; reduce noise and glare; and,
generally enhance the overall image and appearance of the City and quality of life for residents,
employees, and visitors of the project. As shown on the plans for the Preferred Alternative (see
FEIS Figure 1-1, Preferred Alternative Site Plan), areas on the site that shall be landscaped
include:
Street frontage areas;
Right-of-way on public streets (e.g., along new public Streets “A,” “B,” and “C”
onsite);
Along the north and south site property lines (i.e., adjacent to the Barbee Mill
residential development and Seahawks Training Facility);
Pervious site areas throughout the site (except critical areas, such as the wetland
and riparian habitat in the minimum 100-foot shoreline setback area on the Main
Property and on the Isolated Property); and,
Parking lots (i.e., surface parking lots in the northwest and south portions of the site)
and structured parking garages when abutting a public street.
Quendall Terminals 19
Mitigation Document
August 2015
The final landscape requirements for the project shall be determined by the City through Site
Plan review.
F6. The natural vegetation in the minimum 100-foot shoreline setback area and/or other site
areas established or protected by EPA’s ROD or any NRD settlement shall be retained
with proposed site development.
F7. Exterior building lighting, parking lot lighting, and pedestrian lighting shall be directed
downward and away from surrounding buildings, properties and the shoreline of Lake
Washington to minimize the impacts to adjacent uses and fish.
Discussion:
Remediation and potential restoration of the site shall include retaining/re-establishing and/or
expanding wetlands, associated buffers, and other habitat required by EPA or any NRD
settlement in the 100-foot minimum shoreline setback area and in the Isolated Property. No
development shall occur in these areas, except for the trail/emergency access road proposed in
the minimum 100-foot shoreline setback area, if the trail is not prohibited by EPA’s ROD or any
NRD settlement. If EPA’s ROD or any NRD settlement prohibit the trail, the trail shall be
relocated to the west side of the westernmost buildings onsite, and could be combined with the
fire access road.
Limits on the height of light structures, limits on light levels of fixtures, and shielding and
screening of display and exterior lights shall be used in the Quendall Terminals development to
reduce the visibility of lights from adjacent areas (i.e., Barbee Mill), prevent hazards for public
traffic (i.e., on Ripley Lane and Lake Washington Boulevard), and limit impacts on fish in the
lake.
F8. As indicated in the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), building setbacks shall be provided adjacent to Lake Washington
and along the south site boundaries, to enhance the aesthetic character of development
and retain views of Lake Washington.
Discussion:
A minimum building setback of 100 feet shall be maintained adjacent to the Lake Washington
shoreline, in anticipation of EPA’s ROD and any potential NRD settlement, and consistent with
the City of Renton Shoreline Management Program (2011), as recommended by EPA. A
minimum building setback of 40 feet shall be maintained from the site’s south boundary
(adjacent to Barbee Mill).
F9. Building height modulation shall be provided across the site to enhance the aesthetic
character of development and retain some views of Lake Washington.
F10. No surface parking shall be located at the terminus of Street “B” in order to enhance the
aesthetic character of the development, particularly from the shoreline trail, if the trail is
located within the minimum 100-foot shoreline setback and not prohibited by EPA’s ROD
or any NRD settlement. If EPA’s ROD or any NRD settlement prohibit the trail within the
minimum 100-foot shoreline setback, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road.
Quendall Terminals 20
Mitigation Document
August 2015
F11. During final building design, maximum building heights 100 feet from the Lake
Washington OHWM shall be reduced to one half of the maximum height allowed by the
COR zone (125 feet allowed height x ½ = 62.5 feet), consistent with the City of Renton’s
2011 Shoreline Master Program, which will help maintain views toward the lake.
F12. As determined by the City’s responsible public official, the amount of required parking
may be reduced, relocated, and/or redesigned (i.e., through implementation of
transportation demand management (TDM) measures or other means) so that additional
areas of the street-level, under-building parking can be setback from the exterior of the
building, particularly along Streets “A”, “C,” and the lake side of the development. This
will allow other uses, including retail, restaurant, commercial, and residential uses, and
plaza areas to occupy these areas and enhance the aesthetic character at the ground
level.
Discussion:
See the discussion following mitigation measures E3 through E5 above regarding building
design and height.
As indicated in the Transportation section of this Mitigation Document, the applicant shall
prepare a Transportation Demand Management (TDM) plan to the satisfaction of the City of
Renton. This plan shall include measures intended to reduce the needed parking onsite. In
conjunction with the TDM Plan, the applicant shall prepare a Parking Management Plan if
shared parking will occur onsite, and/or if preferential parking or High Occupancy Vehicle (HOV)
parking is proposed onsite. Based on the TDM Plan and the Parking Management Plan, and at
the City reviewing official’s discretion, the site plan for the project could be modified to reduce,
relocate, and/or redesign the parking so that additional retail, restaurant, commercial, and
residential uses, and plaza areas could occupy the street-level of the development, as required
by RMC 4-3-100E.2.
F13. Reflectivity of glazing materials, as well as the use of shading devices, shall be
considered as part of the façade design in order to minimize the potential glare impacts
to surrounding uses.
Discussion:
The architectural design of the proposed buildings shall limit the use of highly reflective
materials (e.g., expanses of metal siding and glass windows) and incorporate low reflectivity
materials (e.g., brick, stucco, and wood) on building facades to the greatest extent possible, and
as shown in EIS Addendum Figures 2-5, 2-6, 2-8, and 2-9. Per the City of Renton Shoreline
Master Program, building surfaces on or adjacent to water (i.e., buildings NW1, NW2, SW1,
SW2, SW3, and SW4 in the western portion of the site adjacent to Lake Washington) shall
employ materials that limit reflected light.
Shading devices over glazed areas shall also be considered in the building design to minimize
glare that could aggravate neighbors (i.e., Barbee Mill), disrupt views from afar (i.e., Mercer
Island), and temporarily blind motorists or cyclists (i.e., on Ripley Lane and Lake Washington
Boulevard).
Quendall Terminals 21
Mitigation Document
August 2015
F14. Design features such as: public art, special landscape treatment, additional open
space/plazas, landmark building form, special paving/pedestrian scale lighting, and/or
prominent architectural features shall be provided as part of development to further
enhance the gateway/landmark features on the site.
Discussion:
The project shall include design features and/or architectural elements to further enhance the
gateway location of the site which are distinctive within the context of Urban Design District C,
but also compatible with the District in form and scale. These urban design requirements will be
applied through the Master Plan and Site Plan review processes.
F15. Vertical and/or horizontal modulation shall be provided along the west or lake side of the
buildings to provide a human scale and break up the larger structures which will be
adjacent to the shoreline area and pedestrian environment.
Discussion:
See the discussion following mitigation measures E3 through E5 above regarding building
design and height.
Policy Nexus:
City of Renton Environmental Review Procedures (RMC 4-9-070); City of Renton Master Plan
and Site Plan Review (RMC 4-9-200); City of Renton Zoning Districts – Uses and Standards
(RMC 4-2); City of Renton Urban Design Regulations (RMC 4-3-100); City of Renton
Landscaping Standards (RMC 4-4-070); City of Renton Exterior On-site Lighting Standards
(RMC 4-4-075); City of Renton Parking, Loading and Driveway Regulations (RMC 4-4-080); City
of Renton Shoreline Permits (RMC 4-9-190); and, City of Renton Shoreline Management Plan
(1983, as amended, and 2011).
G. Parks and Recreation
Refer to DEIS Section 3.8 and EIS Addendum Section 4.7 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on parks and recreation. The
mitigation measures below address the identified parks and recreation-related impacts from the
project.
Mitigation Measures and Discussion
Measures to Improve Public Open Space and Related Areas/Fees2
G1. A parks mitigation/impact fee shall be determined and paid for each multifamily unit in
the proposed development at the time of building permit issuance and in accordance
with the City of Renton Municipal Code.
G2. As shown on the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), approximately 10.6 acres of “Natural Public Open Space Areas”
2 Hours of public access shall meet park standards of sunrise to sunset to count toward public recreation.
Quendall Terminals 22
Mitigation Document
August 2015
and “Other Related Areas” shall be provided on the site. The “Natural Public Open
Space Areas” shall include the approximately 0.5-acre trail within the minimum 100-foot
shoreline setback area, and approximately 3.2 acres of natural area along the trail. If
EPA’s ROD or any NRD settlement prohibits the trail, the trail shall be relocated to the
west side of the westernmost buildings onsite, and could be combined with the fire
access road. It is the City’s intent that the natural area along the trail be used for
retained/re-established and/or expanded wetlands, associated buffers, and all other
habitat restoration areas required as part of EPA’s ROD for the remediation project or
any NRD settlement. The “Other Related Areas” onsite shall include street-level
landscaping, landscaped courtyards, sidewalks, paved plazas, and the Isolated
Property. These areas may or may not meet the City’s standards, regulations, and
procedures for public open space. If EPA’s ROD or any NRD settlement result in
alterations to the plans for the Preferred Alternative, including the “Natural Public Open
Space Areas” or “Other Related Areas,” the City could re-evaluate the plans.
Discussion
Approximately 3.7 acres of “Natural Public Open Space” shall be provided onsite, including the
approximately 0.5-acre trail through the 100-foot shoreline setback area (or an alternate location
on the west side of the westernmost building onsite) that shall be physically accessible to the
general public, and the approximately 3.2 acres of natural area along the trail that shall be
visually accessible to the general public at certain times of the day (the hours of public use [i.e.,
not the residents’ use]) of the trail shall be determined by the City’s Community Services
Administrator). The “Other Related Areas” onsite may or may not be considered public open
space. The City shall determine whether the project has met the City’s standards, regulations
and procedures for public open space during Master Plan review.
G3. Frontage improvements, including sidewalks, shall be provided along the west side of
Lake Washington Boulevard and Ripley Lane N along the site. These sidewalks shall
connect to sidewalks to the north and south, which connect to other pedestrian facilities
in the area.
G4. If the trail through the minimum 100-foot shoreline setback area is not prohibited by
EPA’s ROD or any NRD settlement, public parking shall be provided in the same general
area as the retail/restaurant parking; the applicant shall specifically identify this parking
prior to site plan approval. If EPA’s ROD or any NRD settlement prohibit the trail, the trail
shall be relocated to the west side of the westernmost buildings onsite, and could be
combined with the fire access road; public parking shall be provided for the relocated
trail as described above. Public parking spaces shall be provided as required by the
Renton Municipal Code and the Shoreline Master Program and shall be identified as
public by signage or other means approved by the City.
G5. Signage, detours, and safety measures shall be put in place to detour bicyclists from
using the Lake Washington Loop trail at the time of construction.
G6. If the trail through the minimum 100-foot shoreline setback area is not prohibited by EPA
or any NRD settlement, the connection between the trail and Lake Washington
Boulevard shall be enhanced by providing wider sidewalks (i.e., 15-foot wide) that are
part of public rights-of-way along the Street “B” corridor. If EPA’s ROD or any NRD
settlement prohibits the trail, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road. The
Quendall Terminals 23
Mitigation Document
August 2015
connection of the relocated trail to Lake Washington Boulevard shall also be enhanced
by providing wider sidewalks (i.e., 15-foot wide), as described above.
G7. If the trail through the minimum 100-foot shoreline setback area is not prohibited by EPA
or any NRD settlement, the hours of public use (i.e., not the residents’ use) of the trail
shall be determined by the City’s Community Services Administrator. If EPA’s ROD or
any NRD settlement prohibit the trail, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road; the
hours of public use (i.e., not the residents’ use) of the trail shall be determined by the
City’s Community Services Administrator.
Discussion:
See the discussion following mitigation measures H1 through H5 below regarding on and off-
site pedestrian facilities. The trails and sidewalks provided on the Quendall Terminals site shall
connect the minimum 100-foot shoreline setback area with Lake Washington Boulevard and
other areas beyond the site (including the May Creek trail with a future connection to Cougar
Mountain), and enhance the overall network of trails in the area.
The allowed hours of public use (i.e., not the residents’ use) of the shoreline trail (to be
determined by the City’s Community Services Administrator) shall be indicated through signage.
The signage shall indicate the public's right of access and hours of access, and shall be
installed and maintained by the owner. Such signs shall be posted in conspicuous locations
near the shoreline trail and at the nearest connection to an off-site public right-of-way (i.e.,
Ripley Lane or Lake Washington Boulevard).
G8. Approximately 1.8 acres of indoor and/or outdoor area shall be provided onsite for active
recreation (e.g., Frisbee, swimming pools, tot lots, bocce ball courts, exercise rooms,
active recreation in courtyards etc.), as approved by the City’s responsible public official.
Discussion:
City of Renton Park and Open Space Facility LOS Standards
Pursuant to the Quendall Terminals DEIS page 3.8-6 through 3.8-14, the project would result in
an increased demand on neighborhood and regional parks and recreation facilities. DEIS Table
3.8-3 shows and page 3.8-8 describes the amounts of park and recreation facilities that would
be needed in the City of Renton, based on the City’s LOS standards and the projected
residential population under the EIS alternatives.
Passive and Active Recreation
Passive recreation and active recreation are “industry” terms that are applied differently by
locality. The Renton Trails and Bicycle Master Plan (2009), and the 2003 Park, Recreation and
Open Space Implementation Plan, the parks plans in place at the time the Quendall Terminals
Applications were determined to be complete, do not include definitions for active recreation or
passive recreation. The 2013 State Comprehensive Outdoor Recreation Plan provides the
following definitions for active and passive recreation:
Active Recreation: Predominately muscle-powered activities such as jogging, cycling,
field and court sports, etc.; they commonly depend on developed sites.
Quendall Terminals 24
Mitigation Document
August 2015
Passive Recreation: Activities that require very little use of muscle power, such as
walking, nature viewing, photography, or picnicking.
Common Open Space/Recreation Areas
Per the site’s Urban Design District C regulations (RMC 4-3-100.H.2.a) in place at the time of
complete Applications, common open space and/or recreation areas shall be provided on the
Quendall Terminals site as follows:
The location, layout, and proposed type of common open space shall be subject to
approval by the Director (and approved through the Master Plan and/or Site Plan
review process).
The required common open space shall be satisfied with one or more of the
elements listed below. The Director may require more than one of the following
elements for developments having more than one hundred (100) units:
- Courtyards, plazas or multipurpose open spaces;
- Upper level common decks, patios, terraces or roof gardens;
- Pedestrian corridors dedicated to passive recreation and separate from the
public street system;
- Recreation facilities including, but not limited to, tennis/sports courts, swimming
pools, exercise areas, game rooms, or other similar facilities; or,
- Children’s play spaces.
These common open space and/or recreation area requirements will be applied through the
governing land uses process (i.e., the Master Plan and Site Plan review processes).
G9. A crosswalk including pedestrian crossing warning signs at and in advance of the
crosswalk shall be provided across Lake Washington Boulevard in order to connect the
proposed development to the May Creek Trail on the east side of the Boulevard. The
crosswalk shall be controlled by Rectangular Rapid Flashing Beacons (RRFBs), if the
City determines that such lighting is warranted.
G10. If the trail through the minimum 100-foot shoreline setback area is not prohibited by EPA
or any NRD settlement, the trail and other recreation areas shall be enhanced with site
amenities, such as tables, litter receptacles, benches, interpretive signage, etc., and
approved by the City’s Community Services Administrator. If EPA’s ROD or any NRD
settlement prohibit the trail, the trail shall be relocated to the west side of the
westernmost buildings onsite, and could be combined with the fire access road; the trail
and other recreation areas shall be enhanced with site amenities, such as tables, litter
receptacles, benches, interpretive signage, etc. and approved by the City’s Community
Services Administrator.
G11. The trail shall connect to the Barbee Mill residential development to the south. If EPA’s
ROD or any NRD settlement prohibits the trail, the trail shall be relocated to the west
side of the westernmost buildings onsite, and it could be combined with the fire access
road; the trail shall connect to Barbee Mill residential development to the south.
Quendall Terminals 25
Mitigation Document
August 2015
Discussion:
A crosswalk including pedestrian crossing warning signs at and in advance of the crosswalk
shall be installed in Lake Washington Boulevard adjacent to the site and connecting to the May
Creek Trail. The crosswalk shall be controlled by RRFBs, if the City determines that such
lighting is warranted, to alert drivers to the crosswalk and enhance safety for pedestrians.
Crosswalks controlled by RRFBs consist of pedestrian warning signs and flashing LED beacons
mounted on poles on each side of the roadway crossing. The RRFBs are activated when a
pedestrian pushes a button also mounted on the pole.
Provided it is allowed by EPA or any NRD settlement, the trail through the 100-foot shoreline
setback area (or an alternate location on the west side of the westernmost building onsite) shall
connect to the Barbee Mill residential development at the site boundary where the existing
easement connects to the Barbee Mill development in the southwest corner of the Quendall
Terminals site and the corresponding northwest corner of the Barbee Mill development.
Measures to Improve Semi-Private Recreation Access for Residents
G12. As part of the total open space, semi-private landscaped courtyards on top of the
parking garages shall be provided as shared open space for residents of the site. These
areas shall help to meet the demand for recreation facilities from project residents.
G13. Street level landscaping, plazas, and sidewalks shall be provided. These areas will help
meet the project’s demand for passive recreation facilities.
Discussion:
See the discussion following Mitigation Measures G2 and G8 above regarding required open
space and recreation areas.
Policy Nexus
City of Renton Environmental Review Procedures (RMC 4-9-070); City of Renton Master Plan
and Site Plan Review (RMC 4-9-200); City of Renton Commercial Development Standards
(RMC 4-2-120); Parks Impacts Fee (RMC 4-1-190); City of Renton Street Standards (RMC 4-6-
060); and, City of Renton Shoreline Master Program Regulations ( 1983, as amended, and
2011).
H. Transportation
Refer to DEIS Section 3.9 and EIS Addendum Section 4.8 for a detailed discussion of Affected
Environment and the Impacts of the Quendall Terminals Project on transportation; also refer to
FEIS Section 2-1 for additional analysis of transportation impacts. The mitigation measures, H1
– H15 below address the identified transportation-related impacts from the project.
If the applicant or future developer(s) of the project decides to add additional retail uses along
the street frontages onsite, the proposed traffic mitigation (H1 –H15) listed below would also
accommodate such additional retail space.
Quendall Terminals 26
Mitigation Document
August 2015
Mitigation Measures and Discussion
With or Without Planned I-405 Improvements
H1. A traffic mitigation/impact fee shall be determined and paid for the proposed
development at the time of building permit issuance and in accordance with the City of
Renton Municipal Code to help offset the impacts of the project on the City’s roadways.
H2. TDM measures shall be implemented to reduce the number of vehicle trips and thus
provide some benefit to improving LOS and queuing impacts at study intersections.
H3. Infrastructure improvements within the site shall include full curbs, gutters, sidewalks,
and landscape strips (where applicable) as well as frontage improvements (curb, gutter,
sidewalk, landscape strips, bike lanes, pavement width, and utilities) along the west side
of Lake Washington Boulevard and Ripley Lane N in front of the project site. Provisions
for safe pedestrian circulation shall encourage future transit usage to and from the site
when planned public transit becomes available.
H4. If approved by EPA and any NRD settlement, a pedestrian trail shall be provided onsite
through the minimum 100-foot shoreline setback area that shall be accessible to the
public and shall connect to Lake Washington Boulevard through the internal site
sidewalk system. If EPA’s ROD or any NRD settlement prohibits the trail, the trail shall
be relocated to the west side of the westernmost buildings onsite, and could be
combined with the fire access road; this trail shall connect to Lake Washington
Boulevard through the internal site sidewalk system.
H5. To mitigate traffic impacts to the Lake Washington Boulevard corridor south of the
development, the applicant shall install traffic calming treatments on Lake Washington
Boulevard south of N 41st Street to encourage primary trips generated by the project to
utilize the I-405 corridor. Although the City of Renton has no adopted residential traffic
management program, arterial calming measures could include treatments that create
either horizontal or vertical deflection for drivers. Such treatments could include, but not
limited to chicanes, serpentine raised curb sections, raised median treatments, speed
tables, and/or speed humps. Final design of traffic calming elements shall be approved
by the City.
Discussion:
To mitigate system-wide transportation impacts on planned vicinity transportation facilities and
to reduce or control the general vehicular impacts of the project, the followings shall be
implemented regardless of planned improvements by WSDOT to the I-405 corridor and NE 44th
Street interchange:
Traffic impact fees shall be determined by the City of Renton and paid at the time of
building permit issuance and in accordance with the City of Renton Municipal Code.
The applicant shall prepare a Transportation Demand Management (TDM) plan to
the satisfaction of the City of Renton. The goal of the plan shall be to incorporate site
design features and implement operational programs that reduce the project’s
reliance on single-occupancy vehicle trips generated by the project. Specific site
design features could include, but would not be limited to: on-site bicycle facilities,
Quendall Terminals 27
Mitigation Document
August 2015
bike lockers, public shower facilities, pedestrian amenities, crossing treatments,
covered walkways, and pedestrian-scale illumination treatments. Operational
programs could include: preferential parking for vanpool, carpool, rideshare/carshare
programs, unbundled parking from tenant leases, flex car parking programs, shuttle
bus systems, ride-matching services, reduced transit pass programs for tenants/on-
site employees, on-site building transportation coordinator, and installation of a
commuter information center. The overall goal of the TDM plan shall be to reduce the
site peak hour vehicle trip generation rates by up to 15 percent lower than those
documented in the Quendall Terminal EIS Addendum and FEIS.
As shown on the plans for the Preferred Alternative (see FEIS Figure 1-1, Preferred
Alternative Site Plan), sidewalks onsite shall be provided as follows:
- Street “A”: a minimum of twelve feet (12’) wide on one side;
- Street “B”: a minimum of fifteen feet (15’) wide on both sides;
- Private Drive “D”: a minimum of five feet (5’) wide on one side; and
- Private Drive “E”: a minimum of five feet (5’) on one side adjacent to building
NW2.
Street “C”: The sidewalk for Street C onsite may be required to be widened to twelve
feet (12’) on both sides to accommodate the commercial uses along the parking
garages and the associated pedestrian activity at street level.
Sidewalks offsite shall be as provided follows:
- Lake Washington Boulevard: a minimum of eight feet (8’) wide on the west
side of the street, per the City’s requirements for a Commercial Mixed
Use/Neighborhood Collector Arterial.
- Ripley Lane N: a minimum of 6 feet (6’) wide in front of the site, per the City’s
requirements for a Commercial/Mixed-Use Access Road.
To address traffic impacts to the Lake Washington Boulevard corridor south of the
development, the applicant shall install traffic calming treatments on Lake
Washington Boulevard south of N 41st Street to encourage primary trips generated
by the project to use the I-405 corridor. The applicant shall prepare and submit a
preliminary traffic calming proposal to the City for review and approval. Upon any
revisions, the City and applicant shall conduct a joint public neighborhood meeting to
notify and take public comment to refine the calming measures prior to
implementation. The arterial calming treatments could be installed prior to other site
access/off-site traffic mitigation improvements, but shall be installed no later than in
conjunction with roadway/intersection improvements along Lake Washington
Boulevard.
With or Without Planned I-405 Improvements
H6. The parking supply under the Preferred Alternative shall meet the minimum off-street
parking requirements of the City of Renton.
H7. Shared parking agreements between on-site uses and implementation of TDM
measures for proposed residential uses shall be implemented to reduce parking demand
during peak periods, thereby reducing the necessary parking supply.
Quendall Terminals 28
Mitigation Document
August 2015
Discussion:
The proposed 1,337 parking spaces exceed the spaces required by the City’s parking
regulations (1,334 spaces are required per RMC 4.4-080 F.10.e). Based on the TDM Plan (and
the Parking Management Plan, if prepared), and at the City responsible public official’s
discretion, the site plan for the project could be modified to reduce the required parking through
a parking modification (per RMC 4-4-080 F.10.d). The Planning/Building/Public Works
Department may authorize a modification from minimum or maximum parking requirements for
a specific development should conditions warrant, as described in RMC 4-9-025 D2.
In conjunction with the TDM Plan, the applicant shall prepare a Parking Management Plan if
shared parking would occur onsite, and/or if preferential parking or HOV parking is proposed
onsite. If prepared, the Parking Management Plan shall identify any shared agreements
required, dedicated stalls, or management techniques that will be implemented onsite that could
generate off-site parking demands.
With or Without Planned I-405 Improvements
H8. A fire access road shall be provided to the west of the westernmost buildings onsite. The
road shall be a minimum of 20 feet wide, and shall be constructed with crushed rock or
grass-crete to support the weight of fire apparatus, and shall be available for emergency
vehicle access. If located in the minimum 100-foot shoreline setback area, and approved
by the EPA ROD and any NRD settlement, the road shall also serve as a pedestrian
trail. If EPA’s ROD or any NRD settlement prohibit the fire access road within the
minimum 100-foot shoreline setback area, the road shall be relocated to the west side of
the westernmost buildings onsite, and could be combined with the trail.
H9. In order to promote a multimodal transportation network, redevelopment on the Quendall
Terminals site shall include site amenities (i.e., planting strips, street lighting, etc.) and
access to future transit zones on Lake Washington Boulevard and at the I-405/NE 44th
Street interchange to encourage and accommodate public transportation access in the
future (future potential public transportation in the vicinity could include Bus Rapid
Transit on I-405 planned by Sound Transit and Washington State Department of
Transportation (WSDOT) with a flyer stop at the I-405/NE 44th Street interchange).
H10. A paved bicycle lane shall be provided along the east and west sides of Ripley
Lane/Lake Washington Boulevard from the end of the current bike trail along Ripley
Lane to the intersection of Ripley Lane/Lake Washington Boulevard or a multi-use path
could be developed on one side or separated from Ripley Lane/Lake Washington
Boulevard to mitigate potential conflicts between bicycles and the Quendall Terminals
site access point on Ripley Lane.
Discussion:
Per the Renton Trails and Bicycle Master Plan (2009), bicycle lanes are to be located on either
side of Ripley Lane N and Lake Washington Boulevard. A one-way paved bicycle lane shall be
provided that is a minimum of five (5) feet wide to the curb face where the roadway has a curb,
or four (4) feet where no curb exists. If constructed adjacent to Ripely Lane N/Lake Washington
Boulevard as a multi-use trail, the recommended width is 12 feet with 2 feet clear on both sides
of the trail. The corridor would be required to be designed consistent with King County plans for
the East Side Rail Corridor, if approved. The bike lane or multi-use trail shall be provided from
Quendall Terminals 29
Mitigation Document
August 2015
the end of the current trail to and including the site frontage along Ripley Lane N and Lake
Washington Boulevard.
With Planned I-405 Improvements
H11. Lake Washington Boulevard between Barbee Mill Access (N 43rd Street) and Ripley
Lane N. The eastbound and westbound through lanes planned by WSDOT shall be
extended beyond and through the Barbee Mill access intersection. This shall result in
two through lanes in each direction on Lake Washington Boulevard from the I-405
interchange past the Barbee Mill access (N 43rd Street). Ultimately, the City of Renton
shall determine the best configuration for the improvements, given ongoing coordination
with WSDOT on the adjacent interchange design, King County (owner of the vicinity rail
right-of-way), and adjacent private development.
H12. Intersection #3 – Barbee Mill Access (N 43rd Street)/Lake Washington Boulevard. A
traffic signal shall be installed at this intersection. At the Barbee Mill Access (N 43rd
Street)/Lake Washington Boulevard intersection the eastbound approach shall be
widened to include a separate left-turn only lane and the northbound approach shall be
widened to include a separate left-turn only lane. Ultimately, the City of Renton shall
determine the best configuration for the improvements, given ongoing coordination with
WSDOT on the adjacent interchange design, King County (owner of the vicinity rail right-
of-way), and adjacent private development. If the traffic signal and eastbound left turn
lane at N 43rd Street have not been constructed prior to the WSDOT improvements at
the NE 44th Street/I-405 interchange, the City will consider changing the location of this
signal to the intersection at Ripley Lane/Lake Washington Boulevard. Relocating the
traffic signal to Ripley Lane/Lake Washington Boulevard could reduce/eliminate potential
impacts of traffic queues on N 43rd Street between Lake Washington Boulevard. and
Road A, and with the existing rail crossing (should it be re-activated for rail service or
converted to a trail corridor). An engineering study will be completed at that time to
support the determination of the location for the installation of the traffic signal at either N
43rd Street or Ripley Lane.
Discussion:
With planned improvements by WSDOT to I-405 and the NE 44th Street interchange, to address
project traffic impacts on transportation facilities the applicant shall construct additional site
access improvements and roadway widening along Lake Washington Boulevard as follows:
The applicant shall prepare a preliminary channelization plan for review by the City of
Renton that shall widen Lake Washington Boulevard to extend roadway
improvements beyond and through the Barbee Mill access intersection. This
channelization shall result in two through lanes in each direction on Lake Washington
Boulevard from the I-405 interchange past the Barbee Mill access at NE 43rd Street.
Ultimately, the City of Renton will determine the best configuration for the
improvements, given ongoing coordination with WSDOT on the adjacent interchange
design, King County (owner of the vicinity rail right-of-way), and adjacent private
development. Upon approval of the channelization plan, the applicant shall prepare
construction documents for joint review by the City, WSDOT, and other affected
agencies (i.e., King County), as directed by the City. The developer shall provide
right of way dedication on the frontage of the subject site. The developer would be
required to coordinate with the owners of other properties to acquire any other right
Quendall Terminals 30
Mitigation Document
August 2015
of way that is needed to address the improvements required to mitigate the impacts
of the project. The developer and the City could coordinate to assist in the
acquisition process, if necessary.
Without Planned I-405 Improvements
H13. Traffic Signals. Traffic signals shall be installed at the intersections of the I-405
northbound and southbound ramp intersections, as well as at the intersection of Barbee
Mill Access (N 43rd Street)/Lake Washington Boulevard. The City will consider moving
the location of this signal to the intersection at Ripley Lane/Lake Washington Boulevard
as part of a future WSDOT improvement project to the NE 44th Street interchange.
Relocating the traffic signal to Ripley Lane/Lake Washington Boulevard could
reduce/eliminate potential longer-range impacts of traffic queues on N 43rd Street
between Lake Washington Boulevard. and Road A, and with the existing rail crossing
(should it be re-activated for rail service or converted to a trail corridor). An engineering
study will be completed at that time to support the determination of the location for the
installation of the traffic signal at either N 43rd Street or Ripley Lane.
H14. Intersection #1 - I-405 Northbound Ramps/NE 44th Street. The southbound and
northbound approaches shall be widened so that a separate left turn lane and shared
thru-right turn lane is provided on both legs of the intersection. The final configuration of
the intersection with the additional widening improvements shall be coordinated with
WSDOT.
H15. Lake Washington Boulevard between Barbee Mill Access (N 43rd Street) and I-405
Southbound Ramps. Additional channelization improvements between the Barbee Mill
access and the I-405 southbound ramps shall be constructed. Additional eastbound and
westbound lanes shall be constructed to provide additional queue storage created by the
traffic signals required at the southbound ramp and Barbee Mill Access (N 43rd Street)
along Lake Washington Boulevard. At the Barbee Mill Access (N 43rd Street)/Lake
Washington Boulevard intersection the west bound approach on the Barbee Mill Access
shall be widened to include a separate left-turn only lane and the north bound approach
on Lake Washington Boulevard shall be widened to include a separate left-turn only
lane. Ultimately, the City of Renton shall determine the best configuration for the
improvements, given ongoing coordination with WSDOT on the adjacent interchange
design, King County (owner of the vicinity rail right-of-way), and adjacent private
development.
Discussion:
Without any planned improvements by WSDOT to I-405 and the NE 44th Street interchange, to
address existing deficiencies in transportation facilities and project traffic impacts, the applicant
shall be required to construct a number of intersection, roadway widening, and traffic control
improvements as follows:
The applicant shall prepare a preliminary channelization plan for review by the City of
Renton initially and then WSDOT that encompasses roadway improvements that
shall begin southwest of the Hawk’s Landing (future driveway) entrance to the NE
44th Street and I-405 northbound ramps intersection east of I-405 (see FEIS Figure
2-1, Lake Washington Boulevard Conceptual Improvements - without I-405
Quendall Terminals 31
Mitigation Document
August 2015
Improvements). The channelization plan shall be prepared to WSDOT NW Region
requirements and consider signalization of the Lake Washington Boulevard and
Barbee Mill Access (N 43rd Street) intersection or Lake Washington Boulevard and
Ripley Lane intersection, as well as the I-405 northbound/southbound ramp
junctions. Coordination with adjacent land owners that have current or future access
permitted onto Lake Washington Boulevard shall also be conducted by the applicant
prior to preparation and submittal of final channelization plans for approval.
Consideration of pedestrian crossings and bicycle facilities, as required by the City,
shall also be incorporated into the channelization plan. Upon approval of the
channelization plan, the applicant shall prepare construction documents for joint
review by the City, WSDOT, and other affected agencies (i.e., King County), as
directed by the City. The developer shall provide right of way dedication on the
frontage of the subject site. The developer would be required to coordinate with the
owners of other properties to acquire any other right of way acquisition that is
needed to address the improvements required to mitigate the impacts of the project.
The developer and the City could coordinate to assist in the acquisition process, if
necessary.
Policy Nexus:
City of Renton Environmental Review Procedures (RMC 4-9-070); City of Renton Urban Design
Regulations (RMC 4-3-100); City of Renton Ordinance #5670 – Transportation Impacts Fee;
City of Renton Street Standards (RMC 4-6-060); City of Renton Parking, Loading, and Driveway
Standards (4-4-080) and, City of Renton Shoreline Master Program Regulations (RMC 4-3-090).
I. Cultural Resources
Refer to EIS Addendum Section 4.9 for a detailed discussion of Affected Environment and the
Impacts of the Quendall Terminals Project on cultural resources; also refer to FEIS Section 2-6
for a summary of the cultural resources impacts analysis. The mitigation measures established
below address the identified cultural resource-related impacts from the project.
Mitigation Measures and Discussion
I1. Limited and focused cultural resource monitoring shall be conducted during construction
activities on the site (clearing and grading of the upland portion, construction of deep
building foundations, and excavation of utilities). During construction, a monitoring plan
and inadvertent discovery plan shall be developed as part of the project (see Appendix F
to the Quendall Terminals EIS Addendum for a copy of the proposed monitoring plan
and inadvertent discovery plan).
I2. In the unlikely event that ground-disturbing or other activities result in the inadvertent
discovery of archaeological deposits, construction activities shall be halted in the
immediate area and the Washington State Department of Archaeology and Historic
Preservation (DAHP) shall be contacted. Work shall be halted until such time as further
investigation and appropriate consultation is concluded.
I3. In the unlikely event of the inadvertent discovery of human remains, construction shall
be halted in the area, the discovery shall be covered and secured against further
Quendall Terminals 32
Mitigation Document
August 2015
disturbance, and contact shall be made with law enforcement personnel, DAHP, and
authorized representatives of the concerned Indian tribes.
Discussion:
As described in EIS Addendum Appendix F, archaeological monitoring shall entail having an
archaeologist present during construction excavations below-fill to observe subsurface
conditions and identify any buried archaeological material that may be encountered.
Archaeological monitoring shall seek to identify potential buried surfaces, anthropogenic
sediments, and archaeological features such as shell middens, hearth, or artifact-bearing strata.
The monitoring archaeologist shall inspect project excavations and recovered sediments for
indications of such archaeological resources. Archaeological monitoring of construction
excavation shall proceed until it can be determined with a greater level of confidence that
human remains or other cultural resources are not likely to be impacted by construction
excavation for the project. Upon completion of monitoring, the archaeologist shall prepare a
report on the methods and results of the work, and recommendations for any necessary
additional archaeological investigations.
Upon discovery of a potential or actual archaeological site, or cultural resources as defined by
the RCW 27.44 Indian Graves and Records Act, and RCW 27.53 Archaeological Sites and
Resources, the applicant, their employees, contractors, and sub-contractors shall:
Immediately cease or halt ground-disturbing, construction or other activities around the
area of the discovery and secure the area with a perimeter of not less than thirty (30)
feet until all procedures are completed and the parties agree that activities can resume.
Notify the Local Government Archaeologist at DAHP and the Tribes of the discovery as
soon as possible, but no later than 24 hours after the discovery.
Arrange for the parties to conduct a joint viewing of the discovery within 48 hours of the
notification, or at the earliest possible time thereafter.
Consult with the Tribes and DAHP on the transfer and final disposition of artifacts.
If ground-breaking activities encounter human skeletal remains during the course of
construction, then all activity must cease that may cause further disturbance to those
remains and the area of the find must be secured and protected from further
disturbance. The findings of human skeletal remains shall be reported to the King
County Coroner’s Office and King County Sheriff’s Office in the most expeditious
manner possible.
The King County Coroner’s Office will assume jurisdiction over the human skeletal
remains and make a determination of whether those remains are forensic or non-
forensic. If the county coroner determines the remains are non-forensic, then they will
report the finding to DAHP who will then take jurisdiction of the remains.
The applicant or its authorized representative shall keep and maintain as confidential all
information regarding any discovered cultural resources.
Quendall Terminals 33
Mitigation Document
August 2015
Policy Nexus:
City of Renton Environmental Review Procedures (RMC 4-9-070); and, Revised Code of
Washington – Archaeological Sites and Resources (RCW 27.53).
J. Construction Impacts
Refer to DEIS Section 3.5 and FEIS Chapter 2 – Key Topic Areas for a discussion of Affected
Environment and the Impacts of the Quendall Terminals Project during construction on air
quality and noise. The mitigation measures below address the air quality and noise-related
construction impacts of the project.
Mitigation Measures and Discussion
Air Quality
J1. Site development and construction activities shall comply with applicable Puget Sound
Clean Air Agency (PSCAA) regulations regarding demolition activities and fugitive dust
emissions. If approved by the EPA, wetting of exposed soils, covering or wetting
transported earth materials, washing of truck tires and undercarriages prior to travel on
public streets, and prompt cleanup of any materials tracked or spilled onto public streets
shall be provided.
J2. The EPA cleanup/remediation process for the site and associated institutional control
requirements shall ensure that unacceptable exposures to contaminated soils/dust and
vapors shall not occur during or following construction. An OMMP shall be implemented
to prevent the excavation of soils, installation of utilities, and other site disturbances
without prior EPA approval.
Discussion:
Implementation of BMPs will reduce air emissions related to the construction phase of the
project. Possible management practices for reducing the potential for air quality impacts during
construction include measures for reducing both exhaust emissions and fugitive dust. The
Washington Associated General Contractors brochure “Guide to Handling Fugitive Dust from
Construction Projects” and the PSCAA suggest a number of methods for controlling dust and
reducing the potential exposure of people to emissions from diesel equipment. Some of the
possible control measures that could be implemented to reduce potential air quality impacts
from construction activities for the Quendall Terminals project include:
Use only equipment and trucks that are maintained in optimal operational condition.
Require all off-road equipment to have emission reduction equipment (e.g., require
participation in Puget Sound Region Diesel Solutions, a program designed to reduce air
pollution from diesel, by project sponsors and contractors).
Use car-pooling or other trip-reduction strategies for construction workers.
Implement restrictions on construction truck and other vehicle idling (e.g., limit idling to a
maximum of 5 minutes).
Quendall Terminals 34
Mitigation Document
August 2015
Spray exposed soil with water or other suppressant to reduce emissions and deposition
of particulate matter.
Pave or use gravel on staging areas and roads that would be exposed for long periods.
Cover all trucks transporting materials, wet materials in trucks, or provide adequate
freeboard (space from the top of the material to the top of the truck bed), to reduce
particulate matter emissions and deposition during transport.
Provide wheel washers to remove particulate matter that would otherwise be carried off
site by vehicles to decrease deposition of particulate matter on area roadways.
Cover dirt, gravel, and debris piles as needed to reduce dust and wind-blown debris.
Stage construction to minimize overall transportation system congestion and delays to
reduce regional emissions of pollutants during construction.
Noise
J3. Per the City of Renton’s construction standards related to permitted hours of work (RMC
4-4-030C), commercial and multifamily construction activities within 300 feet of
residential areas shall be restricted to the hours of 7:00 AM to 8:00 PM, Monday through
Friday. Work on Saturdays shall be restricted to the hours of 9:00 AM to 8:00 PM and no
work shall be permitted on Sundays. The City of Renton Development Services Director
shall be required to approve any work outside of these construction hours via a variance.
J4. Noise from construction shall be governed by the timing restrictions and the noise limits
included in the King County noise code requirements (KCC Section 12.88.040). This rule
defines maximum permissible sound levels based on the zoning of the source and
receiving properties and sets maximum levels and durations of allowable daytime
construction noise.
Discussion:
Certain practices can reduce the extent to which people are affected by construction noise and
ensure that construction noise levels stay within the applicable daytime sound level limits.
Examples of practices that could be implemented during project construction include:
Use properly sized and maintained mufflers, engine intake silencers, engine enclosures
and turning off idle equipment.
Make construction contracts specify that mufflers be in good working order and that
engine enclosures be used on equipment when the engine is the dominant source of
noise.
Locate stationary equipment as far away from sensitive receiving locations as possible.
Where this is not feasible, or where noise impacts are still significant, place portable
noise barriers around the equipment, with the opening directed away from sensitive
receiving locations.
Quendall Terminals 35
Mitigation Document
August 2015
To the extent feasible, substitute hydraulic or electric models for impact tools such as
jack hammers, rock drills, and pavement breakers to reduce construction and demolition
noise. Electric pumps could be specified if pumps are required.
Explore the feasibility of using broad-band or ambient sensing vehicle back-up alarms,
which are typically less noticeable than traditional pure-tone alarms.
Locate construction staging areas expected to be in use for more than a few weeks as
far as possible from sensitive receivers, particularly residences (i.e., adjacent to the
Barbee Mill development).
Use quiet equipment and temporary noise barriers to shield sensitive uses, and orient
work areas to minimize noise transmission to sensitive off-site locations.
Policy Nexus:
City of Renton Development Guidelines and Standards - Construction Standards (RMC 4-4-
030C); and, King County Environmental Sound Levels – Construction Equipment and Operation
(KCC Section 12.88.040).