HomeMy WebLinkAboutCO 4 CITY OF RENTON
CONTRACT CHANGE ORDER AGREEMENT
CAG-12-089 4 5/10/2013
PROJECT CHANGE ORDER EFFECTIVE DATE
NUMBER NUMBER
NE 3RDW"CORRIDOR IMPROVEMENTS PH 1 SANDERS GC, LLC
PROJECT TITLE CONTRACTOR
SUMMARY OF PROPOSED CHANGES:
1. Item A6 (revision to unit price)—Removal of Structure and Obstructions
During the course of excavating for signal foundation, the Contractor encountered a large boulder
not specified in the Contact documents. Sanders GC, LLC was directed to remove the boulder.
Work was tacked by Force Account No. 1081 at a cost of$1,773.39.
Bid Item A6— Removal of Structure and Obstructions per Lump Sum is hereby revised to reflect the
cost of removing the boulder.The original amount for this bid item is $1,550.00.The revised amount
for this bid item is$3,323.39.The net change amount for this item is an increase of$1,773.39.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
INCREASE of$1,773.39
2. Item A20(revision to estimated quantity)—Gravel Borrow Incl. Haul
The original estimated quantity of Gravel Borrow Ind. Haul is 3040 Tons. The project required less
Gravel Borrow Ind. Haul than originally estimated since the Contractor was able to reuse native
material as backfill. The revised estimated quantity of Gravel Borrow Ind. Haul is 1700 Tons. The
net quantity change for this item is a decrease 1340 Tons.
Bid Item A20 — Gravel Borrow Ind. Haul paid per Ton is hereby revised to reflect the revised
estimated quantity of 1700 Tons. The original estimated quantity of Gravel Borrow Incl. Haul is 3040
Tons at a unit price of$19.00/TN and total bid price of$57,760.00. The revised estimated quantity
of Gravel Borrow Ind. Haul is 1700 Tons at a total cost of$32,300.00. The net change amount for
this item is a decrease of$25,460.00.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
DECREASE of<$25,460.00>
3. Item A37(revision to estimated quantity)—Tie Bar with Drill Hole
The original estimated quantity of Tie Bar with Drill Hole is 520 Each. Per Feld Directive 018, the
City of Renton directed Prime Contractor, Sanders GC, LLC to proceed with completely separating the
new concrete pavement from existing concrete pavement with 3/4-inch joint material (see New Item
A133 specified below in this Change Order). This change reduced the amount of tie bar required for
the Project since the new and existing concrete pavement is no longer tied together with tie bar.
I
Change Order No.4 1 of 5
The revised estimated quantity of Tie Bar with Drill Hole is 120 Each. The net quantity change for
this item is a decrease 400 Each.
:Bid Item A37—Tie Bar with Drill Hole paid per Each is hereby revised to reflect the revised estimated
quantity of 120 Each. The original estimated quantity of Tie Bar with Drill Hole is 520 at a unit price
of$17.50/Each and total bid price of$9,100.00. The revised estimated quantity of`fie Bar with Drill
Hole is 120 Each at a total cost of$2,100.00. The net change amount for this item is a decrease of
$7,000.00.
The total Change Order amount for Prime Contractor,Sanders GC,LLC for this item is an
DECREASE of<$7,000.00>
4. Item A39(revision to estimated quantity)—HMA CI. 1h In.PG 64-22
The original estimated quantity of HMA Cl. 1h In. PG 6422 is 830 Tons. The project required less
HMA Cl. 1/2 In. PG 64-22 than originally estimated. The revised estimated quantity of HMA Cl. 1h In.
PG 64-22 is 730 Tons. The net quantity change for this item is a decrease 100 Tons.
Bid Item A37 — HMA Cl. ih In. PG 6422 paid per Ton is hereby revised to reflect the revised
estimated quantity of 730 Tons. The original estimated quantity of HMA G. 1h In. PG 6422 is 830
Tons at a unit price of $136.00/TN and total bid price of $112,880.00. The revised estimated
quantity of HMA CI. 112 In. PG 64-22 is 730 Tons at a total cost of $99,280.00. The net change
amount for this item is a decrease of$13,600.00.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
DECREASE of<$13,600.00>
S. Item A121 (revision to unit price)—Minor Change
Bid Item A121 — Minor Change per Estimated Cost is hereby revised to reflect the additional cost of
unanticipated differing site conditions encountered in the field. The original amount for this bid item
is $20,000. The revised amount for this bid item is $35,000. The net change amount for this item is
an increase of$15,000.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
INCREASE of$15,000
6. New Item A130—New Retaining Wall
Per Field Directive 16, Prime Contractor, Sanders GC, LLC constructed new wall between Safeway
fuel station and Safeway Driveway at Whitman Ct. New wall provides flinch curb reveal above fuel
station walkway/parking lot to remedy approximate 18-inch grade difference between back of new
sidewalk and existing grade at fuel station.
Bid Item A130—New Retaining Wall per Lump Sum is hereby created to reflect changes specified in
Field Directive 016. The amount for this new bid item is $2,651.80.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
INCREASE of$2,651.80
Change Order No.4 2 of 5
' 0 •
7. New Item A131—Revised Channeiization
Per Field Directive 21, the City of Renton directed Prime Contractor, Sanders GC, LLC to proceed with
revised channelization to reduce the amount of traffic curbing and revise the Safeway/O'Reilly
driveway exit to right turn only. These changes will provide improved traffic safety and operations.
All work and costs associated with this change to be paid using existing bid items and by Force
Account. Per Field Directive 21
Farce Account to be tracked and paid using existing Bid Item .0121 -
Minor Change. New Item .0131 - Revised Chan i
g nelizat on per Estimated Cost is hereby seated for
Force Account specified in Field Directive 21. All Force Account work associated with this change
previously paid under existing Bid Item A121 — Minor Change to be transferred to New Item A131 —
Revised Channelization. As noted in Field Directive 21, all other work to be paid via unit prices under
existing bid items. The amount for this new bid item is $2,000.00.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
INCREASE of$2,000.00
8. New Item A132—Revised Irrigation Sys. USPS
Per Field Directive 3, the City of Renton directed Prime Contractor, Sanders GC, LLC to proceed with
revised irrigation system along Whitman Ct NE through USPS property. Revised system restored
irrigation system disturbed by construction of new bioswale and mail drop. Work was tracked by
Force Account No. 1004 and 1005 at a cost of$8,991.20.
Bid Item A132— Revised Irrigation System USPS per Lump Sum is hereby created to reflect changes
specified in Field Directive 003. The amount for this new bid item is $8,991.20.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
INCREASE of$8,991.20
9. New Item A133—Separate New Conc.from Ex. Conc.
Per Field Directive 018, the City of Renton directed Prime Contractor, Sanders GC, LLC to proceed
with completely separating new concrete pavement from existing concrete pavement with 3/4-inch
joint material. The existing concrete pavement was not thick enough for the installation of tie bars.
The City authorized this change on the basis of Cost Proposal #9 provided by Sanders GC, LLC.
Bid Item A133 — Separate New Concrete from Existing Concrete per Lump Sum is hereby created to
reflect changes specified in Feld Directive 018. The amount for this new bid item is $8,147.07.
The total Change Order amount for Prime Contractor, Sanders GC, LLC for this item is an
INCREASE of$8,147.07
10.New Item C21—Misc. Restoration Improvements
Per direction from City of Renton and King County Water District 90(KCWD90), Prime Contractor,
Sanders GC, LLC provided additional restoration improvements surrounding the KCWD90 Pump
Station building. Improvements included increasing the extents of driveway apron, minor grading,
t
Change Order No.4 3 of 5
I
tree removal, placing gravel around building and paving pedestrian access ramp. KCWD90
requested and authorized these change on the basis of cost proposal provided by Sanders GC,LLC
New Bid Item C21—Mist Restoration Improvements per Lump Sum is hereby created to reflect
changes requested by'KCWD90.
The total Change Order amount for Prime Contractor,Sanders GC, LLC for this item is an
iNCREASE of$3,736A2
11.Change Order No. 3—Ales Tax Omission
Per Change Order No. 3,New Item C20—Waterline Revisions was created at a cost of$579.04.
Change Order No. 3 erroneously did not account for 9.5%sales tax for this new item. To resolve
Change Order No. 3 sales tax omission, $55.01 is hereby added to the Contract.
The total Change Order amount for Prime Contractor,Sanders GC, LLC for this item is an
INCREASE of$55.01
12.Time Extension
Based on the City of Renton`s review of Sanders GC, LLC schedule and as a result of changes to
electrical items specified by the City of Renton in Change Order No. 1 in conjunction with revised
channelization specified by the City of Renton in this Change Order,the difference between the
pr9ject expiration of Contract working days(May e, 2013)and the projected completion date(May
20 , 2013) is 10 working days.
The total number of working days specified in the Contract is hereby increased by 10 days from 142
working days to 152 working days.
ORIGINAL NEW
CHANGE UNIT UNIT ADD OR
ITEM NO. DESCRIPTION QUANTITY PRICE PRICE <DEDUCT>
SCHEDULE A
Bid Item A6 Removal of Structures&.Obstructions 1 LS $1,550.00 $3,323.39 $1,773.39
Bid Item A20 Gravel Borrow Ind. Haul <1340> TN $57,760.00 $32,300.00 <$25,460.00>
Bid Item A37 Tie Bar with Drill Hole <400> EA $9,100.00 $2,100.00 <$7,000.00>
Bid Item A39 HMA Cf. 1!2 In PG 6422 <100>TN $112,880.00 $99,280.00 <$13,600.00>
Bid Item A121 Minor Change EST $20,000.00 $35,000.00 $15,000.00
New Bid Item A130 Block Wall Revisions 1 LS $2,651.80 $2,651.80
New Bid Item A131 Revised Channelization 1 LS $2,000.00 $2,000.00
New Bid Item A132 Revised Irrigation Sys. USPS 1 LS $8,991.20 $8,991.20
New Bid Item A133 Sep New Conc from Ex Conc 1 LS $8,147.07 $8,147.07
TOTAL SCHEDULE A <$7,496.54>
SCHEDULE C
New Item C21 Misc. Restoration Improvements 1 LS $3,736.42 $3,736.42
SUBTOTAL SCHEDULE C: $3,736.42
9.5% SALES TAX $354.96
Change Order No. 3 Sales Tax Omission $55.01
TOTAL SCHEDULE C $4,146.39
Change Order No.4 40f 5
TOTAL NET CONTRACT INCREASE <$3,350.15>
An independent cost analysis has been performed ®Yes❑ No
The time provided for completion in the Contract is ❑ Unchanged ® Increased ❑ Decreased by 19
Working Days. This Document shall become an Amendment to the Contract and all provisions of the
Contract not amended herein will apply to this Change Order.
Will this change affect expiration or extent of Insurance coverage? ❑Yes❑ No
If"Yes"Will the Policies Ie'Extended? ❑Yes❑ No
STATEMENT:
Payment for the above work wi11 be in accordance with applicable portions of the standard spedfiiations,
and with the understanding that all materials, workmanship and measurements shall be in accordance
with the provisions of the standard spmfrcations, the contract plans, and the special provisions
governing the types of construcfon. By acmpting this change order, the parties agree that this d5ange
order represents full compensation for all work associated with this change order: Ato additional
compensation or daim,per section 1-04.5, will be allowed.
DEPARTMENT RECAP TO DATE:
ORIGINAL CONTRACT AMOUNT $ 2,129,217.14
PREVIOUS CHANGE ORDERS $ 91,840.38
THIS MANGE ORDER $ <3,350.15>
NEW CONTRACT AMOUNT $ 2,217,707.37
CONTRACTOR DATE
f1 � l3
ROBERT M. ?VS0 ,1-P.E. DATE
CITY OF RENTON
Change Order No.4 5 of s .