NOTICE OF APPLICATION AND PROPOSED
DETERMINATION OF NON-SIGNIFICANCE (DNS)
A Master Application has been filed and accepted with the Department of Community & Economic
Development (CED) – Planning Division of the City of Renton. The following briefly describes the application
and the necessary Public Approvals.
DATE OF NOTICE OF APPLICATION: April 30, 2018
LAND USE NUMBER: LUA17-000163, PP, ECF, SA-A, CU-P
PROJECT NAME: PR17-000185 28 Hundred Unit Lot Subdivision
PROJECT DESCRIPTION: The applicant is requesting Preliminary Plat approval, Site Plan approval,
Environmental (SEPA) Review, a street modification, and Conditional Use Permit approval for the construction
of 11 townhomes on individual unit lots within the Residential-14 zoning designation. The townhomes would
be constructed within two 4-unit buildings, and one 3-unit building. One of the townhomes would be reserved
as an affordable dwelling unit. The proposed lots would range in area from 960 square feet to 1,155 square feet.
In addition, two common area tracts are proposed (Tracts A and C). The applicant is requesting a Condi tional
Use Permit for an increase in the maximum floor plate height from 24 feet to 32 feet. Access to the proposed
units is proposed via a 38-foot wide unit lot driveway within Tract B. A street modification is requested to
reduced the required right-of-way dedication and frontage improvement requirements along NE 12th Street.
The site is located within a Wellhead Protection Area, zone 2.
PROJECT LOCATION: 2800 NE 12th St, Renton, WA 98056
OPTIONAL DETERMINATION OF NON-SIGNIFICANCE (DNS): As the Lead Agency, the City of Renton has
determined that significant environmental impacts are unlikely to re sult from the proposed project. Therefore,
as permitted under the RCW 43.21C.110, the City of Renton is using the Optional DNS process to give notice
that a DNS is likely to be issued. Comment periods for the project and the proposed DNS are integrated into a
single comment period. There will be no comment period following the issuance of the Threshold
Determination of Non-Significance (DNS). This may be the only opportunity to comment on the environmental
impacts of the proposal. A 14-day appeal period will follow the issuance of the DNS.
PERMIT APPLICATION DATE: March 23, 2017
NOTICE OF COMPLETE APPLICATION: March 30, 2017
APPLICANT/PROJECT CONTACT PERSON: James Howton, JKH Pacific
12018 SE 51st St, Bellevue WA 98006
Permits/Review Requested: Environmental (SEPA) Review, Preliminary Plat Approval
Other Permits which may be required: Building Permit, Construction Permit
Requested Studies: Geotechnical Report, Arborist Report, Drainage Report
Location where application
may be reviewed: Application documents are now available online through the City of Renton
Document Center website
PUBLIC HEARING: Public hearing is tentatively scheduled for July 10, 2018 before the Renton
Hearing Examiner in Renton Council Chambers at 11:00 am on the 7th floor of
Renton City Hall located at 1055 South Grady Way.
CONSISTENCY OVERVIEW:
Zoning/Land Use: The subject site is designated Residential-14 (R-14) and is located within a
Wellhead Protection Area, zone 2.
If you would like to be made a party of record to receive further information on this proposed project, complete this form
and return to: City of Renton, CED – Planning Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR17-000185 28 Hundred Unit Lot Subdivision/LUA17-000163, PP, ECF, SA-A, CU-P
NAME:
MAILING ADDRESS: City/State/Zip:
TELEPHONE NO.:
Environmental Documents that
Evaluate the Proposed Project: Environmental (SEPA) Checklist
Development Regulations
Used For Project Mitigation: The project will be subject to the City’s SEPA ordinance, RMC 4-2-110A, 4-
3-050, 4-4-070, 4-4-130, 4-6-060, 4-7-070 and other applicable codes and
regulations as appropriate.
Proposed Mitigation Measures: None are recommended at this time.
Comments on the above application must be submitted in writing to Jill Ding, Senior Planner, CED – Planning
Division, 1055 South Grady Way, Renton, WA 98057, by 5:00 PM on May 14, 2017. If you have questions about
this proposal, or wish to be made a party of record and receive additional notification by mail, contact the
Project Manager. Anyone who submits written comments will automatically become a party of record and will
be notified of any decision on this project. A copy of the subsequent threshold determination is available upon
request.
CONTACT PERSON: Jill Ding, Senior Planner; Tel: (425) 430-6598;
Email: jding@rentonwa.gov