HomeMy WebLinkAboutDECISION_LUA18000328_PSE POLE REPLACEMENTPLANNING DIVISION
CERTIFICATE OF EXEMPTION
FROM SHORELINE SUBSTANTIAL DEVELOPMENT
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
DATE:
PROJECT NUMBER:
PROJECT NAME:
PROJECT MANAGER:Angelea Weihs, Assoicate Planner
LUA18-000328, SME
Talbot Paccar Transmission Line Reconductor
May 11, 2018
OWNER:Puget Sound Energy
Kerry Kriner
PO Box 97034 M/S PSE-09N
Bellevue, WA 98009-9734
PROJECT LOCATION:1719 MAPLE VALLEY HWY
PROJECT DESCRIPTION:Puget Sound Energy (PSE) is requesting approval of a Shoreline Exemption and Critical
Areas Exemption for proposed repair and maintenance activities on approximately 1.5
miles of existing Talbot – PACCAR 115 kV transmission line corridor (See Exhibit 1).
The repair and maintenance activities would include replacing aging infrastructure and
providing greater reliability within the transmission system. The properties included in the
Shoreline and Critical Area Exemption request include a total of eight (8) parcels
(1723059015, 1723059013, 2023059008, 2023059007, 0007200187, 0007200001,
1723059178, and 1723059107). PSE will replace 17 of the existing 31 wood poles within
the corridor, reframe the remaining 14 poles, and replace the existing conductor with a
smaller conductor of the same voltage. Nine (9) of the replacement poles and six (6) of
the poles to be reframed are located within critical areas or critical area buffers. Of the 31
poles proposed for replacement/reframing, three (3) poles are located within Cedar River
Regulated Shoreline Jurisdiction (Shoreline High Intensity and Urban Conservancy;
Cedar River Reach C), two (2) poles are located within wetland buffers, and nineteen (19)
of the poles are located within geologic hazards.
The applicant submitted a Stream Study (dated February 9, 2018; See Exhibit 2),
prepared by GeoEngineers, with the project application. GeoEngineers, Inc.
(GeoEngineers) was contracted by Puget Sound Energy (PSE) to provide a stream
study for the Talbot-Paccar 115 kV Re-Conductor Pole Replacement project for three (3)
poles proposed to be replaced within the shoreline jurisdiction of the Cedar River
(Parcels 1723059015 and 1723059013). The report states that, in the vicinity of the
project, the existing condition of the Cedar River shoreline is a developed city park with
buildings, passive park areas, and paved and unpaved driveways and walkways.
Vegetation adjacent to the Cedar River (within approximately 50 to 75 feet of the Ordinary
High Water Mark (OHWM)) is predominantly composed of black cottonwood, red alder,
big leaf maple, snowberry, Himalayan blackberry, Japanese knotweed and sword fern.
According to the report, the three (3) poles proposed to be replaced are all located within
areas devoid of native vegetation. Poles 1/13 and 1/14 (numbered and identified in Exhibit
1) are located within a grass area between a paved pedestrian path and unpaved informal
path within Renton’s Cedar River Park, approximately 100 to 150 feet from the OHWM of
the river. Pole 1/15 is also located in the park on the opposite side of the river,
approximately 70 feet from the river bank, situated in an open area at the end of a gravel
Page 1 of 4
City of Renton Department of Community & Economic Development Certificate of Exemption from Shoreline Substantial Development
Talbot Paccar Transmission Line Reconductor LUA18-000328, SME
access path that follows the transmission corridor. All three (3) poles will be replaced
with wood poles, and replacement conductor will be installed along the transmission
corridor, including the Cedar River crossing. Poles 1/13 and 1/14 are existing 70 and
80-foot tall wood poles, respectively, that will be replaced with the same sized poles.
Pole 1/15 is an existing 85-foot tall wood pole that will be replaced with a 90-foot wood
pole. The poles will be accessed from existing paved and gravel pathways and no native
vegetation is proposed for removal; however, minor trimming is proposed to facilitate
construction.
The report states that poles will be replaced in the same general location as the existing
poles. Pole holes will be augered to a depth of approximately 10 feet and a width of 3 to
4 feet. Removed pole holes will be backfilled with native soils and restored to
pre-construction conditions. Replacement poles will be backfilled with crushed gravel to
set in wetter soils or installed within a caisson. The report states that appropriate
stormwater best management practices (BMPs) will be used based on a project
temporary erosion and sediment control (TESC) plan and input from an onsite Certified
Erosion and Sediment Control Lead (CESCL) inspector. Conductor stringing sites will be
located south of Pole 1/14 and north of 1/16 (outside the shoreline jurisdiction), resulting
in replacement conductor being aerially pulled in place. No work will occur in water or
below the OHWM of the river.
The report concludes that, while the Cedar River provides critical habitat for Chinook
salmon and steelhead, the project will not involve in-water work and construction
activities will not disturb in-water habitat. In addition, no tree removal or vegetation
removal is proposed other than minor trimming. Therefore, none of the species,
associated habitat, or nearby vegetation within the shoreline jurisdiction will be impacted
by the proposed project.
The applicant submitted a Stream and Wetland Evaluation (dated February 9, 2018; See
Exhibit 3), prepared by GeoEngineers, with the project application. GeoEngineers was
authorized to conduct wetland and stream delineation evaluation for the Talbot-Paccar
Re-Conductor project in the vicinity of poles 0/13 and 0/14 ( Exhibit 1). The proposed
project is located northeast of the Talbot Road South and I-405 intersection (Parcel
number 2023059007). A total of two (2) wetlands (identified as Wetlands A and B) and
one (1) stream (Rolling Hills Creek) were identified within and adjacent to the
transmission corridor. The report states that Wetland A meets the criteria for a Category
III wetland and would require a 100-foot buffer and Wetland B meets the criteria for a
Category IV wetland and would require a 50-foot buffer. Rolling Hills Creek is a mapped
Type F stream, which would require a 115-foot buffer. Construction equipment will access
the poles via an existing gravel access pathway to reframe the two (2) existing poles.
The report concludes that no permanent impacts to critical areas or their associated
buffers will occur as a result of this project, as there will be no ground disturbance as a
result of the pole repair and maintenance activities beyond temporary access using an
existing path.
The applicant submitted a Geotechnical Evaluation (dated February 19, 2018; See
Exhibit 4), prepared by GeoEngineers, with the project application. The report states
that, of the 31 poles proposed for replacement/reframing, 19 (9 pole replacements and 10
reframed poles) are located within regulated geologic hazard areas. The report states
that the only potential impact to geologic hazards for the reframed poles would be
associated with access; therefore, GeoEngineers reviewed the 10 reframed poles for
access needs, four (4) of which were excluded from further review due to availability of
paved access. The study provides further review on the remaining 15 reframed/replaced
poles and their impact on sensitive and protected slopes, high erosion hazards, and
medium, high, and very high landslide hazards. The report states that no active areas of
landsliding, slope movement, or erosion in the areas of the proposed
Page 2 of 4
City of Renton Department of Community & Economic Development Certificate of Exemption from Shoreline Substantial Development
Talbot Paccar Transmission Line Reconductor LUA18-000328, SME
replacement/reframing were observed.
The study states that PSE Standard Best Management Practices (BMPs) are sufficient
for pole replacement at most locations. The pole locations can be accessed from
existing site access, the majority of which consists of paved or otherwise improved
areas. Only two (2) localized areas will require the re-establishment of construction
access using a gravel overlay. The study recommends avoiding cuts into the hillslope
upslope of the poles and completing the work during the dry season. The study also
recommends that soils removed from the new pole excavation be removed from the site
and disposed of at an off-site disposal facility or in a stable location. The study
concludes that the proposal can be safely accommodated at the sites, and that it is not
anticipated that the proposed pole improvements will increase the threat of mapped
geologic hazards to adjacent properties beyond pre-development conditions, or adversely
impact other critical areas.
Staff recommends, as a condition of approval, that the applicant follow the
recommendations provided in the Geotechnical Evaluation (dated February 19, 2018)
prepared by GeoEngineers. In addition, staff recommends as a condition of approval, that
if any tree trimming in excess of forty percent (40%) of the tree canopy becomes
necessary within critical areas or buffers, that the applicant notify the Current Planning
Project Manager in writing prior to tree trimming activities.
SEC-TWN-R: NW17 - 23 - 5
LEGAL DESCRIPTION:
(King County Assessor)POR OF GL 4 IN W 1/2 & SW 1/4 OF NE 1/4 & SE 1/4 LY
BTWN COLUMBIA & PUGET SOUND R/W & RENTON-MAPLE
VALLEY RD & NLY OF LN BEG ON WLY MARGIN OF SAID
ROAD 80 FT NWLY FROM S LINE OF NE 1/4 TH S 47-52-00 W
273.22 FT TH S 88-26-00 W 251.95 FT TH S 39-24-35 W 73.20
FT TH N 79-04-40 W 176.04 FT TH S 27-52-20 W LESS ST HWY
LESS BEG INTSN SELY LINE & SLY MGN OF MAPLE VALLEY
RD TH NWLY ALG SD MGN 60 FT TO POB TH CONTG NWLY
100 FT TH SWLY PLW SD SELY LN 225 FT TH SELY PLW SD
MGN 100 FT TH NELY 225 FT TO POB LESS POR LY NWLY
OF A LN BAAP OPPOSITE HWY ENGR STA HES LN 259+91.82
P C ON THE LN LINE SURVEY OF SR 405 RENTON S
CURVES & 80 FT SELY THEREFROM TH NELY PLW SD LN
SURVEY TAP OPPOSITE HES LN 267+60 TH NELY TAP
OPPOSITE HES LN 271+00 ON SD LINE SURVEY & 114 FT
SELY THEREFROM TH NELY PLW SD LINE SURVEY TAP
OPPOSITE HES LN 273+00 POT THEREON & END OF LINE
FOR STATE HWY LESS POR FOR RD PER DEED
#20050418000001
SEC-TWN-R: SE17 - 23 - 5
LEGAL DESCRIPTION:
(King County Assessor)PARCEL 1 CITY OF RENTON LOT LINE ADJUSTMENT NO LUA
13-000410 RECORDING NO 20140326900013 (BEING A
PORTION OF NW QTR SW QTR STR 17-23-05 AND OF W
HALF SE QTR STR 17-23-05)
WATER BODY/REACH:Cedar River Reach C
EXEMPTION JUSTIFICATION: An exemption from a Shoreline Management Substantial Development Permit is hereby
Approved with Conditions* on the proposed project in accordance with RMC 4.9.190C 'Exemption from Permit System'
and for the following reasons:
Page 3 of 4
CityofRentonDepartmentofCommunity&EconomicDevelopmentCertificateofExemptionfromShorelineSubstantialDevelopmentTalbotPaccarTransmissionLineReconductorLUAJ8-000328,SMEMaintenanceandRepair:Normalmaintenanceorrepairofexistingstructuresordevelopments,includingdamagebyaccident,fireorelements.Theproposeddevelopmentis:ConsistentwiththepoliciesoftheShorelineManagementAct.ConsistentwiththeguidelinesoftheDepartmentofEcologywherenoMasterProgramhasbeenfinallyapprovedoradoptedbytheDepartment.ConsistentwiththeCityofRentonShorelineMasterProgram.CONDITIONS:PLN-AdministrativeDecisionConditionI.TheapplicantshallfollowtherecommendationsprovidedintheGeotechnicalEvaluation(datedFebruary19,2018),preparedbyGeoEngineers.PLN-AdministrativeDecisionCondition2.Ifanytreetrimminginexcessoffortypercent(40%)ofthetreecanopybecomesnecessarywithincriticalareasorbuffers,thattheapplicantshallnotifytheCurrentPlanningProjectmanagerinwritingpriortotreetrimmingactivities.SIGNATURE&DATEOFDECISION:\W)QAJd1/‘M(”tc—6ftI/‘2’01JennerHenngDateRECONSIDERATION:Within14daysofthedecisiondate,anypartyofrecordmayrequestthatthedecisionbereopenedbytheapprovalbody.Theapprovalbodymaymodifyhisdecisionifmaterialevidencenotreadilydiscoverablepriortotheoriginaldecisionisfoundorifhefindstherewasmisrepresentationoffact.Afterreviewofthereconsiderationrequest,iftheapprovalbodyfindssufficientevidencetoamendtheoriginaldecision,therewillbenofurtherextensionoftheappealperiod.Anypersonwishingtotakefurtheractionmustfileaformalappealwithinthe14dayappealtimeframe.APPEALS:Theadministrativelandusedecisionwillbecomefinalifnotappealedinwritingtogetherwiththerequiredfeeto:HearingExaminer,CityofRenton,1055SouthGradyWay,Renton,WA98057onorbefore5:00pm,onMay25,2018(RCW43.21.C075(3);WACI97-11-680).RMC4-8-110governsappealstotheHearingExaminerandadditionalinformationregardingtheappealprocessmaybeobtainedfromtheRentonCityClerk’soffice,RentonCityHall,7thFloor,(425)430-6510.EXPIRATION:Two(2)yearsfromthedateofdecision(datesigned)Attachments:SitePlan,StreamStudy,WetlandandStreamEvaluation,GeotechReportcc:PugetSoundEnergyKerryKriner-OwnerPage4of4
!
!
!
!
!
!
!
!
!
!!!
!
!!!
!!
!
!
!!!
!
!
!
!
!
!!!
0/13
0/14
0/15
0/16
0/17
1/1
1/2
1/3
1/4
1/5 1/6 1/7
1/8
1/9
1/10 1/11
1/12 1/13
1/14
1/15
1/16 1/17
1/18
1/19
1/20
1/21
2/1 2/2
2/3 2/4 2/5
S 2nd St
MainAveSF
a
ctory
Pl
N
N 3rd St
S 3rd St Bronson Way SBronsonWayNNE3rdSt
S Grady WayMa
p
l
e
V
a
l
l
e
y
H
w
yParkAveNSunsetBlvdN
I-405 FWYHouserWayN Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,AeroGRID, IGN, and the GIS User Community
Index Map
Puget Sound EnergyTalbot-PACCAR 115 kV Re-conductorRenton, Washington
Figure 2
µ500 0 500
Feet
!Replacement Pole
!Reframe Pole
115kV Re-conductor Alignment
Notes:1. The locations of all features shown are approximate.2. This drawing is for information purposes. It is intended toassist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and contentof electronic files. The master file is stored by GeoEngineers,Inc. and will serve as the official record of this communication.
Projection: NAD 1983 StatePlane Washington North FIPS 4601 Feet
Data Source: Geology from King County. Basemap from Mapbox Open Street Map, 2017 Contours from City of Renton
Stream Study
Talbot-Paccar 115-kV Re-Conductor
Pole Replacement
Renton, Washington
for
Puget Sound Energy
February 9, 2018
Focused Stream and Wetland Evaluation
Talbot-Paccar 115-kV Re-Conductor
Pole Replacement
Renton, Washington
for
Puget Sound Energy
February 9, 2018