HomeMy WebLinkAboutDECISION_LUA18000334_PSE POLE REPLACEMENTDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
PLANNING DIVISION
CERTIFICATE OF EXEMPTION
FROM CRITICAL AREAS REGULATIONS
EVALUATION FORM & DECISION
DATE:
PROJECT NUMBER:
PROJECT NAME:
PROJECT MANAGER:
May 11, 2018
LUA18-000334
Talbot Paccar Transmission Line Reconductor
Angelea Weihs, Assoicate Planner
CONTACT:Kerry Kriner, Puget Sound Energy
PO Box 97034 M/S PSE-09N
Bellevue, WA 980099734
LOCATION:1715 MAPLE VALLEY HWY
DESCRIPTION:Puget Sound Energy (PSE) is requesting approval of a Shoreline Exemption and Critical
Areas Exemption for proposed repair and maintenance activities on approximately 1.5
miles of existing Talbot – PACCAR 115 kV transmission line corridor (See Exhibit 1). The
repair and maintenance activities would include replacing aging infrastructure and providing
greater reliability within the transmission system. The properties included in the Shoreline
and Critical Area Exemption request include a total of eight (8) parcels (1723059015,
1723059013, 2023059008, 2023059007, 0007200187, 0007200001, 1723059178, and
1723059107). PSE will replace 17 of the existing 31 wood poles within the corridor,
reframe the remaining 14 poles, and replace the existing conductor with a smaller
conductor of the same voltage. Nine (9) of the replacement poles and six (6) of the poles
to be reframed are located within critical areas or critical area buffers. Of the 31 poles
proposed for replacement/reframing, three (3) poles are located within Cedar River
Regulated Shoreline Jurisdiction (Shoreline High Intensity and Urban Conservancy; Cedar
River Reach C), two (2) poles are located within wetland buffers, and nineteen (19) of the
poles are located within geologic hazards.
The applicant submitted a Stream Study (dated February 9, 2018; See Exhibit 2),
prepared by GeoEngineers, with the project application. GeoEngineers, Inc.
(GeoEngineers) was contracted by Puget Sound Energy (PSE) to provide a stream study
for the Talbot-Paccar 115 kV Re-Conductor Pole Replacement project for three (3) poles
proposed to be replaced within the shoreline jurisdiction of the Cedar River (Parcels
1723059015 and 1723059013). The report states that, in the vicinity of the project, the
existing condition of the Cedar River shoreline is a developed city park with buildings,
passive park areas, and paved and unpaved driveways and walkways. Vegetation adjacent
to the Cedar River (within approximately 50 to 75 feet of the Ordinary High Water Mark
(OHWM)) is predominantly composed of black cottonwood, red alder, big leaf maple,
snowberry, Himalayan blackberry, Japanese knotweed and sword fern. According to the
report, the three (3) poles proposed to be replaced are all located within areas devoid of
native vegetation. Poles 1/13 and 1/14 (numbered and identified in Exhibit 1) are located
within a grass area between a paved pedestrian path and unpaved informal path within
Renton’s Cedar River Park, approximately 100 to 150 feet from the OHWM of the river.
Page 1 of 5
City of Renton Department of Community & Economic Development Certificate of Exemption from Critical Areas Regulations
Talbot Paccar Transmission Line Reconductor LUA18-000334
Pole 1/15 is also located in the park on the opposite side of the river, approximately 70
feet from the river bank, situated in an open area at the end of a gravel access path that
follows the transmission corridor. All three (3) poles will be replaced with wood poles, and
replacement conductor will be installed along the transmission corridor, including the
Cedar River crossing. Poles 1/13 and 1/14 are existing 70 and 80-foot tall wood poles,
respectively, that will be replaced with the same sized poles. Pole 1/15 is an existing
85-foot tall wood pole that will be replaced with a 90-foot wood pole. The poles will be
accessed from existing paved and gravel pathways and no native vegetation is proposed
for removal; however, minor trimming is proposed to facilitate construction.
The report states that poles will be replaced in the same general location as the existing
poles. Pole holes will be augered to a depth of approximately 10 feet and a width of 3 to 4
feet. Removed pole holes will be backfilled with native soils and restored to
pre-construction conditions. Replacement poles will be backfilled with crushed gravel to
set in wetter soils or installed within a caisson. The report states that appropriate
stormwater best management practices (BMPs) will be used based on a project
temporary erosion and sediment control (TESC) plan and input from an onsite Certified
Erosion and Sediment Control Lead (CESCL) inspector. Conductor stringing sites will be
located south of Pole 1/14 and north of 1/16 (outside the shoreline jurisdiction), resulting
in replacement conductor being aerially pulled in place. No work will occur in water or
below the OHWM of the river.
The report concludes that, while the Cedar River provides critical habitat for Chinook
salmon and steelhead, the project will not involve in-water work and construction activities
will not disturb in-water habitat. In addition, no tree removal or vegetation removal is
proposed other than minor trimming. Therefore, none of the species, associated habitat, or
nearby vegetation within the shoreline jurisdiction will be impacted by the proposed
project.
The applicant submitted a Stream and Wetland Evaluation (dated February 9, 2018; See
Exhibit 3), prepared by GeoEngineers, with the project application. GeoEngineers was
authorized to conduct wetland and stream delineation evaluation for the Talbot-Paccar
Re-Conductor project in the vicinity of poles 0/13 and 0/14 ( Exhibit 1). The proposed
project is located northeast of the Talbot Road South and I-405 intersection (Parcel
number 2023059007). A total of two (2) wetlands (identified as Wetlands A and B) and one
(1) stream (Rolling Hills Creek) were identified within and adjacent to the transmission
corridor. The report states that Wetland A meets the criteria for a Category III wetland and
would require a 100-foot buffer and Wetland B meets the criteria for a Category IV wetland
and would require a 50-foot buffer. Rolling Hills Creek is a mapped Type F stream, which
would require a 115-foot buffer. Construction equipment will access the poles via an
existing gravel access pathway to reframe the two (2) existing poles. The report concludes
that no permanent impacts to critical areas or their associated buffers will occur as a
result of this project, as there will be no ground disturbance as a result of the pole repair
and maintenance activities beyond temporary access using an existing path.
The applicant submitted a Geotechnical Evaluation (dated February 19, 2018; See Exhibit
4), prepared by GeoEngineers, with the project application. The report states that, of the
31 poles proposed for replacement/reframing, 19 (9 pole replacements and 10 reframed
poles) are located within regulated geologic hazard areas. The report states that the only
potential impact to geologic hazards for the reframed poles would be associated with
access; therefore, GeoEngineers reviewed the 10 reframed poles for access needs, four
(4) of which were excluded from further review due to availability of paved access. The
study provides further review on the remaining 15 reframed/replaced poles and their impact
on sensitive and protected slopes, high erosion hazards, and medium, high, and very high
landslide hazards. The report states that no active areas of landsliding, slope movement,
Page 2 of 5
City of Renton Department of Community & Economic Development Certificate of Exemption from Critical Areas Regulations
Talbot Paccar Transmission Line Reconductor LUA18-000334
or erosion in the areas of the proposed replacement/reframing were observed.
The study states that PSE Standard Best Management Practices (BMPs) are sufficient
for pole replacement at most locations. The pole locations can be accessed from existing
site access, the majority of which consists of paved or otherwise improved areas. Only
two (2) localized areas will require the re-establishment of construction access using a
gravel overlay. The study recommends avoiding cuts into the hillslope upslope of the poles
and completing the work during the dry season. The study also recommends that soils
removed from the new pole excavation be removed from the site and disposed of at an
off-site disposal facility or in a stable location. The study concludes that the proposal can
be safely accommodated at the sites, and that it is not anticipated that the proposed pole
improvements will increase the threat of mapped geologic hazards to adjacent properties
beyond pre-development conditions, or adversely impact other critical areas.
Staff recommends, as a condition of approval, that the applicant follow the
recommendations provided in the Geotechnical Evaluation (dated February 19, 2018)
prepared by GeoEngineers. In addition, staff recommends as a condition of approval, that
if any tree trimming in excess of forty percent (40%) of the tree canopy becomes
necessary within critical areas or buffers, that the applicant notify the Current Planning
Project Manager in writing prior to tree trimming activities.
CRITICAL AREA:Cedar River Regulated Shoreline Jurisdiction, Wetland and Stream Buffers, and Geologic
Hazards, including sensitive and protected slopes, landslide hazards, and erosion
hazards.
EXEMPTION JUSTIFICATION:RMC 4-3-050C.3.e.iii. Utilities, Traffic Control, Walkways, Bikeways Within Existing,
Improved Right-of-Way or Easements
Page 3 of 5
CityofRentonDepartmentofCommunity&EconomicDevelopmentCertificateofExemptionfromCriticalAreasRegulationsTalbotPaccarTransmissionLineReconductorLUAI8-000334FINDINGS:TheproposeddevelopmentisconsistentwiththefollowingfindingspursuanttoRMCsection4-3-050C.2.d:I.TheactivityisnotprohibitedbythisoranyotherprovisionoftheRentonMunicipalCodeorStateorFederallaworregulation;ii.TheactivitywillbeconductedusingbestmanagementpracticesasspecifiedbyindustrystandardsorapplicableFederalagenciesorscientificprinciples;iii.Impactsareminimizedand,whereapplicable,disturbedareasareimmediatelyrestored;iv.Wherewaterbodyorbufferdisturbancehasoccurredinaccordancewithanexemptionduringconstructionorotheractivities,revegetationwithnativevegetationshallberequired;V.Ifahazardousmaterial,activity,and/orfacilitythatisexemptpursuanttothisSectionhasasignificantorsubstantialpotentialtodegradegroundwaterquality,thentheAdministratormayrequirecompliancewiththeWellheadProtectionArearequirementsofthisSectionotherwiserelevanttothathazardousmaterial,activity,and/orfacility.Suchdeterminationswillbebaseduponsiteand/orchemical-specificdata.DECISION:AnexemptionfromtheCriticalAreasRegulationsisherebyApprovedwithConditions*.CONDITIONS:I.TheapplicantshallfollowtherecommendationsprovidedintheGeotechnicalEvaluation(datedFebruary19,2018),preparedbyGeoEngineers.2.Ifanytreetrimminginexcessoffortypercent(40%)ofthetreecanopybecomesnecessarywithincriticalareasorbuffers,thattheapplicantshallnotifytheCurrentPlanningProjectmanagerinwritingpriortotreetrimmingactivities.SIGNATURE&DATEOFDECISION:Jø€A&A%IMayII,2018JenniferHenning,PlanningDirectorDateTheabovelandusedecisionwillbecomefinalifthedecisionisnotappealedwithintheI4-dayappealperiod(RCW43.21.C.075(3);WAC197-11-680).Page4of5
City of Renton Department of Community & Economic Development Certificate of Exemption from Critical Areas Regulations
Talbot Paccar Transmission Line Reconductor LUA18-000334
APPEALS: An appeal of this administrative land use decision must be filed in writing together with the
required fee to the City of Renton Hearing Examiner, City of Renton, 1055 South Grady Way, Renton, WA 98057,
on or before 5:00 p.m., on May 25, 2018. RMC 4-8-110 governs appeals to the Hearing Examiner and additional
information regarding the appeal process may be obtained from the Renton City Clerk's Office, (425) 430-6510.
RECONSIDERATION: Within 14 days of the decision date, any party may request that the decision be reopened by the
approval body. The approval body may modify his decision if material evidence not readily discoverable prior to the original
decision is found or if he finds there was misrepresentation of fact. After review of the reconsideration request, if the approval
body finds sufficient evidence to amend the original decision, there will be no further extension of the appeal period. Any
person wishing to take further action must file a formal appeal within the 14-day appeal time frame.
EXPIRATION: Five (5) years from the date of decision (date signed).
Attachments:Site Plan, Stream Study, Wetland and Stream Evaluation, Geotech Report
Page 5 of 5
!
!
!
!
!
!
!
!
!
!!!
!
!!!
!!
!
!
!!!
!
!
!
!
!
!!!
0/13
0/14
0/15
0/16
0/17
1/1
1/2
1/3
1/4
1/5 1/6 1/7
1/8
1/9
1/10 1/11
1/12 1/13
1/14
1/15
1/16 1/17
1/18
1/19
1/20
1/21
2/1 2/2
2/3 2/4 2/5
S 2nd St
MainAveSF
a
ctory
Pl
N
N 3rd St
S 3rd St Bronson Way SBronsonWayNNE3rdSt
S Grady WayMa
p
l
e
V
a
l
l
e
y
H
w
yParkAveNSunsetBlvdN
I-405 FWYHouserWayN Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,AeroGRID, IGN, and the GIS User Community
Index Map
Puget Sound EnergyTalbot-PACCAR 115 kV Re-conductorRenton, Washington
Figure 2
µ500 0 500
Feet
!Replacement Pole
!Reframe Pole
115kV Re-conductor Alignment
Notes:1. The locations of all features shown are approximate.2. This drawing is for information purposes. It is intended toassist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and contentof electronic files. The master file is stored by GeoEngineers,Inc. and will serve as the official record of this communication.
Projection: NAD 1983 StatePlane Washington North FIPS 4601 Feet
Data Source: Geology from King County. Basemap from Mapbox Open Street Map, 2017 Contours from City of Renton
Stream Study
Talbot-Paccar 115-kV Re-Conductor
Pole Replacement
Renton, Washington
for
Puget Sound Energy
February 9, 2018
Focused Stream and Wetland Evaluation
Talbot-Paccar 115-kV Re-Conductor
Pole Replacement
Renton, Washington
for
Puget Sound Energy
February 9, 2018