HomeMy WebLinkAboutC_On-Hold_Letter_180518.pdf
May 18, 2018
Andrey Kovak
First Ukrainian Pentecostal Church
3811 NE 21st St
Renton, WA 98056
SUBJECT: "On Hold" Notice
PR17-000160 First Ukrainian Pentecostal Church Expansion, LUA18-000253
Dear Mr. Kovak,
The Planning Division of the City of Renton accepted the above master application for review on
April 30, 2018. During our review, staff has determined that additional information is n ecessary
in order to proceed further.
The following information will need to be submitted before August 15, 2018 so that we may
continue the review of the above subject application:
A revised TIR that provides all the Core Requirements and all special requirements of the
2017 Renton Surface Water Design Manual (RSWDM) should be provided. If the
stormwater analysis based on the 2017 RSWDM requires a stormwater facility, then the
development is required to provide it. Provide the map and corresponding table of PGIS,
PGPS, total impervious surface, non-PGIS, non-PGPS, permeable pavement, etc., for both
the existing scenario and for the developed scenario. Please include both frontage and
on site information as one combined project. The values of the PGIS and PGPS should be
provided as well. Information should be provided that proves if the water quality facility
exemption criteria is met. If the water quality exemption criteria is not met, Enhanced
Basic water quality is applicable.
The measured infiltration rate of the soil at the location of the proposed permeable
pavement should be provided. Only if the infiltration rate meets the requirements of the
2017 RSWDM should permeable pavement be considered for the site.
The applicant should submit a street modification request to provide a new curb flush
with the existing curb located in front of the adjacent east parcel. The 0.5-foot wide curb,
8-foot wide landscaped planter between curb and sidewalk, and 5-foot wide sidewalk
should be provided.
A minimum of two (2) additional fire hydrants are required within the site, in addition to
the fire hydrant at the end of the water main.
The proposed parking exceeds the maximum number of parking spaces permit per RMC
4-4-080. The applicant should submit a parking modification request to exceed the
maximum number of parking spaces.
The following is a recommended correction for land use review (which will be a required
correction at the time of construction permit review):
o Either extend the water main (8–inch diameter) by approximately 70 feet in length
to provide a Fire Port Connection (FPC) within 50 feet of the hydrant; OR propose
an alternate layout with the Double-Detector Check Valve Assembly (DDCVA) in
the landscape planter outside the building, which must be located within 50 feet
of the fire hydrant.
At this time, your project has been placed “on hold” pending receipt of the requested information.
Please contact me at (425) 430-7312 if you have any questions.
Sincerely,
Angelea Weihs
Associate Planner
cc: Ivan Feltsan/ Applicant
First Ukrainian Pentecostal Church/Owner
Oscar Gestoso / Contact