AMENDMENT NO. 2 TO AGREEMENT FOR REPLACEMENT OF
HIGHLANDS 435 PRESSURE ZONE RESERVOIRS AND MAINS -
FINAL DESIGN AND BIDDING CAG-16-103
THIS AMENDMENT, dated June 30, 2018, is by and between the City of Renton (the "City"), a
Washington municipal corporation, and RH2 Engineering, Inc. ("Consultant"), a Washington
corporation. The City and the Consultant are referred to collectively in this Amendment as the
"Parties." Once fully executed by the Parties, this Amendment is effective as of the last date
signed by both parties.
Whereas,the City engaged the services of the Consultant under Agreement CAG-16-103, dated
June 8, 2016,to provide necessary services for the Replacement of Highlands 435 Pressure Zone
Reservoirs and Mains—Final Design and Bidding(referred to herein as the "Agreement");
Whereas,the Parties wish to amend the Agreement to change the time for performance in order
to allow for additional time to complete remaining engineering design tasks.
NOW THEREFORE, It is mutually agreed upon that CAG-16-103 is amended as follows:
1. Time of Performance:Section V,Time of Beginning and Completion,is amended pursuant
to the schedule(s) set forth in Exhibit B-2. All Work shall be performed by no later than
June 30, 2019.
2. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
ORICiNAL,_1__PAGE.NO A. F PAGP a
IN WITNESS WHEREOF, the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON CONSULTANT
B f'`!/�t f`/� B
By: �' y:
regg AZ erman Tony ,P,P di
Public Works Administrator President
1
24/ 6//a0P14
Date Date
Approved as to Legal Form
Shane Moloney
Renton City Attorney
Contract Template Updated 12/29/2017
PAGE 20F2
ORIGINAL I___PAGE NO 3 OF 3 PAGES
Exhibit B-2: Time Schedule of Completion
City of Renton
Highlands 435 Pressure Zone Reservoir Improvements
Phase 1 --- 6.3 MG Reservoir and Transmission Main
Final Design and Bidding
Anticipated
Task Completion
GENERAL PROJECT TASKS
Task 1 —Project Management Throughout Contract
Duration
Task 2A and 2B—Permitting Assistance December 31,2018
Task 3A and 3B—Services During Bidding March 31,2019
Task 4—Additional Design and Permitting Services Not Applicable
SCHEDULE A--Highlands 435 Reservoir and Street Frontage Improvements
Task Al —Reservoir 60-percent Design Completed
Task A2—Reservoir 90-percent Design October 31, 2018
Task A3—Public Meeting Assistance Completed
Task A4—Finalize Reservoir Design January 31,2019
SCHEDULE B and C—Off-site Water Main and Utility Improvements
Task B1 -Topographic Survey and Geotechnical Investigation Completed
Task B2-Off-site Water Main and Utility Preliminary Design Completed
Task B3 - Off-site Water Main and Utility Final Design December 31,2018
CONTRACT COMPLETION DATE: June 30,2019