HomeMy WebLinkAboutAdden 1CAG-18-026, Adden #1-18
AMENDMENT NO. 1 TO AGREEMENT FOR THE PRV STATION
REHABILITATION AND REPLACEMENT STUDY CAG-18-026
THIS AMENDMENT, dated October 30, 2018, is by and between the City of Renton (the "City"),
a Washington municipal corporation, and RH2 Engineering, Inc. ("Consultant"), a Washington
corporation. The City and the Consultant are referred to collectively in this Amendment as the
"Parties." Once fully executed by the Parties, this Amendment is effective as of the last date
signed by both parties.
Whereas, the City engaged the services of the Consultant under Agreement CAG-18-026, dated
February 14, 2018, to provide necessary services for the PRV Station Rehabilitation and
Replacement Study (referred to herein as the "Agreement");
Whereas, the Parties wish to amend the Agreement to change the time for performance in
order to allow for additional time to complete remaining engineering design tasks.
NOW THEREFORE, It is mutually agreed upon that CAG-18-026 is amended as follows:
1. Time of Performance: Section V, Time of Beginning and Completion, is amended
pursuant to the schedule(s) set forth in Exhibit B-1. All Work shall be performed by no
later than February 28, 2019.
2. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
IN WITNESS WHEREOF, the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON
By hN
--
Gregg A14mAerman
Public Works Administrator
Date
Approved as to Legal Form
'440� a C
Shane Moloney
Renton City Attorney
Contract Template Updated 12/29/2017
PAGE 2 OF 2
CONSULTANT
/V
By:
ToP di
Prny dent
Date 41
Exhibit B-1: Time Schedule of Completion
City of Renton
PRV Station Rehabilitation/Replacement Assessment
ANTICIPATED NOTICE TO PROCEED DATE: February 2018
Task
Anticipated
Completion
Task 1— Data Collection and Site Visits
April 2018
Task 2 — Hydraulic Analysis
December 2018
Task 3 — Standards, Recommendations, and Report
February 2019
ANTICIPATED CONTRACT COMPLETION DATE: February 2019
10/17/2018 11:49:00 PM J:\Data\REN\118-033\00 Contract\PSA_EXHIBIT B_Completion Schedule_PRV Study 20181016.doa