• The state's Office of Financial Management has released official population totals.
Renton's population is now 104,100, an increase of 1,400 from 2017. Renton ranks
as the state's eighth largest city and the fourth largest city in King County.
• The U.S. Environmental Protection Agency is planning to test one of several cleanup
options at the Quendall site around July 20th. The agency will test the Self -
Sustaining Treatment for Active Remediation, or STAR, technology. STAR uses an
underground thermal process that burns creosote contamination out of the soil.
The test will determine the effectiveness of the STAR option prior to the release of
the proposed cleanup plan for public review and comment. The EPA has told city
staff that they have informed property owners around the Quendall site about the
test. Questions about the test can directed to Kathryn Cerise of the EPA at 206-553-
2589.
• Information about preventative street maintenance, traffic impact projects, and
road closures happening this week can be found at
http://rentonwa.gov/trafficimpacts. Preventative street maintenance, traffic impact
projects, and road closures will be at the following locations:
✓ Monday, July 16th through Friday, July 20th, 8:30 a.m. to 4:45 p.m. North 4th
Street will be reduced to two lanes between Garden Avenue North and Park
Avenue North due to the construction of curbs and gutters for the new Sartori
Elementary School. In addition, one to two eastbound lanes of North 3rd Street
between North Park and North Garden Avenues will be closed for construction
of curbs and gutters for Sartori Elementary. Questions may be directed to
Patrick DeCaro at 425-207-6013.
✓ Monday, July 16th through Friday, July 20th, 7:00 a.m. to 5:00 p.m. The
intersection of East Valley Road and SW 19th Street will be closed for the 1-405
Direct Connector Project. One lane of East Valley Road will remain open with
Ed Prince, Council President
Members of Renton City Council
Page 2 of 3
July 16, 2018
flaggers directing traffic through the work site. Questions may be directed to
Justin Johnson at 425-430-7291.
✓ Monday, July 16th through Friday, July 20th, 9:00 a.m. to 3:00 p.m. Single lane
closure along northbound Talbot Road South between the northbound 1-405 on -
ramp and the southbound 1-405 off -ramp for the 1-405 Direct Connector Project.
Questions may be directed to Justin Johnson at 425-430-7291.
✓ Monday, July 16th through Friday, July 20th, 8:00 a.m. to 3:00 p.m. Single lane
closure along the Talbot Road South ramp to northbound 1-405 for the 1-405
Direct Connector Project. Questions may be directed to Justin Johnson at 425-
430-7291.
✓ Monday, July 16th through Friday, July 20th, 9:00 a.m. to 2:30 p.m. Expect
intermittent lane closures and traffic delays along Talbot Road South (SR 515)
related to the 1-405/SR 167 Interchange Direct Connector Project.
In addition, northbound and southbound nighttime lane restrictions and closures
along SR 167 and 1-405 are also scheduled this week related to the project. The
information outlines specific dates and times of the closure. Questions may be
directed to Craig Smiley, WSDOT 1-405/SR 167 Corridor Communications, at 425-
456-8624 or visit the project website at
http://www.wsdot.wa.gov/Pro*ects/1405/SR1671CDirectConnector.
✓ Monday, July 16th through Friday, July 20th, 7:00 a.m. to 3:30 p.m. Additional
truck traffic and hauling will occur in the vicinity of Valley Medical Hospital
related to the construction of the new Medical Office Building. Questions may
be directed to Tom Main at 206-999-1833.
✓ Monday, July 16th through Friday, July 20th, 9:00 a.m. to 3:00 p.m. Additional
truck traffic and hauling will occur in the northbound lanes of 108th Avenue SE
just south of SE Petrovitsky Road due to site construction. Questions may be
directed to Tom Main at 206-999-1833.
✓ Monday, July 16th through Friday, July 20th, 9:00 a.m. to 3:00 p.m. Potential
single lane closure at the 1200 block of Lake Washington Boulevard due to utility
construction. Questions may be directed to Brad Stocco at 206-282-2373.
✓ Monday, July 16th through Tuesday, July 24th. The lower west entrance to
Renton City Hall from eastbound South Grady Way will be completely closed.
The eastbound curb lane along Grady Avenue South will also be closed between
8:30 a.m. and 4:30 p.m. between Williams Avenue South and Renton City Hall.
Street maintenance crews will be removing and reinstalling damaged curb and
Ed Prince, Council President
Members of Renton City Council
Page 3 of 3
July 16, 2018
gutter located at the entrance to City Hall. City Hall may be accessed using the
entrance at Williams Avenue South (previously shared with Sam's Club) or the
upper parking lot (lobby level) entrance located off of Benson Road South.
Questions may be directed to Street Maintenance Supervisor John Kalmbach at
425-766-6183.
✓ Tuesday, July 17th through Thursday, August 2nd, 7:00 a.m. to 4:30 p.m. The
southbound curb lane along Oakesdale Avenue SW between SW 16th Street and
SW 27th Street will be closed weekly Tuesday through Thursday. Street
maintenance crews will be conducting asphalt repairs. Questions may be
directed to Street Maintenance Supervisor John Kalmbach at 425-766-6183.
✓ Monday, July 16th through Friday, August 24th. North 27th Place will be closed
for the construction of the North 27th Place Bridge Scour Repair Project.
Questions may be directed to Derek Akesson at 425-430-7337 or via email at
dakesson@rentonwa.gov. For more information about this project, visit the
project website at www.rentonwa.gov/N27thBridgeScourRepair.
✓ Monday, July 16th through Monday, October 22nd. NE 31st Street will be
closed for the construction of the N E 31st Street Bridge Replacement Project.
Questions may be directed to Derek Akesson at 425-430-7337 or via email at
dakesson@rentonwa.gov. For more information about this project, visit the
project website at www.rentonwa.gov/NE31stBridgeReplace.
✓ Monday, July 16th through December 2018. Road closure on South 14th Street
between Smithers Avenue South and Davis Avenue South for utility construction.
Questions may be directed to Patrick DeCaro at 425-207-6013.
✓ Monday, July 16th through October 2019. The Renton Hill Utility Replacement
Project is underway with anticipated completion in May 2019. Following
completion of the utility project, an overlay of the affected surface streets will be
conducted as part of the 2019 overlay project. The overlay is scheduled to be
completed prior to October 31, 2019.