HomeMy WebLinkAboutMFP18003380DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Franchise Permit: MFP18003380
IVR Number: 18003380
Permit Informaon
Permit Name:Puget Sound Energy Gas Permits
Address/Locaon :06/21/2018Application Date:3223059230Parcel Number:18223 114TH AVE SE
Permit Type:07/10/2018Issue Date:Franchise
Permit Work Class:07/10/2019Expiration Date:Minor Utility
Job Number:106340937Franchise Type:Natural Gas
Description:Install new long side 1 1/8" PE gas service to '18223' asphalt cut anticipated. Restoration per City of Renton
standards.
Contacts
Name Address PhoneTypeBilling
ANISH KUMAR
PUGET SOUND ENERGY - GAS -
6905 S 228th St
Kent, WA 98032
B: (253) 208-2183Applicant
Stuart Bennett
Infrasource Services LLC
14103 Stewart Rd
Sumner, WA 98490
B: (303) 419-8755
H: (425) 677-5197
C: (713) 985-6489
Contractor
Business License Number: BL.036742Construction Contractor: INFRASL871C2
CITY OF RENTON ROW 1055 S Grady Way
Renton, WA 98057-3232
Owner
ANISH KUMAR
PUGET SOUND ENERGY - GAS -
6905 S 228th St
Kent, WA 98032
B: (253) 208-2183Specialized
Billing
X
General Condions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
This permit and plans must be posted at the job site at all times.
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Call (425) 430-7203 or go to: www.MyBuildingPermit.com one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
(Date)(Signature)
Page 1 of 1THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 | Published: 3/30/2017
Planning Division | 1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200
Email: franchisepermits@rentonwa.gov Website: rentonwa.gov
FRANCHISE PERMIT APPLICATION
Published: 3/30/2017
TO THE APPLICANT: Submit an electronic copy of the plans with the Franchise Permit Application and the
Traffic Control Application to franchisepermits@rentonwa.gov. Permit cost is $360.50. Inspection fee for
trenching more than 60 lineal feet or installation of 6 or more poles will be billed at $60.00 per hour.
Franchise Agency:
Franchise Job Number: Phone:
Contact Name: Email:
Job Site Address: Project Name:
Description of Work:
Please check all that apply:
☐ New Construction ☐ Repair/Relocate ☐ Underground ☐ Overhead ☐ Sidewalk ☐ Street
☐ Open Trench ☐ Bore # of feet:
Contractor Name: Phone:
State Contractors License #: City of Renton Business License #:
“I certify that I am the owner or applicant’s authorized agent and do hereby agree to abide to the terms and conditions set forth under this permit and shall comply with the City of Renton’s Trench Restoration and Street Overlay Requirements. ”
Signature Date
INSPECTIONS SHALL BE REQUESTED 24 HOURS PRIOR TO COMMENCEMENT OF ALL WORK BY CALLING THE
INSPECTION LINE AT 425-430-7203 OR BY GOING TO MYBUILDINGPERMIT.COM
Jobs are required to be called in for job start, re-inspection and project final. Re-inspection fees are billed at $75/hour.
All Pre-Construction meetings shall be scheduled at a maximum of 14 days prior to the job start date.
Plan Review/Development Engineering Date Approved as submitted
Pre-Construction Meeting required
Site Construction Inspector Date Approved with comments or redlines
Camera inspection of utilities required
Development Engineering Manager Date
Puget Sound Energy
106340937
Anish Kumar
253-208-2183
anish.kumar@pse.com
18223 114th Ave SE 98055 106340937
Occupying 114th Ave SE for crew to install new long side 1 1/8" PE gas service
to '18223'. 1 3'x5' asphalt cut anticipated. Restoration per City of Renton standards.
18'
PSE/Infrasource 253-208-2183
INFRASL871C2 BL.036742
6/21/2018
MFP18003380
Scott Warlick 6/22/2018
Holly Powers 7/10/2018
CITY OF RENTON
TRAFFIC CONTROL PLAN
PROJECT NAME: PERMIT#
CONSTRUCTION COMPANY: PHONE#:
CONTACT NAME: PHONE#:
ADDRESS: CELL#:
E-MAIL ADDRESS: FAX#:
PROJECT LOCATION: N/E/S/W OF:
WORK TIME: APPROVED BY:
WORK DATE: APPROVAL DATE:
OFFICE COPY T-
CONTRACTOR
DEV. SERVICE, INSPECTION P. MILLER
DEV. SERVICE, PLAN REVIEW B. BANNWARTH
POLICE CHARLES KARLEWICZ
FIRE FIRE MARSHALL FS #13
Permit Holder agrees to all the following:
• Comply with all traffic regulations of the City of Renton and the State of Washington.
• Prepare a traffic control plan and obtain City approval of that plan. That plan shall be implemented for
all street and lane closures, and the plan shall be performed in compliance with the Manual on
Uniform Traffic Control Devices.
• Notify emergency services (253-852-2121) twenty-four (24) hours before any street or lane closures.
• Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of R.C.W. 47.36.200
through 47.36.220, 9A.36.050 Reckless Endangerment, and other applicable State and City codes.
• Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments,
including all costs of defense and attorney’s fees incurred in defending against same, arising from and
related to implementation of the approved traffic control plans including claims arising from towing of
private vehicles and the acts of the Permit Holder’s agents and employees.
• The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or
judgment, and in such event shall indemnify and hold harmless the City for any such claims paid,
including the City’s reasonable attorney’s fees and litigation costs incurred resulting from such claim.
• In the event any claim or suit is brought against City within the scope of this Agreement, Permit Holder
will pay for legal counsel chosen by the City to defend against same.
• Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address
traffic or pedestrian safety or travel.
• By my signature herein, I acknowledge all the above requirements.
PRINT NAME: DATE:
SIGNATURE:
Reset FormPrint Form
106340937
PSE/Infrasource
Jordan Cossette 253-395-6848
6905 S 228th St, Kent 98032
jordan.cossette@pse.com
18223 114th Ave SE
TBD
8/3/2018
Anish Kumar 6/21/2018
MFP18003380
Scott Warlick
7/10/2018Monday - Friday
8:00AM - 3:30PM
SKETCH
I
-- NORTH --
I
NOTES:
• Work Zone Traffic Control shall be in accordance with the Manual on Uniform Traffic Control Devices (MUTCD)
and shown by sketch or reference to WSDOT.
• The plan must be submitted to the City’s PW/Transportation Division for review and/or approval at least three
working days prior to work.
• Approved Temporary Traffic Control Plan must be at the work site during work hours.
• Contractor or entity must call Renton School District (425-204-4455) or any public/private agency to be affected
by a temporary lane or road closure.
• Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded.
• Total road closure lasting more than 24 hours is subject to the approval by the City Council.
• Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
• Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations for
vacate parking or curb lane usage.
• Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
72 hours in advance of effective date and time.
• The cover sheet of this Traffic Control Plan form must be attached to each Temporary No Parking Sign on the
project site.
• Temporary traffic control devices must be removed immediately when work is done or no construction activities
are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance shop
(3555 NE 2nd Street).
#18223 182nd St114th Ave FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKINGFROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKING10101515SHOULDERWORKW21-5UTILITYWORKAHEADUT-WK-AHD100'100'UTILITY
WORK
AHEAD UT-WK-AHD100'UTILITYWORKAHEADUT-WK-AHD100'CHANNELIZATIONDEVICE SPACINGMPH55/7035/4525/30TAPER403020TANGENT806040PSEPUGETSOUNDENERGYJOB#10634093718223 114th Ave SE Renton, 98055June 13 2018jaber.tofan@pse.com(425)424-6425SHEET 1 of 1Puget Sound EnergyTraffic Control Supervisor:Gregory HarwoodCard No. 008997Card Exp. 08/13/2019gregory.harwood@pse.com(425)424-6425NWORK PITLEGEND28" TRAFFIC CONESIGN LOCATIONTRAFFIC FLOWWORK VEHICLE/FLASHING LIGHTSRIGHT OF WAYNotes:1. All signs and spacing to conform to theMUTCD and City of Renton standards.2. All sidewalks, driveways, exits and egressesshall be completely clear unless otherwise indicated.3. Channelizing devices are 28" traffic cones.Use traffic drums (barrels) with steady burningType C lights on all State State Routes and Hwys.4. Sign size can be a minimum of 36" x 36" andshall not obstruct pedestrian access.5. Crew is required to leave a minimum of 11' fortraveling lane width.6. Alert affected residents and businesses.7. Work to take place between 9 a.m. and 4 p.munless otherwise specified. All work for arterialsand major roadways will be from 9 a.m. to 3 p.m.8. Work area will be Work area will be 15' ECL of114th Ave SE & 187' SCL of SE 182nd ST.MFP18003380
Est. Start Date:
&
&
&
Puget Sound Energy Gas Pre-Inspect Form
Job #:106340937
Date:6/12/18 Address:
8/3/18 PM / Inspector:JORDAN COSSETTE 253.395.6848
18223 114TH AVE SE
RENTON, 98055
425.246.0180
Est. Duration:1 Day
Jurisdiction:RENTON City / Zip:
ROW Permit:Yes Customer:NIGEL BEAN
All Scat / Trenchless
PLAT Map:214.083
N
Work Location Surface Type
Job Description / Scope of Work
New Construction:
No
Construction Method
SCAT 18' STUB 1 1/8" PE, SCAT 115' EXT 1 1/8" PE, 2600 EFV, A425 MSA MAIN 74E164
Abandoned 6" AC H2O line in close proximity to main. Has been hit before, dig with caution!
Size of Cut
of CL SE 182ND ST ASPHALT
of CL
15'EAST of CL 114TH AVE SE 187'South 3X5
of CL
Service Information Street Information
of CL
of CL
Job Type
EFV:1-1/8" - 2600 - 9996743 Police #:TCP:Yes
Diameter:1-1/8" PE Flaggers #:Arterial:No
NO Mtr Hoods #:
Meter:A425 Speed Limit:
Route #'s:Bollards:2.5" #4" #ADA Ramps #:
Del Press:6" W.C.Traffic Signal:NO Bus Stop:NO
25 No Parks #:
Meter Loc:
New Residential Svc
Trolley Lines: DIRT / GRAVEL GRASS
A2
A425 MSA
WORK ZONE 1 1/4" PE-A IP MAIN 15' E 74E164 18223
18223
P/L
Abandoned 6" AC
H2O Line in Close
Proximity.
Has been hit before,
dig with caution!
SE 182ND ST 114TH AVE SE Caution:
Underground gas
oil tank
MFP18003380