HomeMy WebLinkAboutMFP17002269DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Franchise Permit: MFP17002269
IVR Number: 17002269
Permit Informa!on
Permit Name:Puget Sound Energy - Electric
Address/Loca!on:05/17/2017Applica!on Date:0739000105Parcel Number:12601 SE PETROVITSKY RD
Permit Type :09/07/2017Issue Date:Franchise
Permit Work Class:09/07/2018Expira!on Date :Minor U*lity
Job Number:#186048141Franchise Type :Electric
Descrip!on:Replace Pole P 01 with taller pole to raise lines . New span guy wires to be installed from P 01 to P02 across
Petrovitsky. New down guy wire to be installed off of P02. Tree trimming by Asplundh to be required prior to pole
replacement. OVERHEAD APPROVED 8/29/2017
Contacts
Name Address PhoneTypeBilling
ANISH KUMAR
PUGET SOUND ENERGY - ELECTRIC - BILLING
6905 S 228th St
Kent, WA 98032
B: (253) 208-2183ApplicantX
VICKI HENSON
POTELCO INC
8001 212th St S
Kent, WA 98032
B: (253) 863-0484Contractor
Business License Number: BL.005109Electrical Contractor : POTELI*344O4
Construc!on Contractor : POTELI*227PL
CITY OF RENTON ROW 1055 S Grady Way
Renton, WA 98057-3232
Owner
General Condi!ons & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
This permit and plans must be posted at the job site at all times.
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Call (425) 430-7203 or go to: www.MyBuildingPermit.com one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575)(Puget Sound Energy at 425.457.5816) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
(Date)(Signature)
Page 1 of 2THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 | Published: 3/30/2017
Planning Division | 1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200
Email: franchisepermits@rentonwa.gov Website: rentonwa.gov
FRANCHISE PERMIT APPLICATION
Published: 3/30/2017
TO THE APPLICANT: Submit an electronic copy of the plans with the Franchise Permit Application and the
Traffic Control Application to franchisepermits@rentonwa.gov. Permit cost is $360.50. Inspection fee for
trenching more than 60 lineal feet or installation of 6 or more poles will be billed at $60.00 per hour.
Franchise Agency:
Franchise Job Number: Phone:
Contact Name: Email:
Job Site Address: Project Name:
Description of Work:
Please check all that apply:
☐ New Construction ☐ Repair/Relocate ☐ Underground ☐ Overhead ☐ Sidewalk ☐ Street
☐ Open Trench ☐ Bore # of feet:
Contractor Name: Phone:
State Contractors License #: City of Renton Business License #:
“I certify that I am the owner or applicant’s authorized agent and do hereby agree to abide to the terms and conditions set forth under this permit and shall comply with the City of Renton’s Trench Restoration and Street Overlay Requirements. ”
Signature Date
INSPECTIONS SHALL BE REQUESTED 24 HOURS PRIOR TO COMMENCEMENT OF ALL WORK BY CALLING THE
INSPECTION LINE AT 425-430-7203 OR BY GOING TO MYBUILDINGPERMIT.COM
Jobs are required to be called in for job start, re-inspection and project final. Re-inspection fees are billed at $75/hour.
All Pre-Construction meetings shall be scheduled at a maximum of 14 days prior to the job start date.
Plan Review/Development Engineering Date Approved as submitted
Pre-Construction Meeting required
Site Construction Inspector Date Approved with comments or redlines
Camera inspection of utilities required
Development Engineering Manager Date
MFP17002269
Justin Johnson 9-7-2017
Holly Powers 9/7/2017
CITY OF RENTON
TRAFFIC CONTROL PLAN
PROJECT NAME: PERMIT#
CONSTRUCTION COMPANY: PHONE#:
CONTACT NAME: PHONE#:
ADDRESS: CELL#:
E-MAIL ADDRESS: FAX#:
PROJECT LOCATION: N/E/S/W OF:
WORK TIME: APPROVED BY:
WORK DATE: APPROVAL DATE:
OFFICE COPY T-
CONTRACTOR
DEV. SERVICE, INSPECTION P. MILLER
DEV. SERVICE, PLAN REVIEW B. BANNWARTH
POLICE CHARLES KARLEWICZ
FIRE FIRE MARSHALL FS #13
Permit Holder agrees to all the following:
• Comply with all traffic regulations of the City of Renton and the State of Washington.
• Prepare a traffic control plan and obtain City approval of that plan. That plan shall be implemented for
all street and lane closures, and the plan shall be performed in compliance with the Manual on
Uniform Traffic Control Devices.
• Notify emergency services (253-852-2121) twenty-four (24) hours before any street or lane closures.
• Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of R.C.W. 47.36.200
through 47.36.220, 9A.36.050 Reckless Endangerment, and other applicable State and City codes.
• Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments,
including all costs of defense and attorney’s fees incurred in defending against same, arising from and
related to implementation of the approved traffic control plans including claims arising from towing of
private vehicles and the acts of the Permit Holder’s agents and employees.
• The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or
judgment, and in such event shall indemnify and hold harmless the City for any such claims paid,
including the City’s reasonable attorney’s fees and litigation costs incurred resulting from such claim.
• In the event any claim or suit is brought against City within the scope of this Agreement, Permit Holder
will pay for legal counsel chosen by the City to defend against same.
• Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address
traffic or pedestrian safety or travel.
• By my signature herein, I acknowledge all the above requirements.
PRINT NAME: DATE:
SIGNATURE:
Reset FormPrint Form
Justin Johnson
SKETCH
I
-- NORTH --
I
NOTES:
• Work Zone Traffic Control shall be in accordance with the Manual on Uniform Traffic Control Devices (MUTCD)
and shown by sketch or reference to WSDOT.
• The plan must be submitted to the City’s PW/Transportation Division for review and/or approval at least three
working days prior to work.
• Approved Temporary Traffic Control Plan must be at the work site during work hours.
• Contractor or entity must call Renton School District (425-204-4455) or any public/private agency to be affected
by a temporary lane or road closure.
• Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded.
• Total road closure lasting more than 24 hours is subject to the approval by the City Council.
• Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
• Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations for
vacate parking or curb lane usage.
• Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
72 hours in advance of effective date and time.
• The cover sheet of this Traffic Control Plan form must be attached to each Temporary No Parking Sign on the
project site.
• Temporary traffic control devices must be removed immediately when work is done or no construction activities
are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance shop
(3555 NE 2nd Street).
5/3/2017
Renton City Hall
1055 S. Grady Way
Renton, WA 98057
PSE WO# 186048141
To Whom It May Concern,
The scope of work relating to the permitting application for WO # 186048141 is to replace existing
legacy distribution pole with a newer and reliable pole. Per the City of Renton municipal code 4-6-090
Utility Lines- Underground Installation: D.1.g.i, this work shows exempt from the city’s underground
requirements as this is a rebuild of existing overhead electrical facilities.
Please contact me if you have any questions or need additional information.
Sincerely,
Sierra Vega
Project Manager
Ph: 253-234-6130
Em: Sierra.vega@pse.com
MFP17002269
DenisLawMayorCommunity&EconomicDevelopmentC.E.“Chip”VincentAdministratorAugust29,2017PugetSoundEnergyattn:AnishKumarPermitSpecialist,SouthwestKing16729126thAveSEBellevue,WA98009Viaemail:anish.kumar’pse.comSUBJECT:RequesttoReplacePSEPole,FranchiseJob#186048141,12601SEPetrovitskyRoadDearMr.Kumar:TheCityofRentonhasreviewedyourrequestinordertopermitPotelcotoreplaceone50-foothighutilitypole(P01)witha55-foothighpoleinordertoraisetheheightofthepowerlines.Newspanguywireswouldbeinstalledfromthenewpole,acrossSEPetrovitsky,toPoleP02.TherequestrequiresanexemptionfromRentonMunicipalCode(RMC)Section4-6-090.ANALYSIS:TheCityhasconsideredtherequestforanexemptionfromRMC4-6-090(D)(1)(g)iandii.Ordinance5834grantsPugetSoundEnergy,therighttoconstruct,operate,set,erect,support,attach,connectmaintain,repair,replace,enlargeandusefacilitiesforpurposesoftransmission,distributionandsaleofelectricalenergyandgas,in,upon,over,under,along,acrossandthroughthefranchisearea.Thereplacementoftheexisting50-foothighutilitypolewithatallerpole(55-foot)isproposedinordertoraisepowerlinesandprovideanewer,morereliablepole.Therefore,theCityisgrantinganexemptionwithconditions,perRMC4-6-090(D)(1)(g)iandiiwhichallowsforextensionsofexistingoverheadelectricalandcommunicationfacilitieswhentherearecontinuingrequirementsforpolesanditisnotlikelythattherewillbeundergroundingintheforeseeablefuture;and,whenthereareexistingoverheadelectricalorcommunicationfacilitiesthatwillnotberemovedandthefacilitiesthatwouldhavebeenrequiredtoberemovedareparalleltothefacilitiesthatwillnotberemoved.1055southGradyWay,Renton,WA980S7rentonwa.govMFP17002269
AnishKumarPage2of2August29,2017DECISION:Therequestedexemptionfromundergroundutilityinstallationrequirements(RMC4-6-090(C)asrequestedbytheapplicantisapprovedsubjecttotheconditionbelowastherequestcomplieswithexemptioncriteriaofRMC4-6-090(D)(1)(g)iandii.ConditionofApproval:1.Thetrafficcontrolplanrequiresseparateapproval.Thisdecisiontogranttheexemptionwithconditionsissubjecttoafourteen(14)dayappealperiodfromthedateofthisletterperRMC4-8-110.AnyappealsoftheadministrativedecisionmustbefiledwiththeCityClerk,alongwiththerequiredappealfee,by5:00pm,September12,2017.Aright-of-wayusepermitandapprovalofthetrafficcontrolplanarestillneededfromtheCity.PleasecoordinatewithHollyPowers.Shecanbereachedviaemailathpowersrentonwa.govorviaphoneat:425-430-7266.Sincerely,ctjrJenniferT.Henning,AICPPlanningDirectorcc:chipVincent,CEDAdministratorGreggZimmerman,wAdministratorCraigBurnell,BuildingOfficialBrianneBannwarth,DevelopmentEngineeringManagerJustinJohnson,EngineeringspecialistVanessaDolbee,currentPlanningManagerAmandaAskren,PlanningandTechnicalServicesManagerHollyPowers,DevelopmentServicesRepresentativePatMiller,ConstructionInspectionSupervisor1055SouthGradyWay,Renton,WA98057rentonwa.gov
MFP17002269
12601 SE Petrovitsky Rd, Renton, WA 98058
REQUESTED DATES:
WORK HOURS:
MHT#1Location: 12601 SE Petrovitsky Rd,
Renton, WA 98058
For: Potelco Inc.
Name: Sierra Vega 253-327-3162
Date: March 14, 2017
Drawn By: Tanja Duffy
TCS Cert#: 9523
Job#: 186048141
NOT DRAWN TO SCALE
SIGN SPACING
MPH
100'
(Seattle 150'
SeaTac 200')
"X"
45+
35
30
25
500'
350'
200'
Summary of Devices
4 - 48" Road Work Ahead
2 - 48" Right Lane
Closed Ahead
2 - 48" Transition Left
2 - Arrow Board
80 - Cones
NOTES:60 800'P
Message
UPO
Merging Devices
L
Shifting
1/2 L
Devices
10 feet
Merging Devices
L 1/2 L
11 feet
Shifting Devices Merging Devices
L 1/2 L
12 feet
Shifting Devices
1/3 L*
Shoulder Taper*
DevicesLength
Offset (W)
Speed (S)
(mph)
20
25
30
35
40
45
50
55
60
65
70
Buffer
Space
Max. Channelizing
Device Spacing
TangentTaper
70
105
150
205
270
450
500
550
600
650
700
5
6
8
8
10
16
14
15
16
17
19
35
55
75
105
135
225
250
275
300
325
350
3
4
5
5
6
9
8
8
9
9
10
75
115
165
225
295
495
550
605
660
715
770
5
7
9
9
11
18
15
16
18
19
20
40
60
85
115
150
250
275
305
330
370
385
3
4
5
5
6
9
8
9
9
10
11
80
125
180
245
320
540
600
660
720
780
840
5
7
10
9
12
19
16
18
19
21
22
45
65
90
125
160
270
300
330
360
390
420
3
4
5
5
6
10
9
9
10
11
12
25
35
50
70
90
150
170
185
200
220
3
3
3
4
4
6
6
6
6
7
7
115
155
200
250
305
360
425
495
570
645
730
20
20
20
30
30
30
40
40
40
40
40
40
40
40
60
60
60
80
80
80
80
80235
316555
166901
316562
166899
duffy@rainierasphalt.com
253-545-1321
ROAD
WORK
AHEAD
RIGHT LANE
CLOSED
AHEAD
ROAD
WORK
AHEAD
RIGHT LANE
CLOSED
AHEAD
ROAD
WORK
AHEADROADWORKAHEAD
350'350'
350'
350'
350'
350'225'
Merging
Taper
225'
Merging
Taper
TTC Shall Be Used For Tree Trimming Also
www.invarion.com
MFP17002269