HomeMy WebLinkAboutP_Utility Plan Renton Project_571014492_V1GENERAL NOTES
- ALL WORK IS TO BE COMPLETED PER PSE STANDARDS & PRACTICES. COPIES
OF ALL PSE STANDARDS ARE AVAILABLE UPON REQUEST.
- WORK SITES SHALL BE KEPT CLEAR OF DEBRIS AND ALL CONSTRUCTION
MATERIALS, EQUIPMENT AND PACKING SHALL BE REMOVED DAILY.
- RETURN ALL UNUSED AND REMOVED POLES, TRANSFORMERS AND HARDWARE
TO PSE STOREROOM. ALL COPPER SHALL BE COILED AND RETURNED THE DAY
IT IS REMOVED FROM THE POLES. REMOVE ALL UNUSED PINS AND INSULATORS.
RETURN ALL STREET LIGHTS, AREA LIGHTS AND FLOODLIGHTS TO PSE.
PRECONSTRUCTION
- NOTIFY APPROPRIATE CITY, COUNTY OR DOT AUTHORITIES 48 TO 72 HOURS,
OR AS REQUIRED BY PERMITTING AGENCY, IN ADVANCE OF STARTING WORK
IN RIGHT-OF-WAY INVOLVING A PERMIT.
- ALL DISTRIBUTION SYSTEM SWITCHING SHALL BE APPROVED BY SYSTEM
OPERATIONS A MINIMUM OF 48 HOURS IN ADVANCE. ALL TRANSMISSION SYSTEM
SWITCHING SHALL BE SCHEDULED WITH THE LOAD OFFICE A MINIMUM OF 5 DAYS
IN ADVANCE.
- NOTIFY CUSTOMERS OF ALL OUTAGES 48 HOURS IN ADVANCE.
- EROSION CONTROL PROCEDURES SHALL BE USED IN ACCORDANCE WITH
THE MINIMAL REQUIREMENTS SPECIFIED IN PSE STD 0150.3200
"TECHNIQUES FOR TEMPORARY EROSION AND SEDIMENT CONTROL".
- WORK SHALL NOT BEGIN UNTIL ALL EASEMENTS AND STREET USE PERMITS
HAVE BEEN SECURED. FINAL NOTIFICATION TO PROCEED SHALL BE GIVEN
BY THE PROJECT MANAGER.
WORK DRAWINGS AND DOCUMENTS
- MARK ALL FIELD CHANGES, EQUIPMENT ID NUMBERS AND UNDERGROUND CABLE
INFORMATION IN RED ON FOREMAN'S COPY OF WORKSKETCH.
- RETURN ONE FOREMAN'S COPY OF WORKSKETCH TO PROJECT MANAGER AT
COMPLETION OF JOB.
- WHEN PERMITS ARE REQUIRED, A COPY SHALL BE AVAILABLE ON WORK SITE
AT ALL TIMES.
SAFETY
- REFER TO PSE STANDARDS 6275.xxxx FOR SYSTEM GROUND REQUIREMENTS.
- PROPER LINE CLEARANCES SHALL BE TAKEN AT THE BEGINNING, AND
RELEASED AT THE END, OF EACH WORK DAY, OR AS OTHERWISE
INSTRUCTED BY THE SYSTEM OPERATOR.
- PROVIDE SIGNS, BARRICADES, AND TRAFFIC CONTROL IN CONFORMANCE
WITH PERMIT REGULATIONS AND LOCAL TRAFFIC REGULATIONS.
0
i
SANTA FE Lij
� W
7TH ST
--- ----- ---------
SHE T 2
LLJQ
GRA
TALBOT - METRO
RENTON 115kV
J '
ST
19
W_
m
O
J
167 =
O
m O UGET
O�
S 21 ST
N
ST
`SO
- -------------------
--------- -
-------- s -----------------
VICINITY MAP
ENGINEER: JOHN SEALY
PROJECT NOTES
PHONE: 425-516-4929
PROJECT SCOPE
- TEMPORARY GUYING TO PROVIDE CLEARANCE FOR NEW CONSTRUCTION
CONSTRUCTION NOTES
- ALL CONSTRUCTION SHALL BE IN ACCORDANCE WITH THE STANDARD NOTES
FOR WOOD POLES CONSTRUCTION, DWG D-12842 SH 1 OF 1.
- THE ENGINEER SHALL BE CONTACTED WITH REGARDS TO ALL TECHNICAL
INFORMATION. THE ENGINEER SHALL HAVE SOLE AUTHORITY TO APPROVE
ANY AND ALL CONSTRUCTION CHANGES.
- DESIGN DETAILS AND NOTES SHALL SUPPLEMENT THE STANDARDS
REFERENCED IN THIS DRAWING.
CALL (800)424-5555 2 BUSINESS DAYS BEFORE YOU DIG
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF FACILITIES
"Locates Required" Yes ❑ No❑
"Outages Required" Yes ❑ No❑
"Flagging Required" Yes ❑ No❑
TRANSMISSION
SYMBOL LEGEND
ABBREVIATION
KEY
O
EXISTING POLE
ANCH
ANCHOR
•
NEW POLE
BRKT
BRACKET
X
REMOVED POLE
CHG
CHANGE
CL
CLASS
❑
EXISTING LAMINATE POLE
C/N
COMMON NEUTRAL
NEW LAMINATE POLE
CU
COPPER
Q
EXISTING STEEL POLE
C/0
CUTOUT
NEW STEEL POLE
DE
DEADEND
DISC
DISCONNECT
EXISTING LATTICE TOWER
DBL
DOUBLE
X
NEW LATTICE TOWER
DA
DOUBLE ARM
—
EXISTING 55KV CONDUCTOR
DDE
DOUBLE DEADEND
—
EXISTING 115KV CONDUCTOR
DWN GUY
DOWN GUY
E
EAST
—
EXISTING 230KV CONDUCTOR
INST
INSTALL
NEW CONDUCTOR
LATL
LATERAL
-
REMOVED CONDUCTOR
LB
LOADBREAK
MT
MOUNT
DOWN GUY
NEUT
NEUTRAL
MULTIPLE DOWN GUYS
N
NORTH
--�E�
SPAN GUY
OH
OVERHEAD
PUSH BRACE
PH
PHASE
STREET LIGHT
PTP
POLE TOP PIN
PRI
PRIMARY
o
*-O
STREET LIGHT WITH POLE
RELOC
RELOCATE
D
LINE CROSSING (PROFILE)
REPL
REPLACE
s
REMV
REMOVE
R/C
RIGID CLEVIS
-
- SEE 0300.1000 FIGURE 5 FOR
SVC
SERVICE
DISTRIBUTION SYMBOL LEGEND
SGL
SINGLE
n
SA
SINGLE ARM
S
SOUTH
SWBD
SWITCH BOARDS
SW GRDS
SWITCH GROUNDS
SW#
SWITCH NUMBER
TAN
TANGENT
TEL/TV
TELEPHONE/TELEVISION
TERM
TERMINATION
X-FER
TRANSFER
XFMR
TRANSFORMER
o
XMSN
TRANSMISSION
TPLX
TRIPLEX
UG
UNDERGROUND
W
WEST
W/
WITH
VERT
VERTICAL
0
i
SANTA FE Lij
� W
7TH ST
--- ----- ---------
SHE T 2
LLJQ
GRA
TALBOT - METRO
RENTON 115kV
J '
ST
19
W_
m
O
J
167 =
O
m O UGET
O�
S 21 ST
N
ST
`SO
- -------------------
--------- -
-------- s -----------------
VICINITY MAP
ENGINEER: JOHN SEALY
PROJECT NOTES
PHONE: 425-516-4929
PROJECT SCOPE
- TEMPORARY GUYING TO PROVIDE CLEARANCE FOR NEW CONSTRUCTION
CONSTRUCTION NOTES
- ALL CONSTRUCTION SHALL BE IN ACCORDANCE WITH THE STANDARD NOTES
FOR WOOD POLES CONSTRUCTION, DWG D-12842 SH 1 OF 1.
- THE ENGINEER SHALL BE CONTACTED WITH REGARDS TO ALL TECHNICAL
INFORMATION. THE ENGINEER SHALL HAVE SOLE AUTHORITY TO APPROVE
ANY AND ALL CONSTRUCTION CHANGES.
- DESIGN DETAILS AND NOTES SHALL SUPPLEMENT THE STANDARDS
REFERENCED IN THIS DRAWING.
CALL (800)424-5555 2 BUSINESS DAYS BEFORE YOU DIG
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF FACILITIES
"Locates Required" Yes ❑ No❑
"Outages Required" Yes ❑ No❑
"Flagging Required" Yes ❑ No❑
C
Im.,
TRANSFER SPAN GUY TO NEW POLE 0/14 ON
THE TALBOT HILL — OBRIEN 02 LINE
3 ,619 L_—
SHUFFLETON—OBRIEN
S RENTON VILLAGE PL
TALBOT HILL—OBRIEN #2
D
r
OD
0
—I
i I �
0
X�� (n
PLAN SCALE
1 "= 100,
0 0 0 0 0
no Ln o
N
POLE TABLE
POLE
GUYS
ANCHORS
POLE
DRILLING
DIST.
OR
STAKE
STATION
ACTION
POLE
LENGTH
POLE
CLASS
SPECIFICATIONS
1025.1400
TYPE
STANDARD
PRACTICE
FRAMING
FROM
GRID NUMBER
REMARKS
ACCESS
NO
CONSTRUCTION
STD.PRAC.
6072.1000
REMARKS
NO
REVISION 16
OR
QTY
POLE TOP
6073.xxxx
FIG
ACTION
2/19
149+02
EXIST
60
1
FIG. 10
HPA
6085.1000
DESCRIPTION
317464-166021
2/20
'151 +44
EXIST
60
H2
FIG. 20
VDE-C
2152.9165
317438-166020
1
1
s2/20E
EXIST
35
1
INSTALL
STUB
3
7/16 SIDE DOWN 8' DOUBLE — GYT7S2
0100
6
INSTALL
2/21
154+89
EXIST
70
1
FIG. 10
1 HPA
16085.1000
3
317438-165993
0170
1
GUYING TABLE
CALL (800)424-5555 2 BUSINESS DAYS BEFORE YOU DIG
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF FACILITIES
"Locates Required" Yes ❑ No❑
"Outages Required" Yes ❑ No❑
"Flagging Required" Yes ❑ No❑
GUYS
ANCHORS
POLE
OR
STAKE
LEAD
CONSTRUCTION
STD.PRAC.
CONSTRUCTION
STD.PRAC.
6072.1000
REMARKS
NO
ACTION
OR
QTY
UNIT
6073.xxxx
FIG
ACTION
QTY
UNIT
SPAN
DESCRIPTION
DESCRIPTION
FIG
DET
2/20
INSTALL
20' E
3
7/16 SIDE DOWN 8' DOUBLE — GYT7S2
0100
6
INSTALL
2
PLATE 24 — 1 IN ROD — ANTP24
3
B
SET ANCHOR AS STAKED$ ANCHORS MUST BE PLACED 5' APART
2/20
REUSE
80' S
3
7/16 SIDE SPAN 8' — GYT30S
0170
1
TRANSFER SPAN GUY TO POLE 0/14 TALBOT HILL — OBRIEN #2
2/20
REMOVE
148' E
3
3/8 SIDE SPAN 8' — GYT30S
0170
1
EXIST
2/20
1 REMOVE
15'920' E
2
7/16 STUB DOWN — GYT7S8
0170
3
CALL (800)424-5555 2 BUSINESS DAYS BEFORE YOU DIG
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF FACILITIES
"Locates Required" Yes ❑ No❑
"Outages Required" Yes ❑ No❑
"Flagging Required" Yes ❑ No❑