CONTRACT: Falcon Ridge Lift Station Replacement CAG-18-120 C.O.# 1
CONTRACTOR: Road Construction Northwest, Inc.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Qty. Unit Price Total Price
025. NEW ITEM: LS 1 $2,964.00 $2,964.00
Additional cost and time to have the wet well interior coating applied prior to the
structure being delivered on site. This is a changed condition as requested by the City.
Sub Total
Sales Tax (10.0%)
Total
$2,964.00
$296.40
$3,260.40
ORIGINAL CONTRACT AMOUNT
CURRENT CONTRACT AMOUNT
ESTIMATED NET CHANGE
ESTIMATED CONTRACT
THIS ORDER
TOTAL AFTER CHANGE
$926,502.50
$926,502.50
$3,260.40
$929,762.90
ORIGINAL CONTRACT WORKING DAYS
CURRENT CONTRACT WORKING DAYS
ESTIMATED NET CHANGE WORKING
ESTIMATED CONTRACT
DAYS THIS ORDER
WORKING DAYS AFTER CHANGE
120
120 1
14
1 134
SIGNATi
Contrac
Project
Approvecj,.90
Shane Moloney, Renton City
Approved By:
Utility Systems
Approved By:
Gregg
Date: i! 19 1 $
Date: 0 Z c, 16
Date:C�
Date: _11�/Pig
H:\File Sys\WWP - Wastewater\WWP-27-03939 Falcon Ridge Lift Station Replacement\Pay Estimates\Change Order #1 CAG 18-
120.doc\MB
Road Construction Northwest, Inc.
PO Box 2228 Renton, Washington 98056 (425) 254-9999 (425) 254-1334 fax
November 5, 2018
To: City of Renton
1055 South Grady Way
Renton, WA 98057
ATTN.: Mr. Michael Benoit
Ms. Alex Fussell
RE: Falcon Ridge Lift Station Replacement and Force Main Improvements
SUBJ: Off -Site 96-inch Wetwell Interior Wasser Aeroshield Coating
Dear Michael / Alex,
Per your request, listed below is our Cost Proposal Summary to apply (Roll -On) the 96-inch Wetwell
Interior Coating at the Granite Precast Yard in Bellingham, WA. This cost will include Granite Precast
providing us an open space area in their yard to complete this work, and WCCL Systems' travel time,
overtime and vehicle charges to go to & from Bellingham. Price will also include Granite Precasts'
additional handling and moving these large 96-inch Wetwell Pieces in their yard prior to shipping.
Back-up documentation from WCCL Systems & Granite Precast, attached.
Summary of costs are as follows:
WCCL Systems (Travel & Overtime)
Granite Precast (Yard Space & Handling)
Misc. Plastic, Tarps & Cover
Allowable Mark -Up on Material
Allowable Mark -Up on Subs
6-Hours @ $225.00
$ 1,350.00
1-LS @ $1,000.00
$ 1,000.00
1-LS @ $200.00
$ 200.00
SUBTOTAL
$ 2,550.00
$1,200.00 @ 21 % $ 252.00
$1,350.00 @ 12% $ 162.00
TOTAL $ 2,964.00
• Due to the additional concrete cure time required prior to applying the Wasser
Aeroshield Coating, we request an additional 14-Working Day to complete this
added scope of work.
Page 1 of 2
Please note that Granite Precast can provide us an open space in their yard to apply this Wasser
Aeroshield Coating, however it will still not be in a controlled environment. WCCL Systems will look
for a dry -weather window and will provide tents, tarps and portable heaters during the completion of this
work. For your convenience, allowable contractor mark-up for Force Account has been added per
Section 1-09.6 of the 2018 WSDOT Standard Specifications. Total cost to the City of Renton for
completing this ADDED Scope of Work is $2,964.00, excluding sales tax.
Please issue us a Work Authorization and Change Order so that we can schedule & coordinate this work.
Should you have any questions or concerns, please contact me at (425) 777-7323.
Very truly yours,
"g`
Gordon Lee
Road Construction Northwest
Page 2 of 2
ca cr�Ar�iTE
Road Construction NW
Renton, Wa
Regarding interior coating of the 96" Wet Well interior coating
Granite Precast will offer an area to coat the interior of the wet well and offer the service of moving
the parts around for the coater fo $1000.
This will not be a covered area as we do not have that available.
The expectation is: This is a rolled on coating. Air Quality NW monitors our yard and if it is not rolled
on we will need to further evaluate how to get this done.
All sand blasting material and masking is picked up and disposed of.
Thankyou
Kai Johnson
Granite Precast
4030 Bakerview Spur Bellingham, WA 98226-360-671-2251 •1-800-808-2251 -Fax 360-671-0780
-- ,
Gordon Lee
From: WCCL Systems <wcclsystems@outlook.com>
Sent: Wednesday, October 17, 2018 9:54 AM
To: Gordon Lee
Subject: Re: 96" Interior coating
Hi Gordon,
Sorry for the delay, Marc has limited email access today.
The travel and mileage will b
6 hrs @ overtime rate of $225.00 per hr. = $1,350.00
Per the attachment from Granite, I don't think Marc will be needing the services for moving parts around but I
will get this confirmed.
Please let me know if you have any questions.
Thank You,
Gina
WCCL Systems LLC
3407 N 24th Street
Tacoma, WA 98406
Marc Valdes cell 253-606-4964
Gina Gepke office 253-219-5554
wccisystems@outlook.com
From: Gordon Lee <gordon@rcnw.com>
Sent: Tuesday, October 16, 2018 4:02 PM
To: WCCL Systems
Subject: FW: 96" Interior coating
Marc / Gina — Per my voice message, please get me a cost for your travel time & vehicle mileage to get to and
from Granite Precast's Yard in Bellingham. Please note the 96-inch Wetwell will require a Roll -On Application.
Very truly yours,
Gordon Lee