HomeMy WebLinkAboutRS_TIR__V7_181116_v1Prepared by: October 30, 2018 Anstey Engineering CIVIL ENGINEERING/CONSULTING 8627 NE 180th Street Bothell, Washington 98011 Phone: (206) 303-7639 Fax: (425) 658-9203 E-mail: benanstey@ansteyengineering.com Table of Contents Technical Information Report (TIR) Cover 1 Table of Contents 2 ⦁ Project Overview – Purpose ⦁ Existing Condition ⦁ Developed Condition ⦁ TIR Worksheet ⦁ Basin Map ⦁ Soil Map 1 ⦁ Site Map 2. Conditions and Requirements Core Requirements #1 Discharge at Natural Location 5 #2 Off-Site Analysis 5 #3 Flow Control 5 #4 Conveyance System 7 #5 Erosion and Sedimentation Control 7 #6 Maintenance and Operation 7 #7 Financial Guarantee and Liability 7 #8 Water Quality 8 #9 Flow Control BMPs Special Requirements 1-6 ⦁ Other Adopted Area Specific Requirements ⦁ Flood Hazard Area Delineation ⦁ Flood Protection Facilities ⦁ Source Controls ⦁ Oil Control ⦁ Aquifer Protection Area 3.Offsite Analysis Task 1 – Study Area Definition and Maps Task 2- Resource Review Task 3 – Drainage System description 4. Flow Control 4.1 Existing Site Hydrology Developed Site Hydrology Performance Standards Flow Control System 2 4.2 Water Quality 5. Conveyance System 6. Special Reports – See Geotech Reports by Cobalt GeoSciences 7. Other Permits 8. CSWPPP – See attached 9. Bond Quantity , Facility Summary & Declaration of Covenant 10. Operations and Maintenance 11. Conclusions Appendix King County iMap of Sensitive Areas 11 Figure AquaFilter Filtration System 12 Figure C.2.7.1.A Schematic Representation of Permeable Pavement 13 Figure City of Renton Std Plan 235.00 Typical Detention Tank 1 PROJECT OVERVIEW This storm drainage technical information report has been prepared to address the 2017 City of Renton site development and storm drainage requirements for the proposed new Church Building addition located at 3811 NE 21st St on Tax parcels #0423059237, and 307 at East side of Redmond Ave NE, South of NE 21st ST, between NE 21st St and NE 19st St in Renton, WA. The Legal Description is: POR OF E 1/2 OF E 1/2 OF NW 1/4 OF NE 1/4 OF SE 1/4 LY N OF S LN OF LOT 4 OF ROSE HAVEN PROD E in King County Washington. The proposed project is located at the South of NE 21st ST, Renton, WA 98056. The property is (2.49 Acre) 108,480 square feet in area. The property has existing development, 13,100sf Church building area and approximately 50,000sf impervious parking lot and walk ways. The rest of the property is covered with grass and trees. The North and East portion site is almost flat, South portion of the site has 3.5% +/- down slope toward south. The north portion of the site, existing church building and paved parking drains to the north to the NE 21st Street Drainage System. The existing gravel parking on the east is a pothole that infiltrates int o the ground. 3 The proposed project involves construction of a new 1,750 square foot building addition, and 21,815 square foot pervious parking extension and Frontage Improvements will be made to NE 21st Street to include new sidewalk curb and gutter. As part of frontage improvement, 23’ at North end, total 3755sf including 1295 impervious parking will be changed to ROW dedicated. 574sf existing walk way will be demolished to construct addition and new 322 sf walkway will be added. There is existing catch basin on North of site, which is connected to storm drainage system via 12” drain under street 3811 NE 21st St, drains toward west . Major portion of existing development on North and East section of site (parcels #0423059237 and 307) drains to the existing North CB. There is also existing catch basin on South West of site which is connected to drainage system on South side NE 19th St. Area from parcel # 0423059068 drains to South catch basin. The surface water from new impervious construction will be added to south catch basin which will flow sheet flow across the site to the existing drainage system in NE 19th Street. Impervious Surfaces : Existing Covered area Existing Church Building 11,176 sq.ft. Existing Asphalt Parking 39,762 sq.ft. Existing Walkway 10,788 sq.ft. Ex other pavement 733 sq. ft Total existing on site Impervious Area 62,919 sq.ft + Area in ROW 2,938.5 = 65,857.5sq ft Proposed new replaced impervious area Proposed Building 1,750 sq. ft Proposed walkway 322 sq. ft Existing Pvmt to landscape change to ROW (-) 1,294 sq. ft New Sidewalk in ROW = 665sf New Curb and gutter in ROW = 187lf = 280.5sq ft = increase in impervious area = 1,723.5 sq ft . New pervious asphalt 21,815sq. ft. Demo existing walk way (-) 574 sq. ft Total Impervious Area 64,914 sq. ft. 4 Target Impervious Surface = New Church Addition Footprint = 1,750 sq. ft. Pervious surface = Parking addition pervious asphalt = 21,815 sq. ft. As more than 7000 sq ft land disturbing activity but new impervious addition is less than 2000 sq ft, the project needs Large Lot Drainage review per 1.3.2 of the 2017 Renton SWDM. A site location and sensitive areas map can be seen in the Appendix. This map shows that the site is not located near sensitive areas. The site is larger than 22,000 sf so BMP’s will be used to the extent possible to control stormwater runoff. ⦁ Conditions and Requirements Summary The 9 core requirements will be addressed in this TIR: CORE REQUIREMENT #1 DISCHARGE AT THE NATURAL LOCATION The flows on this site for the building addition enter a detention tank, from which it continues to flow to the natural downhill flow path. The flows will drain to the NE 21st Street and NE 19th Street drainage systems or be kept on site they are now. Parking addition will be pervious asphalt pavement, the flows will also enter the detention tank. To divert flow from the gravel parking area to the 19th Street Drainage System should require a Drainage Adjustment as it will be a diversion. CORE REQUIREMENT #2 OFFSITE ANALYSIS This is an urban area and the properties around are small and fully developed. There are no significant on or off site flows on this property. No downstream drainage problems were observed. The existing paved surfaces on this site drain to the piped drainage systems in NE 21st Street. The gravel parking area ponds on site. See Level One Downstream Analysis in section 3 CORE REQUIREMENT #3 FLOW CONTROL Proposed Site and Drainage Part A: Existing Site Hydrology The lot is developed, the storm water runoff flows from existing roof and parking lot to existing catch basin and drainage system on North of site and into the NE 21st Street Drainage system. South side of site has grass and trees; it is gently sloped with slope of 3.5%+/- down to south. The storm water runoff from the South side currently disperses across the site toward South and flows to existing catch basin and drainage system under NE 19th St of South side. There is no evidence of any other on-site flows going off-site. The site does not receive any significant off-site flows from the adjacent properties. The soil is glacial till. The existing gravel 5 parking on the east of the site infiltrates on site. Part B: Developed Site Hydrology For the parking addition a 305LF 72" detention tank, outletting to NE 19th St, will used per section 5.1.2 of RSWDM 2017. The existing area to be paved is currently mostly gravel so there will be no significant change of condition. When the 1,750 sf addition to the building is constructed it will also use the detention tank. Part C: Performance Standards Flow control BMPs are used on this Large Lot to control storm water from roof by using a detention tank per 5.1.2 for the parking area and building addition. All BMPs were found to be infeasible due to site constraints. Pervious pavement will be used for the new parking area. Part D: Flow Control System The Erosion and Sediment Control Plans along with the Site Plans include the locations of the flow control systems. In addition, cross-sections of the flow control BMPs can be found in the Appendix. BMPs were analyzed for their practicality and pervious pavement and a detention tank for the parking area and building addition was selected as the only practical BMP. See Section 9 BMP Analysis Part E: Water Quality System The site will have more than 5,000sf of pollution new pollution generating surface,which will be treated at the end of the detention tank by an AquaFilter system. This is not a high use site. No additional facilities will be necessary. Impervious Surfaces Impervious Surfaces Proposed Addition 1,750 sq.ft. Total Impervious Area 1,750 sq.ft. Since this lot is larger than 22,000 square feet, it is subject to the Large Lot BMP Requirements in Appendix C - C.1.3.2of the 2017 Renton Surface Water Design Manual (SWDM) which specify the target impervious surface is equivalent to the roof area of addition. 6 Target Impervious Surface = Roof area addition = 1,750 sq. ft . Pervious Pavement = 21,815 sq. ft. See section 9 for BMP analysis CORE REQUIREMENT #4 CONVEYANCE SYSTEM Not Applicable As the flows on this site are totally dispersed and are minimal there is no conveyance systems needed. Flows from the pervious parking area and building addition will be conveyed through the detention tank, no additional conveyance will be necessary. Core Requirement #5 EROSION AND SEDIMENT CONTROL Temporary ESC measures will be required as there will be disturbance of the soil to construct the additional parking and building addition, and clearing of the site. All of the flows from the driveway and house will flow onto the lot so no adjacent properties will be affected. A construction entrance should be provided at a minimum. No special requirements are needed In order to prevent erosion and trap sediment within t he project site, the following BMPs will be used approximately as shown on the ESC plan: ⦁ Clearing limits will be marked by fencing or other means on the ground. ⦁ Extra excavated soil will be removed from the site or spread on site. ⦁ A rocked construction entrance will be placed at the location of the driveway throughout construction. ⦁ Runoff will not be allowed to concentrate and no water will be allowed to point discharge. ⦁ Mulch will be spread over all cleared areas of the sit e when they are not being worked. Mulch will consist of air-dried straw and chipped vegetation. CORE REQUIREMENT #6 MAINTENANCE AND OPERATION The Pervious Pavement will require little maintenance. See attached Maintenance requirements. This is a private system that will be maintained by the property owner. CORE REQUIREMENT #7 FINANCIAL GUARANTEES AND LIABILITY – Not Applicable 7 The property owner will be responsible to insure that the project is constructed to the approved plans and that the drainage does not cause any problems. CORE REQUIREMENT #8 WATER QUALITY – As less more 5,000sf of new pollution generating impervious area will be created water quality treatment is necessary. The Pervious pavement is self treating by infiltration and an AquaFilter will be provided near the outlet of the detention system to treat any runoff. Core Requirement #9 FLOW CONTROL BMPS PER C.1.3.2 for Large Lot BMPs will be used to the extent feasible to control Stormwater on this site per C.1.3.2. . The only BMP practical for this large lot is a detention tank per 5.1.2 for the additional previous parking area. The roof downspouts will be routed to the detention tank. Pervious asphalt pavement will be used as per section 2.7 and will also use the detention tank. Flow control BMPs are used on this site to control stormwater. See discussion below: C.2.1 Full Dispersion – Roof area is more than 700 sf. A 100 foot vegetated flow path is not available, therefore, full dispersion is not feasible. C.2.2 Full Infiltration – Not feasible as the soils are till per the Cobalt GeoSciences report dated January 19, 2018 C.2.3 Limited Infiltration – Not feasible due to high winter ground water table and till soil per the Cobalt GeoSciences report dated January 19, 2018 C.2.6 Bioretention – Not feasible as there is not a suitable area due to surfacing, slopes and setbacks. C.2.7 Permeable Pavement – Permeable Asphalt Pavement is proposed for proposed addition of parking area. This is light duty overflow parking for the church so pervious asphalt pavement should work adequately. The area is gravel parking now. Underneath the parking area will be a 305 LF 72" detention tank. See WWHM printout. See Cobalt Geotechnical Report on Soils dated May 15, 2018 with letter of June 26, 2018 did 3 holes and found goundwater between 3.5 and 8 feet below the ground. As the proposed pervious pavement will be placed on top of the existing ground at the lower end of the parking lot, the 1 foot minimum separation required for pervious pavement will be maintained. Per C.1.3.2 Pervious Pavement is required to be used if possible and we have adequately permeable soil and an adequate amount of permeable soil above the ground water table which are the only two applicable criteria. A control manhole and detention tank are provided for flow control. C.2.4 Basic Dispersion – There is not the minimum 50 feet required space to implement splash blocks and rock pads. In addition, gravel filled trenches and sheet flow are not feasible due to the inability to achieve 25 feet of vegetated flow path. 8 However, since a detention tank is already needed for the parking area, the building addition will utilize the detention tank. Special Requirements: ⦁ Other Adopted Area Specific Requirements – none known ⦁ Flood Hazard Are Delineation – site is not in a flood plane ⦁ Flood Protection Facilities – No Flood Protection Facilities are required or proposed ⦁ Source Control-The site is a commercial site but we are not adding any impervious pollution generating surface so no source control is required. ⦁ Oil Control- This is not a high use site so oil control is not required ⦁ Aquifer Protection Area- This site is not in an Aquifer protection area. ⦁ Off-Site Analysis Offsite Analysis – Level One Downstream Analysis Task 1. Study Area Definition and Maps The properties to the north of this site are small single family residences, and do not discharge any significant amount of runoff onto this site. 21st st has curbs and drainage system and Frontage of site will be developed to construct curbs and walk way which does not drain any significant run off to site. South side NE 19th St and properties are lower than site, do not discharge any significant amount of runoff onto this site. East and West side properties small single family residences and fully developed, do not discharge any significant amount of runoff onto this site. Task 2: Resource Review Using the King County iMap interactive tool, it was found that there are no immediate critical areas upstream or downstream of the property. Task 3: Field Inspection There are no reported problems to be investigated. The amount of space and soil types present on the property clearly support the flow control BMPs being 9 implemented. There will not be any destruction of aquatic habitat on-site or downstream. The Site was visited on October 11, 2017 and a 1/4 mile downstream investigation was made. As there are no signs of surface flow no problems were identified. The piped drainage systems flow west. Task 4: Drainage System Description and Problem Descriptions For this site, permeable pavement with a detention t ank will be used. The building addition will also use the detent ion tank. Detention of the stormwater from the new addition using the tank will prevent any flooding problems on-site or downstream. NE 21st Street and NE 19th Street both have piped drainage systems that appear to be functioning properly. ⦁ There are no other significant on or off-site flows. The existing church and parking drain to on-site catch basins which drain to the NE 21st Street Drainage System. Task 5: Mitigation of Existing or Potential Problems There are no known existing or potential drainage problems and / or water quality problems. 4 Flow Control ⦁ Existing Hydrology –The site is currently developed with the church building and asphalt and gravel parking. The Church building and asphalt parking drain to an existing catch basin in the parking lot near NE 21st Street which drains to the NE 21st Street piped drainage system. The gravel parking area infiltrates into the ground. Developed Site Hydrology-The existing church building and asphalt parking will continue to drain as they do now. The new 1,750sf Church addition and new paved parking will drain to a detention tank which will discharge to the NE 19th Street storm system. ⦁ Conveyance No special conveyance design is required as a 6” pvc pipe is adequate to take the roof water to the detention tank ⦁ Special Reports – See Geotech Report by Cobalt GeoSciences ⦁ Other Permits – A building Permit will be required. A ROW permit will be required for frontage improvement work in the NE 21st Street ROW. 10 ⦁ CSWPPP – See attached ⦁ Bond Quantity, Facility Summary and Declaration of Covenant – See attached ⦁ Operations and Maintenance- Operations and Maintenance instructions are attached ⦁ Conclusions – The Church Addition, pervious parking and frontage improvements on NE 21st Street can be installed per City standards and without changing the character of the site. Appendix: Imap 11 12 13 14 15