HomeMy WebLinkAboutAdden 1 � CAG-17-075,Adden#1-18
Washington State
�� Department of Transportation
Supplemental Agreement Organization and Atldress
Number 1 BergerABAM Inc.
Original Agreement Number 33301 Ninth Avenue S., Suite 300
Federal Way,WA 98003
CAG-17-075
Phone: 206-431-2300
Project Number Execution Date Completion Date
TED4003844 5/25/2017 12/31/2019
Project Title New Maximum Amount Payable
N 27th Place Bridge Scour Repair $127,218.00
Description of Work
Extend the contract completion date.Include additional scope and budget to modify the design of the scour repairs as a result of the
deletion of the sheet pile wa112 from the construction contract due to difficult pile driving conditions. Increase budget for
construction management and inspection for added working days to remove sheet pile obstructions and other changes. Increase
budget for inspection for extended week day working hours and weekend work in order to reopen street as quickly as possible after
the labor dispute between the IUOE 302 and AGC of Washington delayed the street reopening for several weeks.
The Local Agency of Citv ofRenton
desires to supplement the agreement entered in to with BergerABA1�t�n�.
and executed on 5/25/17 and identified as Agreement No. CAG-1�-o�s
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
The Scope of Work of the Original Agreement is supplemented to include the attached Exhibit A-1
��
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
f01'COt71p12tI0tl Of th2 WOI"k t0 �2ad: Change contract completion date from December 31,2018 to December 31,2019
���
Section V, PAYMENT, shall be amended as follows:
See attached Exhibit"A"and Exhibit D-L The maximum amount payable is increased by$27,534 from$99,684 to$127,218
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
spaces below and return to this office for final action.
gy: Ber erABAM gy: Gregg Zimmerman,Public Works Administrator
Cf!/"'�+� '
Consultant Signa ure � Ap i A t nty Signature
�2.. �l'�L� �,�I �
�e
DOT Form 140-063
Revised 09/2005
Exhibit "A"
Summary of Payments
Basic Supplement#1 Total
Agreement
Direct Salary Cost $2g,297 $9,493 $37,790
Overhead $49,291 $14,615 $63,906
(Including Payroll Additives)
Direct Non-Salary Costs $13,608 $578 $14,186
Fixed Fee $g,488 $2,848 $11,336
Total $99,684 $27,534 $127,218
DOT Form 140-063
Revised 09/2005
EXHIBIT A-1
MODIFIES EXHIBIT A OF THE ORIGINAL AGREEMENT
SCOPE OF WORK
SUPPLEMENTAL AGREEMENT N0. 1
AGENCY: CIN OF RENTON
CONSULTANT: BERGERABAM INC.
CONTRACT: CAG-17-075
PROJECT: N 27TH PLACE BRIDGE SCOUR REPAIR
SUPPLEMENT DESCRIPTION
During the course of construction, working days were added to the construction contract for
removal of sheet pile obstructions and other changes. The ariginal contract scope and budget
was based on the original number of working days in the construction contract. To provide
services for the working days added to the construction contract, additional budget for
Construction Administration and Inspection (CA&I) services is necessary.
The International Union of Operating Engineers (IUOE)loca1302 had a labor dispute with the
Associated General Contractors (AGC) of Washington. IUOE 302 went on strike on August 21,
2018 and went back to work on September 7, 2018. This delayed the reopening of N 27th Place
by several weeks. In order to reopen the street as quickly as possible after the labor dispute
ended, the contractor worked extended week day warking hours and weekends. To provide
inspection services during the extended work hours, additional budget for CA&I services is
necessary.
During sheet pile installation, driving conditions prevented the installation of Wall 2 per the
construction contract. As a result,Wa112 was deleted from the construction contract and the
design of the scour repairs was revised accordingly. To provide for the revised design of the
scour repairs, additional budget for Design Construction Support Services (DCSS)is necessary.
TASK 1.0 CONSTRUCTION ADMINISTRATION AND INSPECTION (CA&I) SERVICES
Task 1.2 Construction Administration and Inspection
No change to the original scope of work for this task.The purpose of this supplement is to
provide additional budget for the scope of this task, for the reasons stated above. Refer to
E�chibit D-1 for an estimate of the budget required to provide CA&I services for the working
days added to the construction contract and extended working hours.
City of Renton BergerABAM,A19.0008.00
North 27th Place Bridge Scour Repair Project December 2018
Renton,Washington Exhibit A-1 Page 1 of 2
TASK 2.0 DESIGN CONSTRUCTION SUPPORT SERVICES (DCSS)
Task 2.3 Change Orders
Task 2.3.1 Elimination of wall 2 and revise design of scour repairs
This is a new subtask
The CONSULTANT shall provide revised engineering drawings that show the proposed design
revisions resulHng from the elimination of sheet pile Wa112. These drawing revisions include,
but are not limited to, the following.
• Addition of a reinforced, cast-in-place, concrete cutoff wall at the downstream end of the
existing culvert
• Addition of a log weir at the concrete cutoff wall
• Addition of a log weir at the outlet of the culvert, downstream from the concrete cutoff wall
• Revised grading plans for the placement of light loose rip-rap and streambed
sediment/cobble mixture, resulting from the elimination of sheet pile Wa112
• Location/placement of additional one-man boulders inside the culvert
The CONSULTANT shall provide revised material quantities resulting from the changes
described above.
Refer to Exhibit D-1 for an estimate of the budget required to provide the services described in
this new subtask.
City of Renton BergerABAM,A19.0008.00
North 27th Place Bridge Scour Repair Project December 2018
Renton,Washington Exhiblt A-1 Page 2 of 2
EXHIBIT D-1 -CONSULTANT FEE DETERMINATION Supplement No 1 -CA plus DCSS Costs
N 27TH PLACE CULVERT SCOUR REPAIR PROJECT 1217/2o1s
Construction Administration and Inspection (CA&I) Task 1.2
DIRECT SALARY COSTS(DSC)for BergerABAM
Personnel Hours Rate Cost
1 Project Manager 8 X $48.77 = $ 390
2 Resident Engineer 24 X $61.32 = $ 1,472
3 Project Inspector 80 X $41.66 = $ 3,333
4 Document Control 40 X $41.03 = $ 1,641
BERGER/ABAM Hours,TOTAL 152 Subtotal Direct Salary Costs(DSC)_ $ 6,836
Salary Escalation-Estimated Salary Escalation Costs are included in above rates $ -
Overhead(OH) 153.96% of(DSC+SE)_ $ 10,524
Fixed Fee(FF) 30.00% of(DSC+SE)= 2,051
TOTAL SALARY COSTS(DSC+SE+pH+FF)_ $ 19,411
SUBCONSULTANTS
Mayes Testing Engineers Inc.,a Terracon Company(Task 3.0) $ -
TOTAL SUBCONSULTANTS- CA8�1= $ -
DIRECT NONSALARY COSTS(DNSC)
RT/Mo RT Miles Mileage Rate
PM Mileage 2 52 $ 0.540 $ 56
RE Mileage 5 52 $ 0.540 $ 140
PI Mileage 10 52 $ 0.540 $ 281
DC Mileage 0 52 $ 0.540 $ -
TOTAL REIMBURSABLE EXPENSES (DNSC) _ $ 477
TOTAL CA&I FEE (DSC+SE+OH + FF+ DNSC)_ $ 19,888
DESIGN CONSTRUCTION SUPPORT SERVICES (DCSS) COSTS Subtask 2.3.1
BergerABAM Design Change $ 7,645
SUBCONSULTANTS
PanGeo $ -
Watershed $ -
TOTAL ESTIMATED DESIGN CONSTRUCTION SUPPORT FEES= $ 7,645
TOTAL ESTIMATED AMOUNT FOR CAB�I t DCSS SERVICES FOR SUPPLEMENT 1 = $ 27,534
Page 1 of 2
EXHIBIT D-1 -CONSULTANT FEE DETERMINATION Supplement No 1 -CA plus DCSS Costs
N 27TH PLACE CULVERT SCOUR REPAIR PROJECT �2/�/20�8
DIRECT SALARY COSTS(DSC)
Personnel Hours Rate Cost
1 Project Manager GB 2.0 X $72.02 = $ 144
2 Project Engineer ST 0 X $78.41 = $ -
3 Civil Engineer BN 30 X $38.22 = $ 1,147
4 Structural Engineer GB 4 X $72.02 = $ 288
5 Designer-CADD LC 24 X $41.20 = $ 989
6 Admin,Clerical 2 X $44.81 = $ 90
Total Hours 62 Subtotal Direct Salary Costs(DSC)_ $ 2,657
Salary Escalation(SE)= 0% of DSC= $ -
Subtotal(DSC+SE)_ $ 2,657
Overhead(OH) 153.96% of(DSC+SE)_ $ 4,091
Fixed Fee(FF) 30.00% of(DSC+SE)_ $ 797
TOTAL SALARY COSTS(DSC+SE+OH+FF)_ $ 7,545
DIRECT NONSALARY COSTS(DNSC)
Mileage 104 miles @ $ 0.540 $ 56
Inspection EquipmentEquipment
Copies $ 44
TOTAL REIMBURSABLE EXPENSES(DNSC)_ $ 100
TOTAL AUTHORIZED AMOUNT = $ 7,645
PAYMENT
Se����es w�n be a��e o„ a �SC ,.,wuPrP� eq�aico 2.840