Loading...
HomeMy WebLinkAboutCO 8 CAG-18-062, CO #8-19 CITY OF RENTON Community Services Department CONTRACT CHANGE ORDER AGREEMENT 4.10.2019 CONTRACT: City of Renton CAG-18-062 Coulon Beach Park Structural Repairs CONTRACTOR: Quigg Brothers,Inc. CHANGE ORDER: No.8 SUMMARY OF PROPOSED CHANGE: Reason/Justification: Additional Work to Contract: Extension of contract time to complete scope of work. DESCRIPTION: Item Qty. Description Unit Price Amount No. w/WSST 1 1 Contract Time Extension $ - $ - Total this Change Order: $ - ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT AMOUNT(W/WSST) AMOUNT THIS ORDER(W/',WSST) TOTAL AFTER CHANGE $ 2,376,000.00 $ 2,508,124.56 $ - $ 2,508,124.56 Additional Calendar Days: (31)Calendar Days Extension of Time.Completion Date Is May 31,2019. The payment specified and agreed to in this change order includes every claim by the contractor for any extra payment with respect to the work described in this change order. The work covered by this change order must be performed under the same terms and conditions as that included in the original agreement. All of the other terms of the original agreement remain in effect. SIGNATURES: � 141 Contractor: Date: <<) `C( Project Manager: /4216 Date 4(i/ Zf/ Approved By: Ilie/ �( 7 se Date: 4-,`` ` ` 4 munlry Services Administ r)