HomeMy WebLinkAboutIDRFR9-11-09 IDR Sheet of Sheets Final Record Book Page Contract 7624 Day Friday Date 9/11/09 WSDOT Exchange Property Conveyor belt shut-down, today due to too much material on site and construction of new belt extension.. Thunder Hill Creek and Mine 7:00 – Arrived on site, NB/I-405 shoulder, below the WSDOT Exchange Property, where Malcolm Drilling crew and drill rig were also on site. Wayne Broughton, Malcolm Drilling Superintendent, Joel Theodore, CH2Hill, and Matt, Merlino, Foreman. 7:30 – Drill rig used steel casing to clean sides and plumb # 2 shaft. 8:15 – Lisa Hodgeson, Chad Brown, Jeff Lavinder on site. Drill rig used an auger to clean debris from the bottom of the shaft. Water below was free flowing. 9:00 – Malcolm crew continued to work on plumbing the sides of the shaft. 9:45 - Pulled steel casing from well #2 and cut window in lower side of the casing. 10:30 – Used auger to clean sump at bottom of well #2 and replaced debris with drain rock. DOT Form 422-004A EF Inspector Revised 1/94