Loading...
HomeMy WebLinkAboutIDRFR9-28-09 IDR Sheet of Sheets Final Record Book Page Contract 7624 Day Monday Date 9/28/09 Benson Road Bridge Pier 1 and Pier 2 - Soil Nails 9:00 – Wayne Broughton and Malcolm Drilling crew on site to continue drilling and placing a second row of soil nails along Benson Road. Al Emter and Tim of Mayes Engineering, on site to monitor installation process. 10:30 – Finished placing and grouting 35 ft. soil nails in Wall 1 and 8 ft. nails in Wall 2. Started installing steel mesh for the second level. 12:30 – Stoneway truck on site to start placing shotcrete against Wall 1. A sample block was made for later cores. WSDOT Exchange Property Terra-Dynamics crew on site to place compost on side slopes. Two side-dump trucks placed material. 11:00 – Talked to Dan Quehl about dust cause by increasing winds that were blowing into residential across Cedar St. He talked to Merlino about spraying water on stockpiles and access road. DOT Form 422-004A EF Inspector Revised 1/94