IDR Sheet of Sheets
Final Record Book Page
Contract 7624
Day Monday Date 9/28/09
Benson Road Bridge
Pier 1 and Pier 2 - Soil Nails
9:00 – Wayne Broughton and Malcolm Drilling crew on site to continue drilling and
placing a second row of soil nails along Benson Road. Al Emter and Tim of Mayes
Engineering, on site to monitor installation process.
10:30 – Finished placing and grouting 35 ft. soil nails in Wall 1 and 8 ft. nails in Wall 2.
Started installing steel mesh for the second level.
12:30 – Stoneway truck on site to start placing shotcrete against Wall 1. A sample block
was made for later cores.
WSDOT Exchange Property
Terra-Dynamics crew on site to place compost on side slopes. Two side-dump trucks
placed material.
11:00 – Talked to Dan Quehl about dust cause by increasing winds that were blowing
into residential across Cedar St. He talked to Merlino about spraying water on stockpiles
and access road.
DOT Form 422-004A EF Inspector