HomeMy WebLinkAboutIDRFR9-29-09
IDR Sheet of Sheets
Final Record Book Page
Contract 7624
Day Tuesday Date 9/29/09
Benson Road Bridge
Pier 1 and Pier 2 – Shoring
Malcolm Drilling crew not on site, today.
Melino crew excavated for level 3 soil nail placement at Pier 2
Soil nail wall finished at Pier 1. Merlino crew removed south access road and excavate
Pier 1.
WSDOT Exchange Property
Terra-Dynamics crew on site to place compost on side slopes. Two side-dump trucks
placed material. Dan Quehl, Mayes Engineering, on site.
City Transfer crew continued to place soil and geogrid at Elev. 215. Track hoe,
earthmover, and dozer transferred soil delivered by conveyor belt to the reinforced slope.
DOT Form 422-004A EF Inspector
Revised 1/94