HomeMy WebLinkAboutIDRFR9-3-09 IDR Sheet of Sheets Final Record Book Page Contract 7624 Day Thursday Date 9/3/09 WSDOT Exchange Property City Transfer crew continued placing imported soil for the reinforced soil slope. Their conveyor belt moved native soils from the Rolling Hills excavation to hillside where a track hoe and earth mover placed material between layers of geogrid. A roller compacted this material. This work was done at Elev. 177 ft. and between Sta. 11+75 to 13+00. 9:00 – Dan Quehl, Mayes Inspector on site. He informed me that Tom Robinson was taking samples of the geogrid (SF 55 and SF 20) to Olympia for testing. Roch Player, CDB on site. Dan said last night’s rain helped compaction by raising moisture to the optimal level. 9:30 – Ken Viren, WSDOT on site to test compaction on lift at Elev. 177 ft. Dan and Ken said both tests passed. Benson Hill Road Gary Merlino crew continued excavation of the hillside east of the roadway and dumping it on the west side. Two flaggers were used for traffic control. Traffic, on both north and southbound lanes, was stopped for several minutes to place material. After noon, this material was transported to the conveyor belt. 2:00 - Traffic control was removed from Benson Road. Rolling Hills A dozer and track hoe continued to excavate to hillside north of the Benson Hill Bridge and along the northbound lanes. Native soils were loaded onto a conveyor belt to the WSDOT Exchange Property. DOT Form 422-004A EF Inspector Revised 1/94